Defense Infrastructure: Actions Taken to Improve the Management
of Utility Privatization, but Some Concerns Remain (05-SEP-06,
GAO-06-914).
Department of Defense (DOD) installations have about 2,600
electric, water, wastewater, and natural gas utility systems
valued at about $50 billion. In 1997, DOD decided that
privatization was the preferred method for improving utility
systems, and Congress approved legislative authority for
privatizing DOD's utility systems with Public Law No. 105-85. DOD
estimates that some utility privatization contracts will cost
over $100 million. In a May 2005 report, GAO identified several
management weaknesses in DOD's implementation of the program. The
Fiscal Year 2006 National Defense Authorization Act required GAO
to evaluate and report on changes to the utility privatization
program since May 2005. Accordingly, this report updates the
status of the program and discusses the effect of DOD's changes
on the concerns noted last year. To conduct this review, GAO
summarized program status and costs, assessed DOD's changes to
program guidance and in other areas, and reviewed the services'
implementation of the changes.
-------------------------Indexing Terms-------------------------
REPORTNUM: GAO-06-914
ACCNO: A60206
TITLE: Defense Infrastructure: Actions Taken to Improve the
Management of Utility Privatization, but Some Concerns Remain
DATE: 09/05/2006
SUBJECT: Contract oversight
Defense budgets
Energy costs
Military budgets
Privatization
Program evaluation
Program management
Electric utilities
Wastewater management
Economic analysis
******************************************************************
** This file contains an ASCII representation of the text of a **
** GAO Product. **
** **
** No attempt has been made to display graphic images, although **
** figure captions are reproduced. Tables are included, but **
** may not resemble those in the printed version. **
** **
** Please see the PDF (Portable Document Format) file, when **
** available, for a complete electronic file of the printed **
** document's contents. **
** **
******************************************************************
GAO-06-914
* Results in Brief
* Background
* DOD Made Utility Privatization a Department Policy
* Implementation Goals Reset and Program Guidance Revised
* GAO Report Identified Weaknesses in Program Implementation
* Program Legislative Authority Modified
* DOD's Response to GAO's Report and Modifications to the Prog
* Utility Privatization Milestones Have Slipped and Implementa
* Services Did Not Meet Program Implementation Milestone
* Services Have Awarded Contracts for a Fraction of the Total
* Program Delays Have Resulted in Increased Implementation Cos
* Services Have Estimated the Number and Cost of Potential Pri
* DOD's Changes to Improve Utility Privatization Implementatio
* DOD Has Taken Steps to Improve the Reliability of Project Ec
* DOD Has Taken Steps to Address Some Funding Issues but Conce
* Utility Costs Increase with Privatization
* Funds Not Programmed for All Potential Utility Privatization
* Air Force May Not Award Some Additional Privatization Projec
* DOD Directed Actions to Improve Utility Privatization Contra
* DOD Has Taken Steps to Address Oversight Concerns
* Some Contract Oversight Concerns Identified at the Four Inst
* Containing Utility Privatization Contract Cost Growth May Be
* DOD Continues to Prefer Permanent Conveyance but Has Taken S
* Cost Growth in Utility Privatization Contracts May Become a
* DOD Has Not Made Changes to Provide More Realistic Savings E
* Changes in Legislative Authority and DOD's Implementation of
* Conclusions
* Recommendations for Executive Action
* Agency Comments and Our Evaluation
* Appendix I: Scope and Methodology
* Appendix II: Comments from the Department of Defense
* GAO's Response to the Department of Defense's Comments
* Appendix III: GAO Contact and Staff Acknowledgments
* GAO Contact
* Acknowledgments
* Order by Mail or Phone
Report to Congressional Committees
United States Government Accountability Office
GAO
September 2006
DEFENSE INFRASTRUCTURE
Actions Taken to Improve the Management of Utility Privatization, but Some
Concerns Remain
GAO-06-914
Contents
Letter 1
Results in Brief 3
Background 6
Utility Privatization Milestones Have Slipped and Implementation Costs
Continue to Climb 11
DOD's Changes to Improve Utility Privatization Implementation Have
Addressed Many Areas but Have Not Eliminated All Program Concerns 14
Conclusions 32
Recommendations for Executive Action 33
Agency Comments and Our Evaluation 34
Appendix I Scope and Methodology 37
Appendix II Comments from the Department of Defense 39
Appendix III GAO Contact and Staff Acknowledgments 47
Tables
Table 1: Percentage of Systems with Privatization or Exemption Decision
and Estimated Program Completion Date 12
Table 2: Status of the Utility Privatization Program as of March 31, 2006
12
Table 3: Implementation Costs for the Utility Privatization Program 13
Table 4: Potential Additional Privatization Contracts and Associated Costs
14
Table 5: Service Estimates of Potential Utility Privatization Program
Funding Shortfall 20
Table 6: DOD's Estimated Cost Avoidance from Utility Privatization 29
This is a work of the U.S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed in
its entirety without further permission from GAO. However, because this
work may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this material
separately.
United States Government Accountability Office
Washington, DC 20548
September 5, 2006
Congressional Committees
Department of Defense (DOD) installations have about 2,600 electric,
water, wastewater, and natural gas utility systems valued at about $50
billion. These systems consist of the equipment, fixtures, pipes, wires,
and other structures used in the distribution of electric power and
natural gas, the treatment and distribution of water, and the collection
and treatment of wastewater. According to DOD officials, many of these
systems have become unreliable and are in need of major improvements. To
address this issue, DOD decided in 1997 that utility privatization was the
preferred method for improving utility systems and services because
privatization would allow installations to benefit from private sector
financing and efficiencies. With private sector financing, installations
could immediately obtain major upgrades to their utility systems and pay
for these improvements over time. Thus, utility improvements could be
achieved without going through the traditional budget justification and
funding process. Under DOD's program, utility privatization normally
involves two transactions with the successful contractor-the conveyance of
the utility system infrastructure and the acquisition of utility services
for upgrades, operations, and maintenance under a long-term contract of up
to 50 years. DOD estimates that some privatization contracts will cost
more than $100 million over the contract time frames.
To institute the program, at DOD's request, Congress approved legislative
authority in 1997 for privatizing utility systems at military
installations.1 The authority requires that the military services meet a
number of conditions to privatize a system including, in part, the
following condition: the services must demonstrate through an economic
analysis that privatization of a system would reduce the government's
long-term costs for utility services. DOD's program guidance permits the
services to exempt systems from privatization when long-term costs will
not be reduced or for unique security reasons.
1National Defense Authorization Act for Fiscal Year 1998, Pub. L. No.
105-85, S: 2812 (1997).
In May 2005, we issued a report that identified management weaknesses in
DOD's implementation of the utility privatization program.2 The report
noted a number of concerns, such as the reliability of the economic
analyses associated with privatization decisions and the adequacy of
contract oversight, and made several recommendations to DOD to improve the
guidance and procedures used to implement and oversee the utility
privatization program. Although DOD initially disagreed with the report's
findings and recommendations, after further review of the report, the
department subsequently reported to Congress that it generally agreed with
our findings and recommendations and decided to issue new guidance on
November 2, 2005, to address the key issues in our prior report.3 Among
other things, this guidance required the services to complete remaining
evaluations of utility system potential for privatization in a timely and
efficient manner, perform an independent review of the economic analyses
supporting proposed projects, consider and plan for increased costs for
utility services resulting from potential privatization projects, and take
steps designed to improve the administration and oversight of awarded
privatization projects. Even before DOD issued the new guidance, the
services had implemented several program improvements including the
requirement for independent reviews of project economic analyses.
In January 2006, the National Defense Authorization Act for Fiscal Year
20064 made several modifications to the legislative authority for the
utility privatization program, restricted the number of utility systems
that DOD could privatize during fiscal years 2006 and 2007, and required
the Secretary of Defense to submit a report to congressional defense
committees by April 1, 2006, addressing program issues and many of the
concerns noted in our May 2005 report. The act also directed us to
evaluate and report on the changes made by DOD to the program since May
2005 and their effects. Accordingly, this report (1) updates the status of
the utility privatization program, and (2) discusses the effect of DOD's
changes on the program management and oversight concerns noted in our May
2005 report.
2GAO, Defense Infrastructure: Management Issues Requiring Attention in
Utility Privatization, GAO-05-433 (Washington, D.C.: May 12, 2005).
3DOD, Under Secretary of Defense, Memorandum for Secretaries of the
Military Departments and Director, Defense Logistics Agency, Subject:
Supplemental Guidance for the Utilities Privatization Program (Washington,
D.C.: Nov. 2, 2005).
4National Defense Authorization Act for Fiscal Year 2006, Pub. L. No.
109-163, S: 2823 (2006) (codified as amended at 10 U.S.C. S: 2688).
To address these objectives, we summarized program implementation status
and costs and compared the status to DOD's past and current goals and
milestones. To determine the effect of DOD's changes on the program
management and oversight concerns noted in our prior report, we
interviewed DOD and service officials and reviewed pertinent policies,
guidance, memorandums, and reports to document the changes made, and we
compared those changes with our previously identified concerns to assess
whether the issues had been fully addressed. Further, we reviewed the
reliability of the economic analyses supporting 10 privatization projects
that were awarded after our prior report and had been subjected to the
services' new independent review process. We also visited four
installations to assess contract administration and oversight issues and
reviewed contract price changes in six ongoing utility privatization
contracts. Although we generally relied on program status data provided by
the services, we confirmed the status data for five utility privatization
projects and did not otherwise test the reliability of the data.
We conducted our review from March through July 2006 in accordance with
generally accepted government auditing standards. A more detailed
description of our scope and methodology is included in appendix I.
Results in Brief
DOD's progress in implementing the utility privatization program has been
slower than expected, and implementation costs have continued to climb.
Since our previous report, the estimated program completion date has
slipped from the department's target of September 2005 to September 2011.
DOD officials have attributed delays in program implementation to
privatization evaluation, solicitation, and contracting processes that
were more complex and time-consuming than originally anticipated. Service
officials also stated that additional delays resulted from the services'
decision to suspend and reassess the management of the program between
October 2005 and March 2006. The officials stated that the suspension
allowed DOD and the services time to review concerns noted in our prior
report, develop and issue supplemental guidance for the program, and
implement program changes necessitated by modifications in the program's
legislative authority. Between May 31, 2005, and September 30, 2005, the
services privatized 14 utility systems under the legislative authority for
the program, bringing the total number of awarded projects to 81. However,
the services have awarded no projects since September 2005 and, therefore,
no projects have been awarded since DOD issued supplemental program
guidance in November 2005. With program delays, the services' total
estimated program implementation costs through fiscal year 2006 have
increased from $268 million to $285 million and additional amounts will be
required before the program is projected to be completed in 2011. Program
delays also caused the Defense Energy Support Center to cancel
solicitations to privatize 42 Army utility systems in May 2006. These
solicitations had been closed from 1 to 4 years with no award decision and
there were concerns that conditions, such as the accuracy of the inventory
and needed improvements, had changed or might change before an award
decision would be made. The Army plans to resolicit these systems over the
next few years.
