Bureau of Land Management: Plan Needed to Sustain Progress in
Establishing IT Investment Management Capabilities (12-SEP-03,
GAO-03-1025).
The mission of the Department of the Interior's Bureau of Land
Management (BLM) is to maintain the health, diversity, and
productivity of the public lands for the use and enjoyment of
present and future generations. BLM employs about 11,000 people,
with information technology (IT) playing a critical role in
helping BLM perform its responsibilities. The bureau estimates
that it will spend about $146 million on IT initiatives in fiscal
year 2003. GAO was asked to evaluate BLM's IT investment
management (ITIM) capabilities and determine the bureau's plans
for improving these capabilities. GAO's evaluation was based on
applying its ITIM maturity framework, which identifies critical
processes for successful IT investment management.
-------------------------Indexing Terms-------------------------
REPORTNUM: GAO-03-1025
ACCNO: A08417
TITLE: Bureau of Land Management: Plan Needed to Sustain
Progress in Establishing IT Investment Management Capabilities
DATE: 09/12/2003
SUBJECT: ADP procurement
Best practices
Financial management
Information resources management
Information technology
Management information systems
Procurement practices
Strategic information systems planning
BLM Budget Planning System
******************************************************************
** This file contains an ASCII representation of the text of a **
** GAO Product. **
** **
** No attempt has been made to display graphic images, although **
** figure captions are reproduced. Tables are included, but **
** may not resemble those in the printed version. **
** **
** Please see the PDF (Portable Document Format) file, when **
** available, for a complete electronic file of the printed **
** document's contents. **
** **
******************************************************************
GAO-03-1025
A
Report to the Subcommittee on Interior and Related Agencies, Committee on
Appropriations, House of Representatives
September 2003 BUREAU OF LAND MANAGEMENT Plan Needed to Sustain Progress
in Establishing IT Investment Management Capabilities
GAO- 03- 1025
Contents Letter 1
Results in Brief 2 Background 3 BLM Has Established Many of the Key
Practices for Effective
Investment Management 12 BLM Does Not Have a Plan to Guide IT Investment
Management
Improvement Efforts 27 Conclusions 28 Recommendations for Executive Action
28 Agency Comments and Our Evaluation 29
Appendixes
Appendix I: Objectives, Scope, and Methodology 31
Appendix II: Comments from the Bureau of Land Management 34 Tables Table
1: Stage 2 Critical Processes* Building the Investment
Foundation 13 Table 2: Summary of Results for Stage 2 Critical Processes
and Key Practices 14
Table 3: IT Investment Board Operation 16 Table 4: IT Project and System
Identification 19 Table 5: IT Project Oversight 21 Table 6: Business Needs
Identification 24 Table 7: Proposal Selection 26
Figures Figure 1: BLM*s IT Investment Management Process 9 Figure 2: The
Five Stages of Maturity with Critical Processes 11
Abbreviations
BLM Bureau of Land Management CIO chief information officer IT information
technology ITIB Information Technology Investment Board ITIM information
technology investment management
This is a work of the U. S. government and is not subject to copyright
protection in the United States. It may be reproduced and distributed in
its entirety without further permission from GAO. However, because this
work may contain copyrighted images or other material, permission from the
copyright holder may be necessary if you wish to reproduce this material
separately.
Letter
September 12, 2003 The Honorable Charles H. Taylor Chairman The Honorable
Norman D. Dicks Ranking Minority Member Subcommittee on Interior and
Related Agencies Committee on Appropriations House of Representatives The
mission of the Department of the Interior*s Bureau of Land Management
(BLM) is to maintain the health, diversity, and productivity of public
lands for the use and enjoyment of present and future generations. To
carry out the functions involved in managing the public lands, BLM employs
a workforce of about 11,000 employees located in headquarters in
Washington, D. C., state offices, field offices, and national centers
specializing in training, fire management support, science and technology,
human resources management, information resources management, and business
services. Information technology (IT) plays a critical role in helping BLM
carry out its responsibilities. The bureau estimates that it will spend
about $146 million on IT initiatives in fiscal year 2003.
This report is one of two in response to your request to evaluate the
Department of the Interior*s IT investment management process. 1 As
agreed, the objectives of our review were to (1) evaluate BLM*s IT
investment management capabilities against the key practices defined in
our IT investment management assessment framework 2 and (2) determine the
agency*s plans for improving these capabilities. We performed our work in
accordance with generally accepted government accounting standards.
Details on our objectives, scope, and methodology are contained in
appendix I.
1 The second report, U. S. General Accounting Office, Information
Technology Departmental Leadership Crucial to Success of Investment
Reforms at Interior, GAO- 03- 1028 (Washington, D. C.: Sept. 12, 2003)
addresses (1) the Department of the Interior*s capabilities
for managing the agency*s IT investments, including its ability to
effectively overseee bureau processes, and (2) the department*s actions
and plans to improve these capabilities.
2 U. S. General Accounting Office, Information Technology Investment
Management: A Framework for Assessing and Improving Process Maturity
(Exposure Draft), GAO/ AIMD10. 1.23 (Washington, D. C.: May 2000).
Results in Brief BLM has made progress in establishing key practices for
effectively managing its IT investments, including the foundational
practices for
selecting and controlling IT investments, which provide assurance that
projects selected meet organizational needs and will be completed on time
and within budget, and the practices for managing investments as a
portfolio. Specifically,
BLM has established most of the key practices (about 85 percent)
associated with building the investment foundation. For example, BLM has
defined and established an investment board for managing IT investments,
implemented processes to ensure that projects support
business needs and meet users* requirements, and established a process for
selecting proposals. Although the agency has not yet, for example, defined
policies and procedures for collecting information into its project and
system inventory to make informed investment management decisions or fully
defined criteria for analyzing and prioritizing new proposals, it
recognizes the importance of resolving these issues and has efforts under
way to address them.