DOD has issued new program guidance and required changes in program
procedures to improve the management and oversight of the utility
privatization program since our May 2005 report. For example, DOD
implemented a requirement for an independent review of economic analyses
for proposed privatization projects and has imposed greater emphasis on
contract oversight. If fully implemented, the changes should result in
more reliable economic analyses supporting proposed privatization
projects, improved budgetary consideration of increased utility costs from
privatization, enhanced oversight of privatization contracts, and reduced
instances where contractors recover more than the amounts they paid as the
fair market value for system conveyances. However, we noted a number of
limitations in implementation of the new procedures. Moreover, a number of
concerns noted in our prior report remain, at least to some degree,
because DOD's changes to address some issues were not implemented
effectively, some changes were not sufficient to fully eliminate some
concerns, and DOD did not make changes to address some concerns. For
example:
o First, although DOD made changes to improve the reliability of
project economic analyses by requiring independent reviews, we
found issues with the implementation of this change. Specifically,
we reviewed the economic analyses supporting 10 privatization
projects that had been subjected to independent review and found
reliability issues that had not been identified during the
independent review.
o Second, although DOD directed the services to adequately
consider in their budgets the increased costs resulting from
utility privatization, questions remain over the availability of
the funds needed to complete the program. The services have
estimated that they will need $453 million more than is currently
programmed for continuing government utility operations to pay
implementation and contract costs associated with the remaining
number of utility systems that might be privatized through 2010
for the Air Force and the Navy and Marine Corps and through 2011
for the Army. In view of competing needs and budget priorities,
the Air Force stated that it will not solicit additional utility
privatization contracts until further resources are identified to
cover the potential increase in costs. DOD had not made any
decisions on the funding availability issue at the time of our
review in June 2006.
o Third, it may take some time to fully implement DOD changes to
improve utility privatization contract administration and
oversight as new privatization contracts are awarded. Our review
of five projects awarded prior to DOD's changes found continued
oversight concerns, including questions about the adequacy of
resources provided to perform oversight and the lack of required
plans for overseeing contractor performance.
o Fourth, DOD reported to Congress in March 2006 that, although
privatization may limit the government's options during contract
negotiations, the department continues to prefer privatization
with permanent conveyance and believes that safeguards are in
place to adequately protect the government's interests. It is too
early in the program's implementation to know to what extent DOD's
efforts will be successful in ensuring equitable periodic contract
price adjustments and limiting long-term cost growth in the
utility privatization program. However, we found cost growth in
three of six privatization projects we reviewed. In one case, the
government's annual costs for utility service were expected to
increase by 92 percent as a result of the contract's first
periodic price adjustment.
o Fifth, DOD did not change its guidance to require that project
economic analyses depict the actual expected costs of continued
government ownership in the event that the systems are not
privatized. Therefore, although DOD reported to Congress that the
81 contracts awarded under the utility privatization authority
will result in about $650 million in long-term cost reductions to
the government, the amount is unrealistic because it was not
calculated based on the actual expected cost differences between
continued government ownership and privatization, and because
privatization generally results in increased, not decreased,
utility service costs to the government.
We are making a number of recommendations designed to ensure that
DOD improves the reliability of the economic analyses for proposed
utility privatization projects, addresses potential program
funding shortfalls, ensures adequate oversight in utility
privatization contracts awarded prior to DOD's program changes,
monitors potential contract cost growth, and clearly depicts the
increased costs resulting from proposed utility privatization
projects. In comments on a draft of this report, DOD generally
agreed with six of our seven recommendations and outlined a plan
of action to address each recommendation. Where it indicated
disagreement, we continue to believe our recommendation has merit.
We discuss DOD's comments in detail later in this report.
Background
At DOD's request, Congress approved legislative authority in 1997
for privatizing utility systems at military installations.5 In
defining a utility system, the authority included systems for the
generation and supply of electric power; the treatment or supply
of water; the collection or treatment of wastewater; the
generation or supply of steam, hot water, and chilled water; the
supply of natural gas; and the transmission of telecommunications.
Included in a utility system are the associated equipment,
fixtures, structures, and other improvements as well as easements
and rights-of-way. The authority stated that the Secretary of a
military department may convey a utility system to a municipal,
private, regional, district, or cooperative utility company or
other entity and the conveyance may consist of all right, title,
and interest of the United States in the utility system or such
lesser estate as the Secretary considers appropriate to serve the
interests of the United States.
Among other things, the 1997 authority also included two
requirements for utility privatization. First, DOD was required to
submit a report to congressional defense committees and wait 21
days before allowing a conveyance. For each conveyance, the report
was to include an economic analysis, based on acceptable
life-cycle costing procedures, demonstrating that (1) the
long-term economic benefit of the conveyance to the United States
exceeds the long-term economic cost of the conveyance to the
United States, and (2) the conveyance will reduce the long-term
costs of the United States for utility services provided by the
utility system concerned. Second, the Secretary was required to
receive as consideration for a conveyance an amount equal to the
fair market value, as determined by the Secretary, of the right,
title, or interest of the United States conveyed. The
consideration could take the form of a lump sum payment or a
reduction in charges for utility services.
Before and after approval of the specific authority for
privatizing utilities, the services have used other authorities
for utility privatization. For example, the Army had privatized
some systems after obtaining congressional authority for each
specific case. Also, the services have privatized systems by
modifications to natural gas services agreements administered by
the General Services Administration and by conveyances of some
systems on the basis of authorities related to base realignment
and closure and the military housing privatization program.
DOD's Office of the Deputy Under Secretary of Defense for
Installations and Environment provides overall policy and
management oversight for the utility privatization program.
However, primary management and implementation responsibility for
the program is delegated to the individual services, their major
commands, and individual installations. In addition, Defense
Logistics Agency's Defense Energy Support Center is responsible
for providing the military services with utility privatization
contracting, technical, and program management support.
DOD Made Utility Privatization a Department Policy
In December 1997, DOD issued Defense Reform Initiative Directive
Number 9, which made utility system privatization a DOD policy.6
The directive instructed the military departments to develop a
plan that would result in privatizing all installation electric,
natural gas, water, and wastewater utility systems by January 1,
2000, unless exempted for unique security reasons or if
privatization would be uneconomical. Under the program,
privatization normally involves two transactions with the
successful contractor-the conveyance of the utility system
infrastructure and the acquisition of utility services for
upgrades, operations, and maintenance under a long-term contract
of up to 50 years. Normally, the conveyances do not include title
to the land beneath the utility system infrastructures.
A year later, in December 1998, DOD issued another directive to
establish program management and oversight responsibilities and
provide guidance for performing economic analyses for proposed
projects, exempting systems from the program, and using
competitive procedures to conduct the program.7 The directive also
stated that the objective was for DOD to get out of the business
of owning, managing, and operating utility systems by privatizing
them and that exemptions from privatization should be rare. The
directive reset the privatization implementation goal to September
30, 2003.
Implementation Goals Reset and Program Guidance Revised
In October 2002, DOD issued revised program guidance and again
reset implementation goals.8 The guidance noted DOD's contention
that many installation utility systems had become unreliable and
in need of major improvements because the installations
historically had been unable to upgrade and maintain reliable
utility systems due to inadequate funding caused by the
competition for funds and DOD's budget allocation decisions. DOD
officials stated that owning, operating, and maintaining utility
systems was not a core DOD function and the guidance stated that
privatization was the preferred method for improving utility
systems and services by allowing military installations to benefit
from private sector financing and efficiencies. The revised
implementation goals directed the military departments to reach a
privatization or exemption decision on all systems available for
privatization by September 30, 2005. The October 2002 guidance
also reemphasized that utility privatization was contingent upon
the services demonstrating through an economic analysis that
privatization will reduce the long-term costs to the government
for utility services. The guidance included details for conducting
the economic analyses, stating that the services' analyses should
compare the long-term estimated costs of proposed privatization
contracts with the estimated long-term costs of continued
government ownership assuming that the systems would be upgraded,
operated, and maintained at accepted industry standards, as would
be required under privatization.
GAO Report Identified Weaknesses in Program Implementation
In May 2005, we issued a report that identified management
weaknesses in DOD's implementation of the utility privatization
program.9 The report noted that utility privatization
implementation had been slower than expected, the services'
economic analyses supporting utility privatization decisions
provided an unrealistic sense of savings to a program that
generally increases government utility costs, DOD's funding
obligations would likely increase faster than they would under
continued government ownership, DOD did not require that the
services' economic analyses be subjected to an independent review
for accuracy and compliance with guidance, implementation of the
fair market value requirement in some cases resulted in higher
contract costs for utility services, the services had not issued
specific contract administration guidance for the program, and
DOD's preferred approach of permanently conveying utility system
ownership to contractors may give the contractor an advantage when
negotiating service contract changes or renewals. The report made
several recommendations for DOD to address these concerns.
Program Legislative Authority Modified
The National Defense Authorization Act for Fiscal Year 2006,10
enacted in January 2006, made several modifications to the
legislative authority for the utility privatization program. The
act did the following:
o Reinstated a requirement that the Secretary of Defense must
submit to congressional defense committees an economic analysis
and wait 21 days after the analysis is received by congressional
defense committees, or 14 days if in electronic form, before
conveying a utility system.11 The economic analysis must
demonstrate among other things that the conveyance will reduce the
long-term costs to the United States of utility services provided
by the utility system. The report and wait requirement had been
replaced with a requirement for a quarterly report of conveyances
by the National Defense Authorization Act for Fiscal Year 2004.12
o Added a requirement that the economic analyses incorporate
margins of error in the estimates, based upon guidance approved by
the Secretary of Defense, that minimize any underestimation of the
costs resulting from privatization or any overestimation of the
costs resulting from continued government ownership.
o Eliminated the requirement that DOD must receive as
consideration for a conveyance an amount equal to the system's
fair market value.
o Limited contract terms to 10 years, unless the Secretary
concerned determines that a longer term contract, not to exceed 50
years, will be cost-effective and provides an explanation of the
need for the longer term contract, along with a comparison of
costs between a 10-year contract and the longer term contract.
o Placed a temporary limitation on conveyance authority stating
that during each of fiscal years 2006 and 2007, the number of
utility systems for which conveyance contracts may be entered into
under this authority shall not exceed 25 percent of the total
number of utility systems determined to be eligible for
privatization under this authority as of January 6, 2006.
o Required DOD to submit, not later than April 1, 2006, to
congressional defense committees a report describing the use of
section 2688 of title 10, United States Code (10 U.S.C. 2688), to
convey utility systems. The report was to address several
specified aspects of the utility privatization program.
DOD�s Response to GAO�s Report and Modifications to the Program�s
Authority
Although DOD initially disagreed with our May 2005 report, after
further review of the report, it subsequently reported to Congress
that the report had brought some significant issues to light and
that the department had decided to issue new guidance to address
the key issues in the report in order to improve program
management. On November 2, 2005, DOD issued the new guidance,
which among other things required the services to complete the
remaining evaluations of utility system potential for
privatization in a timely and efficient manner, perform an
independent review of the economic analyses supporting proposed
projects, consider and plan for increased costs for utility
services resulting from potential privatization projects, and take
steps to improve the administration and oversight of awarded
privatization projects.13 DOD issued additional supplemental
guidance14 on March 20, 2006, to implement the modifications to
the legislative authority made by the Fiscal Year 2006 National
Defense Authorization Act; and on March 31, 2006, DOD submitted to
congressional defense committees the utility privatization report
required by the act.15 Even before DOD issued new guidance to
improve the program in November 2005, the services had implemented
several program improvements, including the requirement for
independent reviews of project economic analyses.
Utility Privatization Milestones Have Slipped and Implementation
Costs Continue to Climb
DOD's progress in implementing the utility privatization program
has been slower than expected and implementation costs have
continued to climb. None of the services met DOD's September 2005
implementation goal and the program's estimated completion date
has now slipped to September 2011. In addition to increasing
implementation costs, program delays have also resulted in the
cancellation of privatization solicitations because of concern
that conditions had changed or might change before a decision
would be made whether to privatize.
Services Did Not Meet Program Implementation Milestone
None of the services met DOD's goal of making a privatization or
exemption decision on all systems available for privatization by
September 30, 2005. Since the program began, DOD officials have
attributed delays in program implementation to privatization
evaluation, solicitation, and contracting processes that were more
complex and time consuming than originally anticipated. Service
officials stated that additional delays occurred because the
services decided to suspend the program between October 2005 and
March 2006. According to the officials, the suspension was
provided to allow DOD and the services time to review concerns
noted in our May 2005 report, develop and issue supplemental
guidance for the program, and implement program changes
necessitated by modifications in the program's legislative
authority made by the National Defense Authorization Act for
Fiscal Year 2006. The services now estimate that their program
completion dates-the date when a privatization or exemption
decision has been made on all available systems-are October 2007
for the Navy and Marine Corps, December 2008 for the Air Force,
and September 2011 for the Army. Among other things, the Army
attributed the extension in its completion date to the
privatization process being more complicated than envisioned and a
recognition that the Army's past estimates for completing the
program were unrealistic. Table 1 shows progress as of March 31,
2006, compared to DOD's goal, as well as the current estimated
program completion dates.16
Table 1: Percentage of Systems with Privatization or Exemption
Decision and Estimated Program Completion Date
Source: DOD.
Services Have Awarded Contracts for a Fraction of the Total Systems
Available for Privatization
After spending about $268 million on program implementation costs
through fiscal year 2005, the services had awarded contracts for a
fraction of the 1,496 utility systems available for privatization.
Between May 31, 2005, and September 30, 2005, the services
privatized 14 utility systems using 10 U.S.C. 2688 authority
bringing the total number of awarded projects to 81. However, the
services have awarded no projects under this authority since DOD
issued supplemental program guidance in November 2005. In addition
to the projects awarded under 10 U.S.C. 2688 authority, DOD
privatized 36 systems under other programs, such as DOD's housing
privatization program. The services also have exempted 147
additional systems, bringing the total systems exempted from
privatization to 458. Table 2 shows program status as of March 31,
2006.
Background
5Pub. L. No. 105-85, S: 2812 (1997).
DOD Made Utility Privatization a Department Policy
6DOD, Deputy Secretary of Defense, Memorandum for Secretaries of the
Military Departments and others, Subject: Department of Defense Reform
Initiative Directive #9-Privatizing Utility Systems (Washington, D.C.:
Dec. 10, 1997).
7DOD, Deputy Secretary of Defense, Memorandum for Secretaries of the
Military Departments and others, Subject: Department of Defense Reform
Initiative Directive #49-Privatizing Utility Systems (Washington, D.C.:
Dec. 23, 1998).
Implementation Goals Reset and Program Guidance Revised
GAO Report Identified Weaknesses in Program Implementation
8DOD, Deputy Secretary of Defense, Memorandum for Secretaries of the Army,
Navy, and Air Force and Director, Defense Logistics Agency, Subject:
Revised Guidance for the Utilities Privatization Program (Washington,
D.C.: Oct. 9, 2002).
9See footnote 2.
Program Legislative Authority Modified
10Pub. L. No. 109-163, S: 2823 (2006).
11Prior to November 2003, section 2688 of title 10 stated that the
Secretary of Defense was not permitted to make a conveyance until he
submitted a report that demonstrated two specific factors and a period of
21 days had elapsed from the date at which the analysis was submitted.
12National Defense Authorization Act for Fiscal Year 2004, Pub. L. No.
108-136, S: 1031(a)(32)(2003).
DOD's Response to GAO's Report and Modifications to the Program's Authority
13See footnote 3.
14DOD, Under Secretary of Defense, Memorandum for Secretaries of the
Military Departments and Director, Defense Logistics Agency, Subject:
Supplemental Guidance for the Utilities Privatization Program (Washington,
D.C.: Mar. 20, 2006).
15DOD, Deputy Under Secretary of Defense (Installations and Environment),
Report to Congress on Use of Utility System Conveyance Authority and
Temporary Suspension of Authority Pending Report (Washington, D.C.: Mar.
31, 2006).
Utility Privatization Milestones Have Slipped and Implementation Costs Continue
to Climb
Services Did Not Meet Program Implementation Milestone
16Although this report includes Defense Logistics Agency program status
information, the report does not include any additional Defense Logistics
Agency program information because the agency has few systems available
for privatization compared to the military services and has awarded no
utility privatization contracts.
Goal for September Actual as of March Estimated
Component 30, 2005 (percent) 31, 2006 (percent) completion date
Army 100 75 September 2011
Navy and Marine 100 78 October 2007
Corps
Air Force 100 82 December 2008
Defense 100 86 December 2007
Logistics Agency
Services Have Awarded Contracts for a Fraction of the Total Systems Available
for Privatization
Table 2: Status of the Utility Privatization Program as of March 31, 2006
Contract
Systems awards
pending using 10
Systems solicitation Total U.S.C.
available for or under Systems in Systems contract 2688
Component privatization reassessment solicitation exempted awards authority
Army 320 0 202 38 80 70
Navy and 645 13 411 200 21 1
Marine
Corps
Air Force 502 4 262 220 16 10
Defense 29 0 29 0 0 0
Logistics
Agency
Total 1,496 17 904 458 117 81
Source: DOD.
Program Delays Have Resulted in Increased Implementation Costs
With program delays, the services' estimated program implementation costs
have increased from about $268 million through fiscal year 2005 to about
$285 million through fiscal year 2006. Additional implementation funds
will be needed before the services complete their programs between October
2007 and September 2011. According to service officials, the funds used to
implement the program primarily paid for consultants hired to help the
services in conducting an inventory of their utility systems, assessing
the systems' condition, preparing economic analyses, and soliciting and
contracting for proposed projects. Program implementation costs did not
include funds used to pay the costs of awarded privatization contracts.
Table 3 shows program implementation costs by service and the Office of
the Secretary of Defense.
Table 3: Implementation Costs for the Utility Privatization Program
Dollars in
millions
Estimated Total estimated
Implementation costs implementation implementation costs
for fiscal years costs for fiscal through fiscal year
Component 1998 through 2005 year 2006 2006
Army $62.5 $4.0 $66.5
Navy and 109.7 4.4 114.1
Marine Corps
Air Force 92.6 8.0 100.6
Office of the 3.6 0.3 3.9
Secretary of
Defense
Total $268.3 $16.8 $285.1
Source: DOD.
Note: Totals may not add due to rounding.
Program delays also caused the Defense Energy Support Center to cancel
solicitations to privatize 42 Army utility systems in May 2006. These
solicitations had been closed from 1 to 4 years with no award decision and
there were concerns that conditions, such as the accuracy of the inventory
and needed improvements, had changed or might change before an award
decision would be made. The Army plans to resolicit these systems over the
next few years. Further, Defense Energy Support Center officials stated
that program delays and the resulting decrease in assistance requested by
the services have made it difficult to retain qualified staff to support
the utility privatization program. Consequently, the center will need to
train new staff once the program's pace begins to increase again.
Services Have Estimated the Number and Cost of Potential Privatization Contracts
In addition to revising their program completion dates since our previous
report, the services also estimated the additional number of systems that
might be privatized by the completion of their programs and the funds
needed to pay the costs of these anticipated contracts. The Army estimated
that 41 additional systems might be privatized with the associated
contract costs totaling about $212 million; the Navy and the Marine Corps
estimated that 40 additional systems might be privatized with the
associated contract costs totaling about $139 million; and the Air Force
estimated that 210 additional systems might be privatized with the
associated contract costs totaling about $602 million (see table 4). Air
Force officials stated that its estimated 210 additional systems was a
"worst case" estimate used to determine the maximum funding needed for
possible additional privatization contracts. The officials stated that the
more likely number of systems that might be privatized was about 105
systems. However, the officials did not provide an estimate of the
contract costs associated with the smaller number of systems.
Table 4: Potential Additional Privatization Contracts and Associated Costs
Dollars in millions
Number of additional systems Potential program costs
that potentially could be if the additional systems
Component privatized are privatized
Army 41 $212.4
Navy and Marine 40 139.3
Corps
Air Force 210 602.0
Total 291 $953.7
Source: DOD.
DOD's Changes to Improve Utility Privatization Implementation Have Addressed
Many Areas but Have Not Eliminated All Program Concerns
DOD has made many changes to improve the management and oversight of the
utility privatization program since our May 2005 report. To improve the
reliability of the economic analyses supporting privatization decisions,
DOD now requires that the analyses undergo an independent review to assess
the inputs and assumptions, ensure that cost estimates for the
government-owned and privatization options are treated in a consistent
manner, and verify that all relevant guidance has been met. Also, in
supplemental program guidance issued in November 2005, DOD reminded the
services to consider and plan for increased costs for utility services
contracts resulting from potential privatization projects and prepare
operation and maintenance budgets based upon the expected costs under
privatization. The guidance also emphasized the importance of contract
oversight and directed a number of actions designed to ensure adequate
contract administration and oversight. Among other things, the guidance
directed the Defense Energy Support Center to develop specific preaward
and postaward procurement procedures for the effective management of
utilities services contracts, directed contracting agencies to adequately
train and prepare personnel involved in the utility privatization
contracts, noted that DOD components are responsible for ensuring that the
acquisition plan adequately addresses cost growth control, and stated that
DOD components are responsible for ensuring that resources required to
properly administer the contracts have been identified and provided. In
March 2006, DOD also issued guidance implementing modifications in the
program's legislative authority made by the Fiscal Year 2006 National
Defense Authorization Act, which among other things addresses our concern
that some utility privatization contracts had allowed contractors to
recover more than they paid as the fair market value for system
conveyances. If fully implemented, the changes should result in more
reliable economic analyses supporting proposed privatization projects,
improved budgetary consideration of increased utility costs from
privatization, enhanced oversight of privatization contracts, and reduced
instances where contractors recover more than the amounts they paid as the
fair market value for system conveyances.