BLM has also initiated efforts to manage its investments as a portfolio*
that is, as a set of competing IT investments* and has begun to address
the evaluation of projects and systems after development using
postimplementation reviews, 3 a critical process associated with the most
capable organizations. For example, BLM has established a council to
support portfolio management activities and begun defining portfolio
selection criteria. BLM has also performed
postimplementation reviews on a limited basis to learn lessons that will
help define and implement a robust IT investment evaluation process.
Although BLM is clearly committed to further developing its IT investment
process, it has not developed a plan to guide its efforts to do so, and,
as a result, may not be able to successfully establish mature IT
investment management processes. According to the chief information
officer (CIO), this is because BLM wanted to develop a plan that is
integrated with improvement plans for other IT management areas, and the
results of the
comprehensive assessment that were to be used as the basis for such a plan
were obtained only in June 2003. BLM officials stated their intention to
3 BLM refers to postimplementation reviews as postdeployment reviews.
develop a plan to guide improvement efforts. By developing such a plan,
BLM would be able to sustain progress made to date. To strengthen BLM*s
investment management capability, we are recommending that BLM develop and
implement a plan aimed at addressing the weaknesses identified in this
report. In written comments on a draft of this report (reprinted in app.
II), BLM*s Director agreed with our findings and recommendations and
stated that they represented a fair and accurate evaluation of the
bureau*s status and progress towards IT investment management maturity.
BLM also provided additional technical comments, which we have
incorporated into the report as appropriate.
Background BLM, an agency of the U. S. Department of the Interior, manages
261 million surface acres and an additional 700 million acres of
subsurface mineral
estate throughout the nation. The agency*s mission is to maintain the
health, diversity, and productivity of public lands for the use and
enjoyment of present and future generations. To carry out this mission,
BLM employs a workforce of about 11,000 employees located in headquarters
in Washington, D. C., 12 state offices, 130 field offices, and national
centers
specializing in training, fire management support, science and technology,
human resources management, information resources management, and business
services.
BLM*s Use of IT BLM collects, analyzes, and records a tremendous amount of
business information about the public lands and resources, ranging from
land title to recreational usage to wildlife habitat. These data are
mainly geographic in character and are best understood when displayed and
analyzed in spatial
form using automated geographic information systems. Numerous parties*
including public land users; educational institutions; public interest
groups; other federal, state, tribal, and local agencies; and the
scientific community* use these data or information to make thousands of
business decisions each year.
The central focus of BLM*s IT strategy is to develop integrated systems
that help BLM meet national and local needs in managing the lands and
natural resources, while supporting the mission and goals outlined in
BLM*s Strategic Plan. For example, BLM uses its Automated Fluid Minerals
Support System to support its Oil and Gas Program. The system helps match
mineral estate information to information on existing wells,
facilities, permits, and inspections and provides an automated system for
granting permits to BLM customers and creating reports. Currently, BLM
issues approximately 41,000 permits and reports and conducts about 19,000
inspections per year. BLM also uses its Management Information System,
which provides a Web- enabled, business information, budgetary, financial,
and program performance system so that simple data analysis can be
performed benefiting the entire bureau. This system provides managers with
up- to- date business data to make cost effective decisions concerning the
management of BLM*s people, resources, and natural resources for several
of Interior*s mission goals. BLM*s estimated IT expenditures are $146.45
million for fiscal year 2003.
Prior Weaknesses in BLM*s Between 1995 and 2001, we conducted reviews and
issued several reports
IT Investment Management on problems and risks that threatened the
successful development and
Process deployment of BLM*s modernization of its Automated Land and
Mineral
Record System. In a recent report addressing this issue, we noted, among
other things, that after 15 years and about $411 million obligated, the
project was terminated because the Initial Operating Capability module* a
major component of the system* did not meet BLM*s business needs and
therefore could not be deployed. 4 We also reported that the absence of
adequate investment management processes and practices at BLM was a
significant factor contributing to the failure of the system. Accordingly,
we recommended that the Secretary of the Interior direct BLM to take
certain actions to help it strengthen its investment management process.
BLM has
been working on improving its process since that time. BLM*s Approach to
BLM has assigned several individuals and groups with responsibilities for
Investment Management
managing national IT investments, that is investments which, among other
things, are considered major applications or general support systems; have
a life- cycle value of greater than $500,000; or will affect multiple
states, centers, or business areas. 5 These individuals and groups and
their roles are described below. 4 U. S. General Accounting Office, Land
Management Systems: Status of BLM*s Actions to
Improve Information Technology Management, GAO/ AIMD- 00- 67 (Washington,
D. C.: Feb. 27, 2000). 5 Other criteria for national investments include
investments between $50,000 and $500,000 for which a state or center does
not have its own ITIB, and operations and maintenance investments that are
not included in program base funding.
National Information Technology Investment Board (ITIB)* Chaired by
BLM*s Deputy Director of Operations, this board is responsible for
selecting, controlling, and evaluating all national IT investments.
Members include the CIO, Chief Financial Officer, Assistant Directors from
the business units, two State Directors, an Associate State Director, the
CIO Council Chair, the Bureau Architecture Chair, a Fire and Aviation
Portfolio Representative, and several ex officio members including
Interior*s CIO, the bureau Architect, and managers from the System
Coordination Office and the Investment Management Group.