Although DOD has made many changes to improve implementation of the
utility privatization program, the changes have addressed some concerns
but have not eliminated all concerns noted in our prior report, such as
ensuring the reliability of project economic analyses and ensuring
effective contract oversight. We found that changes to address some issues
have not been effectively implemented, some changes were not sufficient to
totally eliminate the concerns, and DOD did not make changes to address
some concerns causing continued questions about the reliability of the
economic analyses, the availability of funds to pay for the remaining
projects that might be privatized, the adequacy of contract oversight in
projects awarded prior to DOD's changes, and the control of long-term cost
growth in utility privatization contracts. We also have concerns that the
program may continue to provide an unrealistic sense of savings and
decision makers may have incomplete information on the financial effect of
privatization decisions.
DOD Has Taken Steps to Improve the Reliability of Project Economic Analyses but
Implementation Is a Concern
Although DOD has made changes to improve the reliability of the analyses
supporting proposed utility privatization projects, we found issues with
the services' implementation of the changes. In November 2005, DOD issued
supplemental program guidance requiring DOD components to ensure that
independent reviews were conducted for all economic analyses supporting a
proposed conveyance. The guidance stated that the independent review
should verify that all relevant guidance has been met and that
privatization is in the best interest of the government. In March 2006,
DOD reported to Congress that the independent review included procedures
to review the general inputs and assumptions, verify that the inventory in
the economic analysis is identical to the inventory in the solicitation,
and ensure that the government and the contractor treat the renewal and
replacement cost estimates in a consistent manner.17 Even before DOD
issued the guidance requiring independent reviews, Army and Air Force
officials stated that they had implemented such reviews to help ensure
reliability of their project analyses. The officials stated that
independent reviews were performed on the analyses supporting 12 utility
privatization projects that were awarded in September 2005-after our
previous report-but before DOD's issuance of the guidance requiring
independent reviews.
As an additional step to help ensure reliable economic analyses, DOD's
March 2006 report to Congress stated that the services must conduct
postconveyance reviews that compare actual project costs with the
estimated costs included in the projects' economic analyses. DOD stated
that the postconveyance reviews are conducted 2 to 3 years after contract
award, or 1 year after the first periodic price adjustment, whichever is
later, and that the results of these reviews will be compiled until such
time as the analysis of all conveyances is complete. DOD stated that the
reviews are to include an analysis of the system's inventory, changes in
requirements and contract costs, and a comparison of actual contract costs
with estimates from the economic analyses.
Although DOD's changes are key steps in the right direction to improve the
reliability of the economic analyses, we found issues with the
implementation of the changes. First, we reviewed the analyses associated
with 10 Army and Air Force projects awarded in September 2005. Although
these analyses were prepared prior to the issuance of DOD's supplemental
guidance, the services had already implemented an independent review
process and these analyses underwent an independent review. Service
officials noted that the independent reviews had just begun and expected
that the thoroughness of the reviews would improve as experience was
gained and DOD's supplemental guidance was implemented. We found that the
reviews did identify some questionable items and that some changes were
made to improve the reliability of the economic analyses. Yet, we also
found questionable items in each analysis that were not identified during
the independent review. For example:
17Renewals and replacements is a term used to describe the normal
replacement of, or repairs to, a system's components or parts as needed to
keep the system functioning in accordance with industry standards.
o The economic analysis for the natural gas system privatization
at Minot Air Force Base did not treat estimates of renewal and
replacement costs for the government-owned and privatization
options in a consistent manner. The analysis estimated that the
Air Force would spend $7.1 million on renewals and replacements
during the first year of continued government ownership. Under the
first year of privatization, the analysis estimated that the
contractor would spend about $0.2 million on renewals and
replacements. When we asked about this difference, Air Force
officials stated that the contractor is not required to perform
the same renewals and replacements identified in the government
estimate and that the government found the contractor's proposal
to be acceptable. Because the analysis was not based on performing
the same work, the cost estimates were not consistently developed
and resulted in favoring the privatization option. This issue was
not identified in the independent review.
o The economic analyses for the water and wastewater
privatization projects at Andrews Air Force Base were based on the
systems' inventory (i.e., the wells, pumps, water treatment
equipment, valves, fire hydrants, water distribution mains,
meters, storage tanks, reservoirs, and other components that
constitute the systems) and condition 2 years prior to contract
award. The Air Force stated that adjustments to the contract could
be made after contract award, if needed, to reflect changes in the
inventory. However, because the analyses were not updated to
reflect inventory changes before contract award, the reliability
of the analyses is less certain. This issue was not noted in the
independent review.
o The economic analyses for privatization of the electric
distribution system at Fort Leavenworth and the water and
wastewater systems at three Army installations in the Tidewater
Virginia area incorrectly included financing costs under the
government option. Although this favored the privatization option,
the amount was not enough to change the outcome of the analyses.
This issue was not identified in the independent review. However,
Army officials told us that they would ensure that this did not
occur in future analyses.
Second, although DOD noted in its March 2006 report to Congress
the importance of postconveyance reviews as an additional measure
to help ensure reliable economic analyses, DOD has not issued
guidance that requires the services to perform the reviews.
Service officials stated that they had performed only a limited
number of postconveyance reviews and do not have plans to perform
the reviews in the manner or frequency described in DOD's report
to Congress. Also, DOD's report cited seven Army Audit Agency
postconveyance reviews, four additional Army postconveyance
reviews, and one Air Force postconveyance review. However, only
three of the Army Audit Agency reviews included a comparison of
actual contract costs with estimates from the economic analyses.
DOD Has Taken Steps to Address Some Funding Issues but Concerns Remain
Although DOD has taken steps to help ensure that the services
adequately consider the increased costs from utility privatization
projects during budget preparation, questions remain over the
availability of the additional funds needed to complete the
program. The services estimate that they potentially will need
$453 million more than is currently programmed for continuing
government utility operations to pay implementation and contract
costs associated with the remaining number of utility systems that
might be privatized through 2010 for the Air Force, the Navy, and
Marine Corps, and through 2011 for the Army. As a result, in view
of competing needs and budget priorities, the Deputy Assistant
Secretary of the Air Force (Installations) stated in an April 2006
memorandum that the Air Force could not afford to award further
utility privatization contracts unless additional resources are
provided.
Utility Costs Increase with Privatization
Our May 2005 report noted that installation utility costs under
privatization typically increase significantly above historical
levels because the systems are being upgraded and the contractors
recoup their investment costs through the utility services
contracts. Essentially, under the privatization program, the
services leverage private sector capital to achieve utility system
improvements that otherwise would not be feasible in the short
term because of limited funding caused by the competition for
funds and budget allocation decisions. The services pay for the
improvements over time through the utility services contracts,
which are "must pay" bills. As a result, if an installation's
funds were not increased sufficiently, then funds provided for
other installation functions where there was more discretion in
spending might be used to pay the higher utility bills. This, in
turn, could negatively affect those other functions, such as the
maintenance of installation facilities. We recommended that DOD
provide program guidance emphasizing the need to consider
increased utility costs under privatization as the military
services prepare their operation and maintenance budget requests
and that DOD direct the service Secretaries to ensure that
installation operations and maintenance budgets are adjusted as
necessary to reflect increased costs from utility privatization
projects.
In November 2005, DOD issued supplemental program guidance that
reminded DOD components to consider the increase in utility costs
from privatization. Specifically, the guidance directed the
components to consider and plan for increased costs for utility
services contracts resulting from potential privatization projects
and system conveyance and prepare operation and maintenance
budgets based upon the expected costs under privatization.
Funds Not Programmed for All Potential Utility Privatization Projects
DOD's guidance addresses the recommendations from our May 2005
report and, if implemented, should result in the increased costs
from utility privatization projects being adequately considered
during budget preparation. However, in view of competing needs and
budget priorities, questions remain over availability of the
additional funds needed to complete the program. To illustrate,
DOD's November 2005 supplemental guidance also directed DOD
components to advise the Deputy Under Secretary of Defense
(Installations and Environment) if significant shortfalls are
anticipated that will affect utilities privatization efforts. In
response to that direction, each service estimated the remaining
number of utility systems that might be privatized, calculated the
associated implementation and contract costs, compared these costs
with the funds already programmed for continued government
operation of the systems that might be privatized, and determined
whether any potential funding shortfalls existed. The Army's
estimate was through fiscal year 2011 and the other services'
estimates were through fiscal year 2010. As a result of this
review, each service determined that funding shortfalls existed to
pay for potential future privatization contracts (see table 5).
Table 5: Service Estimates of Potential Utility Privatization
Program Funding Shortfall
Dollars in
millions
Potential
Number of systems program costs Total unfunded
that potentially if the systems Total funds requirement
Component could be privatized are privatized programmed (shortfall)
Army 41 $212.4 $90.3 $122.1
Navy and 40 139.3 103.2 36.1
Marine Corps
Air Force 210 602.0 306.9 295.1
Total 291 $953.7 $500.4 $453.3
Source: DOD.
Air Force May Not Award Some Additional Privatization Projects Due
to Funding Issues
Air Force officials stated that the increased costs from potential
future utility privatization contracts had reached a critical
point. The officials stated that because funds are limited and
funding needs for some Air Force programs are greater than the
funding needs for utility upgrades, the Air Force has concluded
that it will not solicit new utility privatization contracts until
additional resources are identified to specifically cover any
potential increase in future costs. Air Force officials further
explained that privatization results in improving utility systems
to an industry standard level by creating "must pay" contracts.
However, without additional resources, funding these contracts
must come from other base operating support funds, which would
result in diverting critical resources from remaining facilities
and infrastructure. Also, the officials noted that the utility
privatization program drives system recapitalization to an
industry standard level that may be questionable when compared to
historical Air Force requirements and, furthermore, reflects a
funding level that is not affordable in light of current fiscal
constraints and differing Air Force modernization priorities.
When we questioned a cognizant DOD official in June 2006 about the
potential funding shortfall, the official stated that each service
has competing priorities and the cost of awarding contracts to
privatize utility infrastructure is just one of many. However, the
official also stated that the funding issue and alternatives were
under discussion but conclusions had not yet been reached.
DOD Directed Actions to Improve Utility Privatization Contract
Oversight but Some Concerns Remain
DOD has made a number of changes designed to improve utility
privatization contract administration and oversight since our May
2005 report. However, it may take some time for the improvements
to be fully implemented as the changes are applied to new
privatization contract awards and efforts may be needed to ensure
that the changes are applied, where needed, to previously awarded
contracts.
DOD Has Taken Steps to Address Oversight Concerns
To address privatization contract oversight concerns, DOD issued
supplemental program guidance in November 2005 that emphasized to
the services the importance of contract oversight and directed a
number of actions designed to ensure adequate contract
administration and oversight. Among other things, the guidance
o directed the Defense Energy Support Center to develop specific
preaward and postaward procurement procedures for the effective
management of utilities services contracts resulting from a
utility conveyance, and coordinate with the Defense Acquisition
University to develop a training program for all contracting
officers and DOD components involved in utilities privatization
efforts;
o directed contracting agencies to adequately train and prepare
personnel involved in the administration of the utilities services
contracts resulting from a utilities conveyance;
o stated that contracting officers must be able to use guidance
for postaward contract management and contract provisions to
ensure that the government's interests are protected in the
long-term utility service contracts and associated real estate
documents;
o stated that prior to awarding a services contract resulting
from a utility conveyance, DOD components are responsible for
ensuring, among other things, that resources required to properly
administer the contract have been identified; and
o directed that transfers of contract administration
responsibilities from the procuring contract office to the
contracting administration office should include an on-site
transfer briefing with government and contractor personnel that
includes, among other things, a clear assignment of
responsibilities.
During our visit to the Defense Energy Support Center in April
2006, officials stated that in accordance with the guidance, the
center had already issued the preaward and postaward procurement
procedures that would help ensure the effective management of
utilities services contracts. The officials stated that they had
also begun developing a training program for all contracting
officers and other DOD personnel involved in utilities
privatization efforts and had developed procedures for
transferring contract responsibilities that should help ensure
effective contract oversight. During our visits to the services,
officials stated that, in addition to working with the Defense
Energy Support Center, further efforts were underway to ensure
that postaward management is effective. For example, Air Force
officials stated that they had developed their own postaward plan,
which defines the responsibilities and standards by which the
government could ensure that utility services are provided in
accordance with requirements. Navy officials stated that the Navy
plans to prepare a quality assurance plan for each utility
privatization contract awarded.
Some Contract Oversight Concerns Identified at the Four Installations
We Visited
Although the steps taken by DOD, the Defense Energy Support
Center, and the services are significant improvements,
implementation will be the key to ensuring effective oversight of
all utility privatization contracts, and it may take some time to
fully implement improvements as new privatization contracts are
awarded. From the time DOD's supplemental guidance was issued and
other improvement measures were put into place through the time of
our review in June 2006, the services awarded no new utility
privatization contracts. Thus, to assess contract oversight, we
were unable to visit installations with utility privatization
contracts awarded after DOD's changes were implemented. Instead,
we assessed contract oversight at four installations with five
utility privatization projects that were awarded prior to our May
2005 report. We found continuing concerns about the adequacy of
oversight because no additional resources were provided to oversee
the contracts at all four installations and mandatory written
plans for overseeing contractor performance were not prepared at
two installations.
For example, officials at each of the four installations we
visited noted that no additional resources were provided at the
installation level to perform contract oversight once their
utility systems were privatized. The contract officials stated
that the extra work associated with the contracts was added to
their workload of overseeing other contracts. Some officials
stated that they did not have sufficient personnel to perform the
level of detailed monitoring of contractor performance that they
believed was needed. According to Fort Eustis officials, when the
electric system was privatized, they requested three additional
people to oversee the contract based on the magnitude of the
workload associated with this contract. Yet, no additional people
were provided and the extra workload was added to the workload of
the staff responsible for overseeing other contracts.
Also, our review of the electric distribution system privatization
projects at Fort Eustis and the Army's Military Ocean Terminal
Sunny Point found that neither installation had a quality
assurance surveillance plan in place for overseeing contractor
performance. Such plans are required by the Federal Acquisition
Regulation. Officials at both installations stated that although a
formal surveillance plan had not been prepared, they were
performing oversight to ensure that the contractors met contract
requirements. Nevertheless, formal contractor performance
monitoring plans are an important tool for ensuring adequate
contract oversight.
Containing Utility Privatization Contract Cost Growth May Be a Challenge
Because contractors own installation utility systems after
privatization and, therefore, may have an advantage when
negotiating contract changes and renewals, containing utility
privatization contract cost growth may become a challenge as
contracts go through periodic price adjustments and installations
negotiate prices for additional needed capital improvement
projects and other changes. In March 2006, DOD stated that
although it recognizes that privatization may limit the
government's options during contract negotiations, the department
continues to prefer privatization with permanent conveyance and
believes that safeguards are in place to adequately protect the
government's interests. Although it is too early in the program's
implementation to know to what extent DOD's efforts will be
successful in ensuring equitable contract price adjustments and
limiting long-term cost growth in the utility privatization
program, our review found indications that containing cost growth
may become a concern.
DOD Continues to Prefer Permanent Conveyance but Has Taken Steps
to Control Costs
In our prior report, we noted that, according to DOD consultant
reports, DOD's approach to utility privatization differs from
typical private sector practices in that private sector companies
may outsource system operations and maintenance but normally
retain system ownership. As a result, the consultant reports note
that DOD's preferred approach of permanently conveying utility
system ownership to contractors may give the contractor an
advantage when negotiating service contract changes or renewals.
This occurs because DOD must deal with the contractor or pay
significant amounts to construct a new utility distribution system
to replace the one conveyed to the contractor, attempt to purchase
the system back from the contractor, or institute legal action to
reacquire the system through condemnation proceedings. Because of
concern that contractors may have an advantage when it comes time
to negotiate contract changes and renewals, we recommended that
DOD reassess whether permanent conveyance of utility systems
should be DOD's preferred approach to obtaining improved utility
services.
DOD stated that it has reassessed its position and continues to
believe that owning, operating, and maintaining utility systems is
not a core mission of the department and that permanent conveyance
of systems under utilities privatization enables the military
installations to benefit from private sector innovations,
economies of scale, and financing. Although DOD contends that
private industry can normally provide more efficient utility
service than can the government, DOD has not provided any studies
or other documentation to support its contention. Given that the
private sector faces higher interest costs than the government and
strives to make a profit whereas the government does not, it is
not certain that utility services provided by the private sector
would be less costly than utility services provided by the
government through the use of up-front appropriations.
Although DOD continues to prefer privatization with permanent
conveyance of the utility systems, DOD has recognized that
privatization may limit the government options during contract
renegotiations and has taken steps to help control contract cost
growth. First, DOD stated in its March 2006 report to Congress
that a contractor also may have limited options under
privatization because the contractor typically cannot use the
installation's utility system to service other customers. DOD
reported that privatization creates a one-to-one relationship
between the installation and the contractor. In this relationship,
DOD stated that both parties must work together to execute fair
and equitable contract changes, both parties have significant
vested interests in successful negotiations, and both parties
retain substantial negotiation leverage.
Second, DOD noted that service contracts awarded as part of a
privatization transaction are contracts subject to the Federal
Acquisition Regulation and applicable statutes. Because it is
recognized that privatization will as a practical matter limit
future opportunities to recompete this service, DOD stated that
all contracts will include appropriate provisions to protect the
government's interest while allowing the contractor reasonable
compensation for the services provided. DOD's report further
stated that fixed price contracts with prospective price
adjustment provisions have been determined to be the most
appropriate contract in most situations and that this type of a
contract will mitigate cost risk and hopefully result in a
satisfactory long-term relationship for both the contractor and
the government.
Third, DOD noted that utility services contracts resulting from a
utility conveyance may include a contract clause that provides an
option for the government to purchase the system at the end of the
contract period. According to Defense Energy Support Center
officials, the center has developed language for future Army and
Air Force contracts that would provide an option for the
government to buy back a system at the end of the contract period.
Center officials stated that this clause may help the government
in negotiations at the end of the contract term. Navy officials
stated that the Navy does not plan to include a buy back clause in
its future utility contracts because a system could be taken back,
if necessary, through condemnation procedures.
Fourth, in its November 2005 supplemental guidance, DOD emphasized
the importance of controlling contract cost growth. Specifically,
the guidance noted that prior to awarding a services contract
resulting from a utility conveyance, DOD components are
responsible for ensuring that the acquisition plan adequately
addresses cost growth control, which includes specifying the
appropriate price adjustment methodology and postaward contract
administration.
Cost Growth in Utility Privatization Contracts May Become a Concern
Although DOD has policies, guidance, and procedures to help
control contract costs and ensure that price adjustments are
equitable, cost growth may still become a concern as utility
privatization contracts go through periodic price adjustments and,
in some cases, installations negotiate changes for additional
capital improvement projects or other needs. According to DOD,
most utility privatization contracts include provisions for
periodic price adjustments. The price adjustment process allows
contract price changes based on changes in market prices,
generally to cover inflation, and changes to the service
requirement from system additions or modifications resulting from
capital upgrades. Under this process, the contractor is required
to submit sufficient data to support the accuracy and reliability
of the basis for service charge adjustments. If the contractor's
data is determined to be fair and reasonable, the contracting
officer negotiates a service charge adjustment. Utility
privatization contracts normally provide for price adjustments
after an initial 2-year period and every 3 years thereafter. In
addition to cost increases from service charge adjustments,
contract costs can also increase as a result of contract
modifications to pay for additional capital improvement projects
not included in the initial contract.
According to the services, utility privatization contracts for 22
systems are currently undergoing, or will be subject to, their
first periodic price adjustment before the end of calendar year
2007.18 Although it is too early to know the extent of cost
changes that might occur in these contracts, our review of six
contracts-one that completed a periodic price adjustment, one that
was undergoing periodic price adjustment, and four that had not
yet undergone a periodic price adjustment-found conditions that
indicate that cost growth in utility privatization contracts may
become a concern. Changes in contract costs could result in
privatization costs increasing above the levels estimated in the
economic analyses. To illustrate:
o The Fort Rucker natural gas distribution system privatization
contract was issued on April 24, 2003. The contract provided for a
price adjustment after the initial 2 years of the contract and
then every 3 years thereafter. In February 2005, the contractor
submitted a proposal for a price adjustment and requested an
increase in the price paid to the contractor for operations and
maintenance, associated overhead, and renewals and replacements.