System Coordination Office* Created in June 2000 to support a number of
IT management functions, the System Coordination Office, among other
things, is responsible for coordinating the screening of all
IT investments and projects to ensure that they are in line with the
bureau*s selection, control, and evaluation criteria, and monitors project
performance (scope, schedule, and budget). The office is also responsible
for coordinating the development of a project management
curriculum and mentoring and developing a cadre of trained and experienced
project managers. Investment Management Group* Responsibilities of this
group include
coordinating the development and maintenance of the bureau*s IT investment
portfolio, ensuring that all investments fit within budget constraints,
and providing investment updates and forecasting as needed.
Information Technology Portfolio Management Council* Chartered in June
2003, but established about a year ago, this council serves as an advisory
council to the ITIB and is responsible, among other things, for applying
business- related rating and ranking criteria to BLM*s portfolio,
performing trade- off analyses, and working with the Investment
Management Group to develop funding strategies. The council is also
responsible for ensuring that investments are clearly tied to the mission
and strategic plans (both business and information resources management)
of the bureau and selected by a consistent, repeatable,
objective process. Members include national IT portfolio managers 6 for
each of the directorates, representatives from the state portfolios and
the Bureau Enterprise Architecture Team, and members from the System
Coordination Office and the Investment Management Group.
Bureau Enterprise Architecture Team* Responsible for ensuring that
investment proposals and business cases are aligned with the bureau
enterprise architecture*s business processes, data, applications, and
technology components. 7 Project proponent* Responsible, among other
things, for leading the development of the investment proposal,
coordinating and championing the development of the business case, and
working with the project manager throughout the life cycle of the project.
Project sponsor* A field, center, or Washington office manager who
authorizes the development of a business case. The project sponsor shifts
roles to become the system owner when the project moves into operations
and maintenance. The project sponsor is responsible for selecting a
project manager, approving all project documentation, and participating in
a management oversight role throughout the planning,
design, development, testing, acceptance, and deployment of the project.
Project manager* Responsible for developing the project plan and leading
and managing the project. The project manager reports directly to the
project sponsor. Ultimately, it is the project managers who
6 Portfolio managers are responsible for ensuring that all IT investment
proposals, national systems, and externally directed systems are planned,
developed, maintained, and distributed according to the bureau*s ITIM
process and configuration management, and are in conformance with
established bureau hardware and software standards, as well as the
bureau*s architecture and technical reference model; summarizing all
operations and maintenance costs associated with existing and proposed
systems; ensuring that all new project proposals address the
discontinuance of existing systems as a cost saving measure; and working
directly with each state or center that proposes moving a state, center,
or local application to a national system.
7 An enterprise architecture is an investment blueprint that defines, both
in logical terms (including business functions and applications) and in
technical terms (including hardware, software, data communications, and
security), how an organization operates today (current architecture), how
it intends to operate tomorrow (target architecture), and a road map for
making the transition from today to tomorrow.
are responsible for successfully managing and completing one or more
projects approved by the ITIB.
The bureau has also defined a three- phase IT investment management
process which involves selecting proposed IT projects (select phase),
controlling ongoing projects through development (control phase), and
evaluating projects that have been deployed (evaluate phase). Each phase
comprises multiple stages that have entrance and exit criteria defined in
the IT Investment Management Process guide that must be satisfied before a
project can move from one stage to the next stage or phase in the process.
The System Coordination Office tracks projects* progress through the
various stages, ensuring that they comply with the processes defined in
the guide. The national ITIB stays abreast of projects* performance
through quarterly report reviews. The board is also directly involved in
key milestone (i. e., stage) reviews.
Select Phase The purpose of the phase is to ensure that BLM chooses the IT
projects that best support its mission and align with the bureau*s
architecture. During this phase, the project proponent and portfolio
manager are expected to collaborate to develop an investment proposal.
The System Coordination Office is responsible for reviewing the proposal
and ensuring that issues are identified and resolved. Finally, the ITIB is
to review the proposal and either approve it, approve it with
stipulations, return it for further analysis, or reject it. If the ITIB
approves the proposal, the project manager and project proponent are to
work to develop a more elaborate business case. The System Coordination
Office reviews the business case and coordinates the reviews performed by
other groups (e. g., the Bureau Enterprise Architecture Team). The Office
then makes recommendations for approval to the ITIB on the basis of these
reviews.
At the end of the select phase, a project plan is to be developed that
defines the strategies for managing the project. According to BLM
officials, to date the ITIB has placed more emphasis on this phase than on
the other two.
Control Phase Once selected for inclusion in the bureau*s IT portfolio,
each project is to be managed by a trained or experienced IT project
manager and monitored by the System Coordination Office and ITIB on a
quarterly basis throughout its life cycle.
Included within the project*s plan, which is developed at the end of the
select phase, are milestones for architecture, technical, and project
management reviews. Factors such as project risk, complexity, and cost
determine the scope and frequency of each of these milestone reviews.
Projects that fall short of meeting their predetermined budget, schedule,
or scope requirements are to be reviewed by the ITIB, who works with the
project managers to develop an appropriate course of action. If this issue
arises, the ITIB must decide whether to continue the project; rebaseline
the scope, schedule, or budget; or to terminate the project. Ultimately,
all decisions that are carried out are a result of the ITIB voting
process.
Evaluate Phase Once a project has been fully implemented and accepted by
the users and system owner, the System Coordination Office and ITIB are
responsible for monitoring its schedule and budget quarterly. BLM has
also, on a limited basis, begun performing postimplementation reviews* BLM
refers to these as postdeployment reviews* in which a project*s actual
results are to be evaluated against expected results to compare realized
to estimated benefits and assess the project*s impact on mission
performance.