According to a government memorandum that summarized the results
of the price adjustment process, the requested increases were
based on the contractor's actual labor hours and material costs
and additional overhead costs which resulted from a change in the
way the contractor calculated overhead costs. The change in
overhead calculations included costs that were not included in the
original proposal submission or in the contract. When queried, the
contractor responded that the costs were not originally submitted
but should have been. After review, the government team
responsible for the price adjustment process determined that the
requested increases were allowable and reasonable and approved the
price increase. The change increased the government's annual
utility service charge costs from about $87,000 to about $124,000,
an increase of about $36,000, or 41 percent. In approving the
increase, the government team noted that although the estimated
cost avoidance from privatization would be reduced, the contract
was still economical compared to the estimated costs of government
ownership.
o The Sunny Point electric distribution system privatization
contract was issued on September 30, 2003. In January 2006, the
contractor submitted a proposal for a price adjustment and
requested an increase in the utility service charge based on the
contractor's actual labor hours and material costs associated with
operating and maintaining the system, including the installation's
emergency generators. According to installation officials, the
costs to operate and maintain the system were significantly higher
than originally anticipated by the contractor because of errors in
the system's inventory used to develop the solicitation, such as
not including all of the installation's emergency generators. When
queried about the requested price increase, the contractor
responded that the initial contract bid would have been higher if
the true inventory of the system had been known. Although the
price adjustment process was not final at the time of our visit in
June 2006, installation officials stated that the government team
responsible for the process had determined that the requested
increases were allowable and reasonable and had approved the price
increase. As a result of the price adjustment, the government's
annual utility service costs are expected to increase from about
$415,000 to $798,000 in the third year of the contract, an
increase of about $383,000, or 92 percent.
o The Fort Eustis electric distribution system privatization
contract was issued on June 24, 2004. While this contract is not
scheduled for a periodic price adjustment until December 2006, the
contract costs have increased by about $431,000, or 26 percent,
since the contract was signed. The increase is the result of two
factors. First, the annual service charge was increased by about
$73,000 as the result of correcting errors to the system's
inventory described in the privatization solicitation. Second, the
contract's cost was increased by about $358,000 to pay for capital
improvement projects that were added to the original contract.
Fort Eustis officials stated that funding for the capital
improvement projects added to the contract did not have to compete
for funding against other needed installation improvement projects
because project costs were added to the privatization contract.
The officials stated that it was unclear whether these projects
would have been approved for funding had the privatization
contract not been in place.
The remaining three contracts we reviewed-the water and wastewater
privatization contracts at Bolling Air Force Base and the electric
distribution system privatization contract at Dobbins Air Reserve
Base-were not yet eligible for, or not subject to, a periodic
price adjustment. At the time of our visits in May 2006, actual
contract costs in these cases approximated the estimates in the
projects' economic analyses.
DOD Has Not Made Changes to Provide More Realistic Savings
Estimates from Utility Privatization
Because DOD has not changed the guidance for performing the
economic analyses or taken any other steps to change the
perception that the utility privatization program results in
reduced costs to the government, the program may continue to
provide an unrealistic sense of savings for a program that
generally increases annual government utility costs in order to
pay contractors for enhanced utility services and capital
improvements. The concern was caused by the methodology DOD uses
to determine whether a proposed privatization contract would meet
the statutory requirement for reduced long-term costs. In our
previous report, we noted that DOD's guidance directs the services
to compare the estimated long-term costs of the contract with the
estimated long-term "should costs" of continued government
ownership assuming that the service would upgrade, operate, and
maintain the system in accordance with accepted industry standards
as called for in the proposed contract. This estimating method
would be appropriate, if in the event the system is not
privatized, the service proceeded to upgrade, operate, and
maintain the system as called for in the estimate. However, this
generally is not the case. According to DOD and service officials,
if a system is not privatized, then the anticipated system
improvements would probably be delayed because of DOD's budget
allocation decisions, which have limited funds for utility
improvements. Because of the time value of money, a future expense
of a given amount is equivalent to a smaller amount in today's
dollars. Thus, if reduced costs to the government are expected to
be a key factor in utility privatization decision making, then it
would appear more appropriate for the services to compare the cost
of a proposed privatization contract with the cost of continued
government ownership on the basis of the actual planned
expenditures and timing of these expenditures.
Since May 2005, DOD has not changed the guidance for performing
the economic analyses nor has DOD taken other steps, such as
showing current utility system costs in the economic analyses, to
change the perception that the utility privatization program
results in reduced costs to the government. DOD's November 2005
supplemental program guidance directed the services to continue to
prepare economic analyses based on the "should costs," which is
defined as an independent government estimate of the costs
required to bring the system up to and maintain it at current
industry standards. Further, DOD's March 2006 report to Congress
stated that the "should cost" estimate is the government's best
tool for predicting the future requirement for individual systems
and is the most realistic methodology. Yet, the report also
acknowledged that the department had done an inadequate job of
defining industry standards and then subsequently programming,
budgeting, and executing to that requirement. Because DOD has not
programmed funds to do the work described in the "should cost"
estimate if the system is not privatized, DOD's estimates of the
reduced costs to the government that would result from
privatization are not based on realistic cost differences.
Information that DOD reported to Congress in March 2006
illustrates our concern. DOD's report stated that the department's
total cost avoidance from utility conveyances is expected to
exceed $1 billion in today's dollars and, as shown in table 6, the
report included information showing that the 81 contracts awarded
under 10 U.S.C. 2688 will result in about $650 million in reduced
costs to the government in today's dollars compared to DOD's
"should cost" estimate.
Table 6: DOD's Estimated Cost Avoidance from Utility Privatization
Dollars in
millions
Estimated
Number of costs under Estimated costs Estimated cost
systems government under avoidance with
Component privatized ownership privatization privatization
Army 70 $2,377.0 $1,867.5 $509.5
Navy and 1 308.1 215.4 92.7
Marine Corps
Air Force 10 220.5 173.0 47.5
Total 81 $2,905.6 $2,255.9 $649.7
Source: DOD.
Note: Estimates are totals in today's dollars over the contract
terms (50 years for most projects).
DOD's reported cost avoidance amounts provide an unrealistic sense
of savings for several reasons:
o First, as previously stated, the estimated costs under
government ownership are not based on the actual expected costs if
the system is not privatized but rather on a higher "should cost"
amount. As a result, estimated costs under government ownership
are overstated and, therefore, DOD's estimated cost avoidance is
overstated, at least in the short term.
o Second, the government's costs for utility services increase
with privatization. Army officials estimated that average annual
cost increase for each privatized Army system was $1.3 million.
Also, the services estimate that they will need $453 million more
than is currently programmed for continuing government ownership
to pay for the contract and other costs associated with the
remaining number of utility systems that might be privatized
through 2010 for the Air Force and the Navy and Marine Corps, and
through 2011 for the Army.
o Third, DOD's reported cost avoidance does not consider the
program's one-time implementation costs. Through fiscal year 2005,
about $268 million was spent to implement the program.
o Fourth, the economic analyses used to estimate the cost
avoidance between the government-owned and privatization options
for several of the 81 projects included in DOD's report to
Congress are unreliable. As noted in our previous report, our
review of seven project analyses identified inaccuracies,
unsupported cost estimates, and noncompliance with guidance for
performing the analyses. The cost estimates in the analyses
generally favored the privatization option by understating
long-term privatization costs or overstating long-term government
ownership costs. When we made adjustments to address the issues in
these analyses, the estimated cost avoidance with privatization
was reduced or eliminated. Also, as discussed in another section
of this report, although DOD has taken steps to improve
reliability, we found questionable items in 10 economic analyses
supporting projects awarded after our May 2005 report.
o Fifth, cost growth in privatization contracts might reduce or
eliminate the amount of the estimated cost avoidance from
privatization. We reviewed the analysis supporting the Navy's one
privatization project under 10 U.S.C. 2688, awarded in 1999, and
compared actual contract costs to the estimated contract costs
included in the analysis. The analysis showed that if contract
costs continue to increase at the same rate experienced since the
contract was awarded, then the project's estimated cost avoidance
would be reduced from about $92.7 million to about $18 million.
This analysis also did not include consideration of privatization
contract oversight costs. Consideration of these costs would
further reduce the estimated cost avoidance to about $4 million.
As discussed in another section of this report, we found contract
cost growth concerns in 3 of 6 additional utility privatization
projects we reviewed, which will reduce the estimated cost
avoidance for those projects.
In addition to providing an unrealistic sense of savings by
providing only the "should cost" estimates, the economic analyses
do not include other information that would provide decision
makers with a clearer picture of the financial effect of
privatization decisions. If the analyses included information
showing the amount that the government currently spends on
operating, maintaining, and upgrading the utility systems being
evaluated for privatization, decision makers could better consider
the increase in costs that will result from privatization as they
assess the merits of proposed projects. However, DOD's guidance
does not require that the services' economic analyses include
current utility system cost information.
The National Defense Authorization Act for Fiscal Year 2006
modified the program's legislative authority by requiring that
project economic analyses incorporate margins of error in the
estimates that minimize any underestimation of the costs resulting
from privatization of the utility system or any overestimation of
the costs resulting from continued government ownership and
management of the utility system. This step could help improve the
reliability of the cost differences between the government-owned
and privatization options. The modified authority stated that
incorporating margins of error in the estimates was to be based
upon guidance approved by the Secretary of Defense. However, as of
June 2006, DOD had only issued general guidance in this area with
no details on how the services were to comply with the new
requirement. Specifically, on March 20, 2006, DOD issued guidance
directing the services to include in the economic analysis an
explanation as to how margin of error considerations were
addressed in developing the independent government cost estimate
and carried forward in the price analysis report and cost realism
report. Although the guidance referenced Office of Management and
Budget Circular A-94, dated October 29, 1992; DOD Instruction
7041.3, dated November 7, 1995; and Deputy Secretary of Defense
memorandum and guidance dated October 9, 2002; none of these
documents provide details on how margins of error should be
incorporated into the economic analyses. At the time of our review
in June 2006, Army and Navy officials stated that they were
evaluating how to include margins of error into future economic
analyses. Air Force officials stated that their economic analyses
already included margins of error calculations but that no formal
rules existed on how to use the results of the calculations.
Without detailed DOD guidance, there is little assurance that the
services will include margins of error considerations in an
appropriate and consistent manner in future project economic
analyses.
Changes in Legislative Authority and DOD�s Implementation of the
Change Address Fair Market Value Concerns
DOD's changes to implement a modification to the legislative
authority for the utility privatization program have addressed the
fair market value concerns discussed in our May 2005 report. Our
report noted that in some cases implementation of a previous
legislative requirement that the government receive fair market
value for systems conveyed to privatization contractors had
resulted in higher contract costs for utility services. To address
this concern, we recommended that DOD place greater scrutiny on
the implementation of the fair market value requirement in
proposed contracts to minimize cases where contractors recover
more than the amounts they paid for system conveyances. Subsequent
to our report, in January 2006, the National Defense Authorization
Act for Fiscal Year 2006 was enacted.19 The act changed the
legislative language from stating that fair market value from a
conveyance must be received to stating that fair market value from
a conveyance may be received.