Necessary changes or modifications to the project are to be identified,
and technical compliance with the bureau enterprise architecture is also
to be assessed. The main objective of the postimplementation review is to
derive lessons learned, which may lead to investment management process
improvements and opportunities for improving business processes (which in
turn provide input into the select phase). To date, BLM has performed
postimplementation reviews for two systems.
Figure 1 illustrates BLM*s IT investment management process phases and
stages. The highlighted stages represent those for which the ITIB must
make an approval decision before a project can move forward.
Figure 1: BLM*s IT Investment Management Process
ITIM Maturity Framework On the basis of research into the IT investment
management practices of leading private- and public- sector organizations,
we have developed an
information technology investment management (ITIM) maturity framework. 8
This framework identifies critical processes for successful IT investments
organized into a framework of five increasingly mature stages. The ITIM is
intended to be used as both a management tool for implementing these
processes incrementally and an evaluation tool for determining an
organization*s current level of maturity. The overriding purpose of the
framework is to encourage investment processes that increase business
value and mission performance, reduce risk, and increase accountability
and transparency in the decision process. This framework has been used in
several GAO evaluations 9 and adopted by a number of agencies. These
agencies have used ITIM for purposes ranging from self- assessment to
redesign of their IT investment management processes.
ITIM is a hierarchical model comprising five *maturity stages.* These
maturity stages represent steps toward achieving stable and mature
processes for managing IT investments. Each stage builds upon the lower
stages; the successful achievement of each stage leads to improvement in
the organization*s ability to manage its investments. With the exception
of the first stage, each maturity stage is composed of *critical
processes* that must be implemented and institutionalized for the
organization to achieve that stage. These critical processes are further
broken down into key practices that describe the types of activities that
an organization should be performing to successfully implement each
critical process. An organization may be performing key practices from
more than one maturity stage at one time. This is not unusual, but efforts
to improve investment management capabilities should focus on becoming
compliant with lower stage practices before addressing higher stage
practices.
8 GAO/ AIMD- 10. 1.23. 9 U. S. General Accounting Office, Information
Technology: INS Needs to Strengthen Its Investment Management Capability,
GAO- 01- 146 (Washington, D. C.: Dec. 29, 2000);
Information Technology Management: Social Security Administration
Practices Can Be Improved, GAO- 01- 961 (Washington, D. C.: Aug. 21,
2001); Information Technology: DLA Needs to Strengthen Its Investment
Management Capability, GAO- 02- 314 (Washington, D. C.: Mar. 15, 2002);
United States Postal Service: Opportunities to Strengthen IT Investment
Management Capabilities, GAO- 03- 3 (Washington D. C.: Oct. 15, 2002);
Information Technology: Executive Office for U. S. Attorneys Needs to
Institutionalize Key IT Management Disciplines, GAO- 03- 751 (Washington,
D. C.: July 25, 2003).
Stage 2 in the ITIM framework encompasses building a sound investment
management process* by developing the capability to control projects so
that they finish predictably within established cost and schedule
expectations* and establishing basic capabilities for selecting new IT
projects. Stage 3 requires that an organization continually assess
proposed
and ongoing projects as parts of a complete investment portfolio: an
integrated and competing set of investment options. This approach enables
the organization to consider the relative costs, benefits, and risks of
newly proposed investments along with those previously funded and to
identify the optimal mix of IT investments to meet its mission,
strategies, and goals. Stages 4 and 5 require the use of evaluation
techniques to continuously improve both the investment portfolio and
investment processes to better achieve strategic outcomes. Figure 2 shows
the five maturity stages and the associated critical processes.
Figure 2: The Five Stages of Maturity with Critical Processes
As defined by the model, each critical process consists of *key practices*
that must be executed to implement the critical process.
BLM Has Established In order to have the capabilities to effectively
manage IT investments, an
Many of the Key agency should (1) have basic, project- level control and
selection practices
in place (stage 2 capabilities) and (2) manage its projects as a portfolio
of Practices for Effective investments, treating them as an integrated
package of competing
Investment investment options and pursuing those that best meet the
strategic goals, Management
objectives, and mission of the agency (stage 3 capabilities). In addition,
an agency would be well served by implementing capabilities for improving
its investment management process (stage 4 capabilities).
BLM has executed the majority of the project- level control and selection
practices. The bureau has also initiated efforts to manage its projects as
a portfolio and performed two postimplementation reviews to learn lessons
to improve its investment management process. When BLM implements all
critical processes associated with building an investment foundation and
managing its projects as a portfolio, the bureau will have greater
confidence that it has selected the mix of projects that best supports its
strategic goals and that the projects will be managed to successful
completion.
BLM Has Implemented Most At ITIM stage 2 maturity, an organization has
attained repeatable, of the Key Practices
successful IT project- level investment control processes and basic
Required to Establish selection processes. Through these processes, the
organization can identify an IT Investment
expectation gaps early and take appropriate steps to address them.
According to ITIM, critical processes at stage 2 include (1) defining
Foundation
investment review board 10 operations, (2) collecting information about
existing investments, (3) developing project- level investment control
processes, (4) identifying the business needs for each IT project, and (5)
developing a basic process for selecting new IT proposals. Table 1
discusses the purpose for each of the stage 2 critical processes.
10 An investment review board is a decision- making body made up of senior
program, financial, and information managers that is responsible for
making decisions about investments or projects.
Tabl e 1: Stage 2 Critical Processes* Building the Investment Foundation
Critical process Purpose
IT investment board operation To define and establish the governing board(
s) responsible for selecting, controlling, and evaluating IT investments.
IT project and system
To create and maintain an IT project inventory to assist in identification
managerial decision making.
IT project oversight To regularly determine each IT project's progress
toward cost and schedule milestones using established criteria and take
corrective actions when milestones are not achieved.
Business needs identification To ensure that each IT project supports the
for IT projects organization's business needs and meets users' needs.
Proposal selection To ensure that an established, structured process is
used to select new IT proposals.
Source: GAO.
To its credit, BLM has put in place about 85 percent of the key practices
associated with stage 2 critical processes. 11 The bureau has satisfied
all the key practices associated with establishing the governing boards
responsible for managing IT investments and ensuring that IT projects
support organizational needs and meet users* needs. It has satisfied a
majority of the key practices associated with proposal selection and IT
project oversight and is working on incorporating the use of an IT project
and system inventory into its IT investment management process. Table 2
summarizes the status of BLM*s critical processes for stage 2, showing how
many associated key practices it has executed.
11 BLM hired a contractor to perform an independent assessment of its ITIM
stage 2 capabilities, which was completed in January 2003. The assessment,
which indicated that BLM had established the majority of key practices for
four out of five critical processes, provided an important source of data
for our evaluation.
Table 2: Summary of Results for Stage 2 Critical Processes and Key
Practices Total required Key practices
by critical Percentage of key Critical process executed
process practices executed
IT investment board operation 6 6 100% IT project and system
3 7 42% identification IT project oversight 10 11 91%
Business needs identification 8 8 100% Proposal selection 5 6 83%
Total 32 38 84%
Source: GAO.
BLM Has Established an The creation of decision- making bodies or boards
is central to the IT
Investment Board for Managing investment management process. At the stage
2 level of maturity,
IT Investments organizations define one or more boards, provide resources
to support
their operations, and appoint members who have expertise in both
operational and technical aspects of proposed investments. Resources
provided to support the operations of IT investment boards typically
include top management*s participation in creating the board( s) and
defining their scope and formal evidence acknowledging management*s
support for board decisions. The boards operate according to a written IT
investment process guide tailored to the organization*s unique
characteristics, thus ensuring that consistent and effective management
practices are implemented across the organization. Once board members are
selected, the organization ensures that they are knowledgeable about
policies and procedures for managing investments. Organizations at the
stage 2 level of maturity also take steps to ensure that executives and
line managers support and carry out the decisions of the IT investment
board. According to ITIM, an IT investment management process guide should
be
a key authoritative document that the organization uses to initiate and
manage IT investment processes and should provide a comprehensive
foundation for policies and procedures developed for all other related
processes. (The complete list of key practices is provided in table 3.)
BLM has executed all the key practices for this critical process. For
example, in 1998, the bureau established an IT Investment Board (the ITIB)
to manage national investments. With the development of the IT Investment
Management Process guide in 2001, BLM provided the board and all involved
parties (i. e., project managers and sponsors, portfolio
managers, investment management group) with specifics concerning
responsibilities and procedures. 12 This guide is centered on a project*s
life cycle and requisite decision points (phases and stages) in the
investment process from the submission of a proposal to a
postimplementation review.
The board is also adequately resourced, with the main support being
provided by the System Coordination Office, whose responsibilities include
developing and modifying the bureau*s criteria for selecting, controlling,
and evaluating potential and existing IT investments and documenting,
recording, and transmitting decisions made by the board. Experienced
senior- level officials from both business and IT areas are members of the
board and exhibit the core competencies required by the investment
management process. Finally, all actions by the board are well documented
using meeting minutes and records of decision. In June 2003, an action-
item
tracking matrix was introduced. This matrix is used to identify and track
ITIB- approved decisions and assigned responsibilities to ensure that the
board*s decisions are carried out. By executing all key practices
associated with creating and defining investment board operations, BLM has
greater assurance that the ITIB will effectively carry out its
responsibilities. Table 3 shows the rating for each key practice required
to implement the critical process for establishing IT investment board
operation at the stage 2 level of maturity. Each of the *Executed* ratings
shown below represents instances where, based on the evidence provided by
BLM officials, we concluded that the specific key practices were executed
by the organization.
12 According to BLM *Instruction Memorandum 2001- 222,* this policy
expired on September 30, 2002. BLM still continues to use this version to
guide IT investment management efforts. A newer version is currently in
draft, but no expected release date was identified.
Table 3: IT Investment Board Operation Type of practice Key practice
Rating Summary of evidence
Organizational 1. An organization- specific Executed BLM*s IT Investment
Management Process guide and associated memo commitments IT investment
process guide
issued in September of 2001 direct the national ITIB*s operations. The IT
is created to direct each investment board*s charter updated in April 2003
also defines operating board's operations. procedures for the board.
2. Organization executives Executed BLM established the System
Coordination Office to, among other things, and line managers support
support the investment management process. The office*s and carry out IT
investment responsibilities include ensuring that the ITIB*s decisions are
carried out board decisions. by documenting and communicating these
decisions and tracking
actions to support them. The ITIB recently adopted an action- item
tracking matrix to better track decisions made, assigned responsibilities,
and established time frames related to board decisions. Prerequisites 1.
Adequate resources are Executed A number of resources support the ITIB*s
operations. They include the
provided for operating each System Coordination Office which, among other
things, screens IT IT investment board.
investment proposals and monitors project performance; the Investment
Management Group, which helps ensure that IT investments fit within BLM*s
budget plan; and an IT Portfolio Management Council that is responsible
for providing the board with an enterprise view of the bureau*s various
portfolios. The BLM intranet also features an *ITIB Membership Guide Book*
site that contains links to information on the ITIM process and related
resources. 2. Board members
Executed Board members understand the investment board*s policies and
understand the investment procedures and have experience in making
investment management board's policies and decisions. High- level training
has been provided to members during past procedures and exhibit core
board meetings on an informal basis. In addition, BLM plans to provide
competencies in using the
more formal training that addresses the core competencies that IT
investment approach via
members should have in order to more effectively contribute to the ITIM
training, education, or process. This first formal training session is
expected to be conducted in experience.