In March 2006, DOD issued guidance to implement modifications in
the legislative authority made by the act. With regard to fair
market value, DOD's guidance to the services noted that military
departments are no longer required to obtain fair market value
exclusively through cash payments or rate credits. The military
departments now have the flexibility to seek consideration in a
manner other than a payment of the fair market value when the
economic analysis demonstrates it is in the best interest of the
government. The guidance also stated that the military departments
may not dispose of the government's property without receiving an
appropriate return, but the amount and nature of that return may
be determined and represented in a number of ways, depending on
the negotiated deal.
The change in legislative authority and the additional guidance
issued by DOD address our concern with receipt of fair market
value for system conveyances. Our review of 10 economic analyses
for projects awarded after our May 2005 report showed that the
fair market value paid by the contractor and the amount recovered
were the same. Thus, according to these analyses, the receipt of
the fair market value for the conveyances in these cases did not
result in any increased costs to the government.
Conclusions
DOD has made many changes to improve the management and oversight
of the utility privatization program since our previous report. If
fully implemented, the changes should result in more reliable
economic analyses supporting proposed privatization projects,
improved budgetary consideration of increased utility costs from
privatization, enhanced oversight of privatization contracts, and
reduced instances where contractors recover more than the amounts
they paid as the fair market value for system conveyances.
However, a number of program concerns remain because DOD's changes
to address some issues noted in our previous report have not been
effectively implemented, some changes were not sufficient to
totally eliminate the concerns, and DOD did not make changes to
address some concerns. Specifically, implementation of DOD's
changes to improve the reliability of the economic analyses, such
as requiring independent reviews and noting the importance of
postconveyance reviews to compare actual contract costs with
estimates from the analyses, could be improved. The reliability of
the analyses could continue to be questionable until DOD requires
independent reviewers to report to decision makers on the
thoroughness of the economic analyses and any significant
anomalies between the ownership options, estimated costs,
inventories, and assumptions and also issues guidance requiring
the services to perform the postconveyance reviews as noted in its
March 2006 report to Congress. An additional concern is the
services' estimated shortfall in the funds needed to pay contract
costs associated with the remaining number of utility systems that
might be privatized by the end of their programs. Unless DOD
addresses the potential funding shortfall in view of all DOD and
service funding and priority needs, questions will remain over the
availability of the additional funds needed to complete the
program. Also, although DOD's changes designed to improve utility
privatization contract administration and oversight are key steps
in the right direction, it may take some time to fully implement
improvements as new privatization contracts are awarded and
oversight of older contracts is assessed. Until DOD ensures that
the contracts awarded prior to the program changes have adequate
resources and contractor performance surveillance plans, the
adequacy of contract oversight will remain a concern. Further,
because contractors own installation utility systems after
privatization, they may have an advantage when negotiating
contract changes and renewals. Unless DOD places additional
emphasis on monitoring contract cost growth as utility
privatization contracts undergo periodic price adjustments and
other changes are negotiated, concern will continue that
containing utility privatization contract cost growth may become a
challenge.
Because DOD did not change guidance to require that project
economic analyses show the actual costs of continued government
ownership if the system is not privatized, or take any other steps
to change the perception that the utility privatization program
results in reduced costs to the government, DOD continues to
provide an unrealistic sense of savings to a program that
generally increases government utility costs in order to pay
contractors for enhanced utility services and capital
improvements. Until DOD requires that each economic analysis
includes information on the system's current costs and the actual
expected costs if the system is not privatized, decision makers
will have incomplete information on the financial effect of
privatization decisions. In addition, unless the Secretary of
Defense issues detailed guidance explaining how the services
should incorporate margins of error in the economic analyses, as
required by the National Defense Authorization Act for Fiscal Year
2006, there is little assurance that the full benefit from this
requirement will be achieved.
Recommendations for Executive Action
We recommend that the Secretary of Defense direct the Deputy Under
Secretary of Defense (Installations and Environment) to take the
following seven actions:
o require independent reviewers to report to decision makers on
the thoroughness of each economic analysis and any significant
anomalies in the assumptions used and estimated costs for each
ownership option;
o issue guidance requiring the services to perform the
postconveyance reviews as noted in DOD's March 2006 report to
Congress;
o address the utility privatization program potential funding
shortfall in view of all DOD and service funding and priority
needs;
o ensure that utility privatization contracts awarded prior to
the November 2005 supplemental guidance have adequate resources
and contractor performance surveillance plans;
o place additional emphasis on monitoring contract cost growth as
utility privatization contracts undergo periodic price adjustments
and other changes are negotiated;
o require, in addition to the "should cost" estimate, that each
project economic analysis include the system's current annual
costs and the actual expected annual costs if the system is not
privatized; and
o issue detailed guidance explaining how the services should
incorporate margins of error in the economic analyses.
Agency Comments and Our Evaluation
In comments on a draft of this report, the Deputy Under Secretary
of Defense (Installations and Environment) generally agreed with
six of our seven recommendations and outlined a plan of action to
address each recommendation. The Deputy Under Secretary noted that
the utility privatization systems evaluated in our report were
approved prior to DOD's November 2005 program guidance and that
the guidance will be fully implemented prior to awarding
additional contracts. We recognize that issues identified in this
report pertain to contracts awarded before supplemental program
guidance was issued in November 2005. Nevertheless, we believe the
issues identified in this report highlight areas that merit
increased attention as the program continues-and this is reflected
in the department's response to each recommendation.
The Deputy Under Secretary indicated disagreement with our
recommendation to require, in addition to the "should cost"
estimate, that each project economic analysis include the system's
current annual costs and the actual expected annual costs if the
system is not privatized, and also stated that full implementation
of DOD's November 2005 guidance will provide further reassurance
that every conveyance will reduce the long-term costs of the
department compared to the costs of continued ownership. However,
as noted in our May 2005 report and again in this report, we
believe that in the short term it is clear that the utility
privatization program increases annual costs to the government
where contractors make system improvements and recoup their costs
from the department through their service contracts. DOD's sole
use of "should costs" as a basis for comparing its long-term costs
with those contained in contractor proposals provides a less clear
picture of savings to the government since, as our reports have
shown, the government's "should costs" do not provide a realistic
portrayal of the planned government expenditures. Accordingly, we
believe our recommendation continues to have merit.
DOD's comments and our detailed response to specific statements in
those comments are presented in appendix II.
We are sending copies of this report to other interested
congressional committees; the Secretaries of Defense, the Army,
the Navy, and the Air Force; and the Director, Office of
Management and Budget. We will also make copies available to
others upon request. In addition, the report will be available at
no charge on GAO's Web site at http://www.gao.gov .
If you or your staff have any questions about this report, please
call me at (202) 512-5581 or e-mail at [email protected] . Contact
points for our Offices of Congressional Relations and Public
Affairs may be found on the last page of this report. The GAO
staff members who made key contributions to this report are listed
in appendix III.
Barry W. Holman, Director Defense Capabilities and Management
List of Congressional Committees
The Honorable John Warner Chairman The Honorable Carl Levin
Ranking Minority Member Committee on Armed Services United States
Senate
The Honorable Ted Stevens Chairman The Honorable Daniel K. Inouye
Ranking Minority Member Subcommittee on Defense Committee on
Appropriations United States Senate
The Honorable Duncan L. Hunter Chairman The Honorable Ike Skelton
Ranking Minority Member Committee on Armed Services House of
Representatives
The Honorable C. W. Bill Young Chairman The Honorable John P.
Murtha Ranking Minority Member Subcommittee on Defense Committee
on Appropriations House of Representatives
Appendix I: Scope and Methodology
To update the status of the Department of Defense's (DOD) utility
privatization program, we summarized program implementation status
and costs and compared the status to DOD's past and current goals
and milestones. We discussed with DOD and service officials issues
affecting implementation of the program, such as the services'
suspension of the program between October 2005 and March 2006, and
inquired about the effects of implementation delays on program
completion plans. Using data from the services' quarterly program
status reports to DOD, we summarized the program implementation
status by service and compared the status to program status
reported in our prior report. We confirmed the quarterly reports'
status data on five privatization projects at the four
installations we visited but did not otherwise test the
reliability of the data. We also reviewed and summarized the
services' estimates of the additional number of systems that might
be privatized by the completion of their programs and the funds
needed to pay the costs associated with these anticipated
projects.
To assess the effect of DOD's changes on the program management
and oversight concerns noted in our May 2005 report, we documented
the changes made by interviewing DOD and service officials and
reviewing pertinent policies, guidance, memorandums, and reports,
discussed with DOD and service officials the intended objective
for each of the changes, and compared the changes with the
concerns identified in our prior report. To assess the effect of
DOD's changes on the reliability of the economic analyses
supporting privatization decisions, we reviewed the economic
analyses supporting 10 privatization projects that were awarded
after our May 2005 report and that had been subjected to the
services' new independent review processes. The analyses were
judgmentally selected to obtain examples from both the Army and
the Air Force. For each analysis, we evaluated the basis for the
estimates and assumptions used and assessed consistency and
compliance with DOD guidance. We did not otherwise attempt to
independently determine estimates of long-term costs for the
projects. We shared the results of our analyses with service
officials and incorporated their comments as appropriate. To
assess the effect of DOD's changes on consideration of increased
costs from utility privatization, we summarized the services'
estimates of the additional funds that would be needed to pay
costs associated with the remaining number of utility systems that
might be privatized and inquired about DOD's plans for dealing
with a potential program funding shortfall. To assess the effect
of DOD's changes on the administration and oversight of utility
privatization projects, we visited four installations with five
utility privatization projects awarded prior to our May 2005
report: Fort Eustis, Virginia; the Army's Military Ocean Terminal
Sunny Point, North Carolina; Bolling Air Force Base, Maryland; and
Dobbins Air Reserve Base, Georgia. These installations were
judgmentally selected because they represented a cross section of
typical utility privatization projects, as corroborated with
service officials. At each installation, we discussed resources
available for contract oversight and plans for contractor
performance monitoring. Also, to assess the effect of DOD's
changes on controlling cost growth in utility privatization
contracts, we reviewed cost changes in the five utility
privatization contracts at the installations we visited, discussed
the reasons for the changes with local officials, and compared the
actual contract costs with estimates from the projects' economic
analyses. We also reviewed cost changes in the Fort Rucker natural
gas privatization contract because, according to the services, it
was the only contract awarded under the legislative authority
specifically provided for utility privatization that had completed
a periodic price adjustment. To assess the effect of DOD's changes
on cost avoidance estimates from privatization, we reviewed the
estimates DOD reported to Congress to determine whether the
estimates reflected the actual changes expected in the
government's utility costs.