November 2003. Activities 1. Each IT investment board
Executed The ITIB membership includes both IT and business knowledge. It
is created and defined with
includes the CIO (also the Vice Chair); and representatives from the board
membership
System Coordination Office; state, center, and field offices; Bureau
integrating both IT and
Enterprise Architecture Team; and budget areas. business knowledge. 2.
Each IT investment board
Executed ITIB operations are guided by BLM*s IT Investment Management
operates according to
Process guide, its associated instruction memo, and the ITIB charter.
written policies and The guide specifies procedures for selecting,
controlling, and evaluating procedures in the
investments, while the ITIB charter contains specific operating
organization- specific IT
procedures. investment process guide.
Source: GAO.
BLM Has Not Defined Policies An IT project and system inventory provides
information to investment
and Procedures for Collecting decision makers to help evaluate the impacts
and opportunities created by
Information into the Budget proposed or continuing investments. This
inventory (which can take many Planning System to Make
forms) should, at a minimum, identify the organization*s IT projects
Informed Investment
(including new and existing systems) and a defined set of relevant
Management Decisions
investment management information about them (e. g., purpose, owner,
lifecycle stage, budget cost, physical location, and interfaces with other
systems). Information from the IT project and system inventory can, for
example, help identify systems across the organization that provide
similar functions and help avoid the commitment of additional funds for
redundant systems and processes. It can also help determine more precise
development and enhancement costs by informing decision makers and other
managers of interdependencies among systems and how potential
changes in one system can affect the performance of other systems.
According to ITIM, effectively managing an IT project and system inventory
requires, among other things, (1) identifying projects and systems,
collecting relevant information about them, and capturing this information
in a repository; (2) assigning responsibility for managing the inventory
process and ensuring that the inventory meets the needs of the investment
management process; (3) developing written policies and procedures for
maintaining the project and system inventory; (4) making information from
the inventory available to staff and managers throughout the organization
so they can use it, for example, to build business cases and support
activities to select and control projects; and (5) maintaining the
inventory and its information records to contribute to future investment
selections and assessments. (The full list of key practices is provided in
table 4.)
BLM has executed three out of seven of the key practices for IT project
and system identification. For example, the bureau is using its target
application architecture and Budget Planning System 13 to collect
information on its IT projects and systems to make informed IT investment
management decisions; according to CIO officials, the architecture is used
for the information it contains on BLM*s business processes and supporting
data, applications, and technology, while the Budget Planning System is
used for the financial information on the investments. Resources have been
assigned to support activities related to identifying IT projects and
systems, including the Bureau Enterprise Architecture Team and the Budget
13 The Budget Planning System is part of BLM's larger Financial Management
System. It contains financial data on individual investments. These data
can be directly tied to annual budget submissions.
Planning System system owners. According to BLM, all national projects and
systems are in both the target application architecture and Budget
Planning System (although BLM officials told us that they have planned a
meeting to determine whether additional requirements are needed for the
Budget Planning System to effectively serve as an inventory for investment
management purposes).
Despite these strengths, policies and procedures for collecting project
and system information in the Budget Planning System for investment
management purposes have not yet been defined. However, the CIO has
directed teams composed of the System Coordination Office, portfolio
managers, the Investment Management Group, and system owners of the Budget
Planning System to *identify the ownership of each process associated with
the IT project and system inventory.* This step would form the basis for
policies and procedures relating to the collection (and use) of
information in the inventory. Until BLM defines these policies and
procedures, it cannot adequately ensure that its inventory can be relied
upon as an effective tool to assist in investment decision making. Table 4
shows the rating for each key practice required to implement the critical
process for IT project and system identification at the stage 2 level of
maturity and summarizes the evidence that supports these ratings.
Table 4: IT Project and System Identification Type of practice Key
practice Rating Summary of evidence
Organizational 1. The organization has written policies Not executed BLM
is using its enterprise architecture and Budget commitments and procedures
for identifying its IT
Planning System to collect information about its IT projects and systems
and collecting, in
projects and systems. However, the bureau has not yet an inventory,
information about the IT
defined the policies and procedures associated with projects and systems
that is relevant to
collecting information in the Budget Planning System for the investment
management process.
investment management purposes. 2. An official is assigned responsibility
Executed According to the ITIB charter, it is the ITIB*s responsibility
for managing the IT project and system
to manage the IT project and system identification process identification
process and ensuring that
and ensure that the inventory meets the needs of the the inventory meets
the needs of the investment management process. According to BLM*s
investment management process.
self- assessment, in practice, this responsibility has been delegated to
the Bureau Enterprise Architecture Team for the architecture and to the
System Coordination Office for the Budget Planning System.
Prerequisite 1. Adequate resources are provided for Executed Resources for
IT project and system identification identifying IT projects and systems
and
activities include contractor support for the enterprise collecting
relevant information into an architecture and the Budget Planning System
system inventory.
owners. Activities 1. The organization's IT projects and Executed
According to BLM officials, all national projects and systems are
identified, and specific systems are in the enterprise architecture*s
target
information about them is collected in application component and in the
Budget Planning an inventory. System. 2. Changes to IT projects and
systems Not executed According to BLM, changes to projects and systems are
are identified, and change information
not reliably being maintained in the inventory. is maintained in the
inventory.
3. Information from the inventory is Not executed Information from the
enterprise architecture and the available on demand to decision Budget
Planning System is available to decision makers makers and other affected
parties.
and other affected parties through BLM*s intranet site. However, this
information is not reliable because, according to BLM, it is not being
maintained in a consistent manner (see activity 2).
4. The IT project and system inventory Not executed According to BLM,
changes to projects and systems are and its information records are
not reliably being maintained in the inventory. maintained to contribute
to future investment selections and
assessments. Source: GAO.
Projects* Progress Toward Cost Investment boards should effectively
oversee IT projects throughout all
and Schedule Milestones Is life- cycle phases (concept, design, testing,
implementation, and
Regularly Determined operations/ maintenance). At the stage 2 level of
maturity, investment
boards should review each project*s progress toward predefined cost and
schedule expectations, using established criteria and performance
measures, and take corrective actions to address cost and milestone
variances. According to ITIM, effective project oversight requires, among
other things, (1) having written policies and procedures for project
management; (2) developing and maintaining an approved management plan for
each IT project; (3) making up- to- date cost and schedule data for
each project available to the oversight boards; (4) reviewing each
project*s performance by regularly comparing actual cost and schedule data
with expectations; (5) ensuring that corrective actions for each
underperforming project are documented, agreed to, implemented, and
tracked until the desired outcome is achieved; and (6) having written
policies and procedures for oversight of IT projects. (The complete list
of key practices is provided in table 5.)
BLM has in place all but one of the key practices associated with
effective project oversight. Project management policies and high- level
procedures are defined in the IT Investment Management Process guide,
associated memoranda, and in best practices guidance. In addition, project
oversight policies and procedures are defined in the guide and associated
memoranda, which, among other things, require the involvement and
approval of the board at key stages in a project*s life cycle. For
example, according to the guide, the ITIB must review and approve
investment proposals before they can be developed into business cases.
Further, once a project has been approved, the ITIB reviews up- to- date
cost, schedule, and scope information quarterly and analyzes this
information against predetermined performance expectations. The board also
determines corrective actions for projects that have not met performance
expectations.
We verified that cost, schedule, and scope information was submitted to
the ITIB quarterly and analyzed against expectations and, when significant
variances occurred, corrective actions were determined for the three
projects we reviewed. 14 This involved rebaselining the project plan based
on schedule slippages or increased costs. In all cases, the ITIB was
responsible for this decision. Notwithstanding these strengths, as
discussed in the previous section, BLM*s IT project and systems inventory
has not yet been developed to the
14 The three projects we reviewed* PayCheck, National Integrated Land
System, and Antivirus* are described in appendix I.
point where information is consistently collected and maintained to make
informed investment management decisions. This increases the risk that the
ITIB will not have at its disposal reliable information for supporting
project and portfolio investment decisions and oversight. Table 5 shows
the rating for each key practice required to implement the
critical process for project oversight at the stage 2 level of maturity
and summarizes the evidence that supports these ratings.
Table 5: IT Project Oversight Type of practice Key practice Rating Summary
of evidence
Organizational 1. The organization has written Executed BLM*s policy and
procedures for managing IT investments are defined commitments policies
and procedures for
in the IT Investment Management Process guide and its associated project
management. instruction memo.
2. The organization has written Executed The ITIB charter and IT
Investment Management Process guide policies and procedures for
specify that the board shall perform IT project oversight by regularly
management oversight of IT
analyzing each IT investment*s planned progress toward cost and projects.
schedule milestones against actual progress/ performance. Instruction
memos define procedures for submitting up- to- date project information to
the ITIB quarterly. In addition, specific procedures for determining
corrective actions for projects that have not met predetermined
performance standards were approved and adopted
by the ITIB in June 2003. Prerequisites 1. Adequate resources are
Executed Adequate resources are provided to assist the board in overseeing
IT provided to assist the board( s) in projects. Specifically, the System
Coordination Office has the primary overseeing IT projects.
responsibility of maintaining an integrated project schedule and
conducting IT project oversight on all investments as they move through
the ITIB decision process.
2. Each IT project has and Executed The IT Investment Management Process
guide requires that the maintains an approved project
project management plan be developed so that investments can be management
plan that includes
managed to achieve technical cost, schedule, performance, and risk cost
and schedule controls.
management objectives. The three projects we reviewed have project
management plans. In addition, we verified that the ITIB and System
Coordination Office applied cost and schedule controls in their quarterly
reviews of these projects.
3. An IT investment board is Executed BLM*s board has been in operation
since 1998. It is responsible for operating. selecting, controlling, and
evaluating all national IT investments. 4. Information from the IT project
Not Information from the IT project and system inventory is available to
and system inventory is used by executed the ITIB. However, according to
BLM, this information is not being the IT investment board as maintained
reliably.
applicable.
(Continued From Previous Page)
Type of practice Key practice Rating Summary of evidence
Activities 1. Each project*s up- to- date cost Executed BLM has a policy
memo requiring project managers to submit up- todate and schedule data are
provided cost, schedule, and scope information to the System to the
appropriate IT investment Coordination Office quarterly, and this
information is provided to the board.
ITIB. We verified that this was the case for the three projects that we
reviewed. 2. Using established criteria, the Executed The ITIB oversees
each IT project*s performance by comparing actual IT investment board
regularly
cost, schedule, and scope data to expectations quarterly. Quarterly
oversees each IT project*s
project status reports indicate whether reported data fall within an
performance by comparing
acceptable range when compared to expected cost and schedule actual cost
and schedule data to (red/ yellow/ green). We verified that this was the
case for the three expectations.
projects that we reviewed. 3. The IT investment board
Executed Special reviews were conducted for the three projects we reviewed
performs special reviews of when they did not meet predetermined
performance standards. projects that have not met predetermined
performance standards.