We conducted our review from March through July 2006 in accordance
with generally accepted government auditing standards.
Appendix II: Comments from the Department of Defense
Note: GAO comments supplementing those in the report text appear at the
end of this appendix.
See comment 1.
See comment 4.
See comment 3.
See comment 2.
See comment 5.
GAO's Response to the Department of Defense's Comments
The following is our detailed response to the Department of
Defense's (DOD) comments provided on August 21, 2006.
Our responses to DOD's comments are numbered below to correspond
with the department's various points.
1. As noted in this report, we identified concerns
with the independent review performed on each of the
10 economic analyses we reviewed. We did not attempt
in this report to prove that the questionable items
we identified with each analysis would have changed
the proposed outcomes but noted that improvements are
needed in the thoroughness of the independent reviews
that will be performed on future projects. Until DOD
requires independent reviewers to report to decision
makers on the thoroughness of the economic analyses
and any significant anomalies, we continue to believe
the reliability of the analyses could be questioned.
As outlined in our May 2005 report and this report,
to ensure a valid comparison of costs we continue to
believe that the government's "should cost" estimate
should be closely based on performing the same work
that the contractor would perform.
2. Our report does not suggest that postconveyance
reviews should be conducted prematurely as indicated
by DOD in its comments. The fact is that the utility
privatization contracts under 10 U.S.C. 2688
authority began to be awarded in 1999, about 7 years
ago, and postconveyance reviews do not appear to have
been performed on many ongoing utility privatization
contracts since that time. Although DOD noted in its
March 2006 report the importance of postconveyance
reviews as an additional measure to help ensure
reliable economic analyses, it has not issued
guidance to require the services to perform such
reviews.
3. Our report clearly shows that Air Force officials,
not GAO, stated that without additional resources,
funding for utility privatization contracts must come
from other base operating support funds, which would
result in diverting critical resources from remaining
facilities and infrastructure.
Furthermore, DOD's comment that utility sustainment
funds have been used for other base support
operations in the past only reinforces the need to
address the utility privatization program potential
funding shortfall. We have completed a number of
reviews in which we have identified examples where
the shifting of operation and maintenance funds from
one account to other accounts to fund must-pay bills
and other priorities contributes to management
problems and funding shortfalls. For example, in
February 2003, we reported that the services withheld
facilities sustainment funding to pay must-pay bills,
such as civilian pay, emergent needs, and other
nonsustainment programs, throughout the year and
transferred other funds back into facilities
sustainment at fiscal year's end.1 Still, the amounts
of funds spent on facilities sustainment were not
sufficient to reverse the trend in deterioration. In
June 2005, we reported that hundreds of millions of
dollars originally designated for facilities
sustainment and base operations support had been
redesignated by the services to pay for the Global
War on Terrorism.2 While installations received
additional funds at the end of the fiscal year to
help offset shortfalls endured during the year, the
timing made it difficult for the installations to
maintain facilities and provide base support services
efficiently and effectively. Similarly, unless the
potential funding shortfall in the utility
privatization program is addressed, funding will
likely have to be redesignated to fund the utility
privatization program rather than be used for its
intended purpose.
4. Our report raises concerns about the adequacy of
the services' oversight of several privatization
contracts that were awarded prior to DOD's November
2005 supplemental guidance. Given that the Office of
the Deputy Under Secretary of Defense (Installations
and Environment) has overall policy and management
oversight responsibilities for the utility
privatization program, we continue to believe that
this office is the appropriate level for providing
direction and assurance that utility privatization
contracts awarded prior to the supplemental guidance
have adequate resources and contractor performance
surveillance plans, as we recommend.
5. Our report highlights the importance of monitoring
cost growth because contractors have ownership of the
utility systems after privatization and, therefore,
may have an advantage when negotiating contract
changes and renewals. In addition, controlling the
potential growth in the cost of ongoing utilities
privatization contracts is important to the services
in their planning for the adequate funding of the
program. We did not review the effect of contract
cost growth on the government estimate because the
government estimate is not a relevant factor in
controlling costs once a system has been privatized.
Although a comparison of actual costs of a
privatization project with the estimates included in
the project's economic analysis is a useful tool to
help improve the reliability of analyses of future
privatization projects, it is unlikely that such
comparisons would assist in controlling cost growth.
Furthermore, DOD's comment refers to a "savings
delta." As noted in our May 2005 report and again in
this report, in the short term it is clear that the
utility privatization program increases annual costs
to the department where contractors make system
improvements and recoup their costs through the
service contracts.
Appendix III: GAO Contact and Staff Acknowledgments
GAO Contact
Barry W. Holman, (202) 512-5581 or ( [email protected] )
Acknowledgments
In addition to the person named above, Susan C. Ditto, Harry A.
Knobler, Katherine Lenane, Mark A. Little, Gary W. Phillips,
Sharon L. Reid, and John C. Wren also made major contributions to
this report.
GAO�s Mission
The Government Accountability Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in
meeting its constitutional responsibilities and to help improve
the performance and accountability of the federal government for
the American people. GAO examines the use of public funds;
evaluates federal programs and policies; and provides analyses,
recommendations, and other assistance to help Congress make
informed oversight, policy, and funding decisions. GAO's
commitment to good government is reflected in its core values of
accountability, integrity, and reliability.
Obtaining Copies of GAO Reports and Testimony
The fastest and easiest way to obtain copies of GAO documents at
no cost is through GAO's Web site ( www.gao.gov ). Each weekday,
GAO posts newly released reports, testimony, and correspondence on
its Web site. To have GAO e-mail you a list of newly posted
products every afternoon, go to www.gao.gov and select "Subscribe
to Updates."
Obtaining Copies of GAO Reports and Testimony
The first copy of each printed report is free. Additional copies
are $2 each. A check or money order should be made out to the
Superintendent of Documents. GAO also accepts VISA and Mastercard.
Orders for 100 or more copies mailed to a single address are
discounted 25 percent. Orders should be sent to:
U.S. Government Accountability Office 441 G Street NW, Room LM
Washington, D.C. 20548
To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax:
(202) 512-6061
To Report Fraud, Waste, and Abuse in Federal Programs
Contact:
Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail:
[email protected] Automated answering system: (800) 424-5454 or
(202) 512-7470
Congressional Relations
Gloria Jarmon, Managing Director, [email protected] (202) 512-4400
U.S. Government Accountability Office, 441 G Street NW, Room 7125
Washington, D.C. 20548
Public Affairs
Paul Anderson, Managing Director, [email protected] (202)
512-4800 U.S. Government Accountability Office, 441 G Street NW,
Room 7149 Washington, D.C. 20548
18Air Force officials stated that four additional utility privatization
contracts were previously eligible for periodic price adjustment but no
adjustment was made because neither the contractor nor the government
requested an adjustment.
19Pub. L. No. 109-163, S: 2823 (2006).
1GAO, Defense Infrastructure: Changes in Funding Priorities and Strategic
Planning Needed to Improve the Condition of Military Facilities,
GAO-03-274 (Washington, D.C.: Feb. 19, 2003).
2GAO, Defense Infrastructure: Issues Need to Be Addressed in Managing and
Funding Base Operations and Facilities Support, GAO-05-556 (Washington,
D.C.: June 15, 2005).
(350812)
www.gao.gov/cgi-bin/getrpt? GAO-06-914 .
To view the full product, including the scope and methodology, click on the link above.
For more information, contact Barry W. Holman at (202) 512-5581 or
[email protected].
Highlights of GAO-06-914 , a report to congressional committees
September 2006
DEFENSE INFRASTRUCTURE
Actions Taken to Improve the Management of Utility Privatization, but Some
Concerns Remain
Department of Defense (DOD) installations have about 2,600 electric,
water, wastewater, and natural gas utility systems valued at about $50
billion. In 1997, DOD decided that privatization was the preferred method
for improving utility systems, and Congress approved legislative authority
for privatizing DOD's utility systems with Public Law No. 105-85. DOD
estimates that some utility privatization contracts will cost over $100
million. In a May 2005 report, GAO identified several management
weaknesses in DOD's implementation of the program.
The Fiscal Year 2006 National Defense Authorization Act required GAO to
evaluate and report on changes to the utility privatization program since
May 2005. Accordingly, this report updates the status of the program and
discusses the effect of DOD's changes on the concerns noted last year. To
conduct this review, GAO summarized program status and costs, assessed
DOD's changes to program guidance and in other areas, and reviewed the
services' implementation of the changes.
What GAO Recommends
GAO is making seven recommendations to improve the management of the
utility privatization program. DOD generally agreed with six and indicated
disagreement with one recommendation. Still, GAO believes this
recommendation continues to have merit.
DOD's progress in implementing the utility privatization program has been
slower than expected and the estimated completion date has slipped from
the department's target of September 2005 to September 2011. DOD
attributed the delays to the complexity of the program and to the
services' decision to suspend and reassess the management of the program
between October 2005 and March 2006. Since May 2005, the services
privatized 14 utility systems under the legislative authority for the
program, bringing the total number of awarded projects to 81. However, the
services have awarded no projects since DOD issued new program guidance in
November 2005. Meanwhile, the services' total estimated program
implementation costs through fiscal year 2006 have increased to $285
million, and more funds will be required before the program is completed
in 2011.
Since GAO's May 2005 report, DOD has issued new guidance and required
changes in procedures. If fully implemented, these changes should result
in more reliable economic analyses, improved budgetary consideration of
increased utility costs, enhanced oversight of privatization contracts,
and reduced instances where contractors recover more than the fair market
value paid for system conveyances. However, a number of concerns from the
May 2005 report remain. For example:
o Although DOD made changes to improve the reliability of project
economic analyses by requiring independent reviews, GAO reviewed
10 economic analyses and found reliability issues that had not
been identified during the independent reviews.
o DOD directed the services to adequately consider in their
budgets the increased costs resulting from utility privatization.
However, questions remain over the availability of the funds
needed to complete the program because the services estimate that
they will need $453 million more than is currently programmed to
pay costs associated with remaining utility systems that might be
privatized.
o Although DOD made many changes to improve contract
administration and oversight, it may take some time to fully
implement the changes as new privatization contracts are awarded.
GAO's review of five projects awarded prior to DOD's changes found
continuing questions about the adequacy of resources provided to
perform oversight and the lack of required plans for overseeing
contractor performance.
o It is too early in the program's implementation to know to what
extent DOD's efforts will be successful in ensuring equitable
periodic contract price adjustments and limiting long-term cost
growth in the utility privatization program. However, GAO found
indications that cost growth may become a challenge.
o DOD did not change its guidance to require that project
economic analyses depict the actual expected costs of continued
government ownership if the systems are not privatized. Therefore,
DOD's reported $650 million in long-term cost reductions is
unrealistic.
*** End of document. ***