4. Appropriate corrective actions Executed For each of the projects we
reviewed, there are ITIB decision papers for each under- performing
documenting the corrective actions that have been agreed upon by project
are defined, documented, the ITIB and project manager. These actions
include rebaselining the and agreed to by the IT project plan to account
for schedule slippage or increased costs. investment board and the project
manager. 5. Corrective actions are Executed The board recently approved an
action- item tracking matrix that tracks implemented and tracked until
board decisions, parties responsible, and associated time frames. the
desired outcome is achieved.
According to project documentation, corrective actions were tracked until
implemented for the three projects we reviewed. Source: GAO.
Processes Ensure That IT Defining business needs for each IT project helps
ensure that projects
Projects Support Business Needs support the organization*s mission goals
and meet users* needs. This
and Meet Users* Needs critical process creates the link between the
organization*s business
objectives and its IT management strategy. According to ITIM, effectively
identifying business needs requires, among other things, (1) defining the
organization*s business needs or stated mission goals, (2) identifying
users for each project who will participate in the project*s development
and implementation, (3) training IT staff adequately in identifying
business needs, and (4) defining business needs for each project. (The
complete list of key practices is provided in table 6.)
BLM has executed all the key practices for this critical process. The
bureau*s IT Investment Management Process guide requires that business
needs and associated users of each IT project be identified in the
investment proposal and business case stages of the select phase. BLM also
has detailed procedures for developing these two documents that call for
identifying business needs and associated users. Resources for identifying
business needs and associated users include the project sponsor, project
proponent, and the System Coordination Office and detailed procedures and
associated templates for developing investment proposals and business
cases. Bureau specific business needs are defined in the Bureau of Land
Management*s Strategic Plan for fiscal years 2000* 2005, and projects are
also often linked to the Department of the Interior*s strategic goals and
goals of the President*s Management Agenda. 15 In addition, individuals
responsible for managing projects at BLM can adequately identify business
needs; according to BLM, the bureau*s practice is to select staff from
business units as project managers (instead of staff from the IT unit).
Finally, according to BLM officials, all national applications are in the
Budget Planning System and target enterprise architecture, which are
repositories of investment information that BLM is planning on using to
make informed investment management decisions. For the three projects we
reviewed, business needs and associated users were identified in business
case or project planning documents, and users were involved in project
management throughout the life cycle of the project through, for
example, chartered user- group meetings, structured walk- throughs,
prerelease workshops, and conference calls. Because it is executing all
key practices associated with business needs identification, BLM can have
greater assurance that its projects will support business needs and meet
users* needs. Table 6 shows the rating for each key practice required to
implement the
critical process for business needs identification at the stage 2 level of
maturity and summarizes the evidence that supports these ratings.
15 The President's Management Agenda is a strategy for improving the
management and performance of the federal government. The Agenda contains
five governmentwide and nine agency- specific goals to improve federal
management and deliver results that matter to the American people.
Table 6: Business Needs Identification Type of practice Key practice
Rating Summary of evidence
Organizational 1. The organization has written Executed BLM has guidance
for developing investment proposals and commitment policies and procedures
for
business cases that calls for identifying the business needs (and
identifying the business needs (and the associated users) of each IT
project. the associated users) of each IT project.
Prerequisites 1. Adequate resources are provided Executed BLM has adequate
resources for identifying business needs for identifying business needs
and
and associated users. They include the project managers, associated users.
portfolio managers, and the System Coordination Office.
2. The organization has defined Executed The Bureau of Land Management*s
Strategic Plan for fiscal business needs or stated mission
years 2000* 2005 defines the agency*s mission goals. goals. 3. IT staff
are trained in business
Executed According to BLM officials, individuals responsible for managing
needs identification. projects at BLM generally come from the business/
program areas. Therefore, they can adequately identify business needs. 4.
IT projects and systems are
Executed According to BLM officials, all national IT investments and most
identified in the IT project and state and center IT investments are in
the enterprise system inventory.
architecture and Budget Planning System, which together represent the IT
project and system inventory.
Activities 1. The business needs for each IT Executed BLM requires that
business needs for each IT project be project are clearly identified and
identified in investment proposals and business cases. We defined.
verified that the business needs for the three projects we reviewed were
clearly identified and defined. 2. Specific users are identified for
Executed BLM requires that specific users be identified for each IT
project each IT project. in investment proposals and business cases. We
verified that
specific users were identified for the three projects we reviewed. 3.
Identified users participate in Executed According to BLM officials, users
are involved in project project management throughout a
management throughout a project*s life cycle. For the three project*s life
cycle. projects were reviewed, users were involved in project management
through various types of meetings.
Source: GAO.
Proposal Selection Process Is Selecting new IT proposals requires an
established and structured process
Established, but Criteria for to ensure informed decision making and
infuse management
Analyzing and Prioritizing accountability. According to ITIM, this
critical process requires, among
Investments Have Not Been other things, (1) making funding decisions for
new IT proposals according
Fully Defined to an established process; (2) providing adequate resources
to proposal
selection activities; (3) using an established proposal selection process;
(4) analyzing and ranking new IT proposals according to established
selection criteria, including cost and schedule criteria; and (5)
designating an official to manage the proposal selection process. (The
complete list of key practices is provided in table 7.)
BLM has executed five of the six key practices associated with proposal
selection. For example, the IT Investment Management Process guide defines
a multistage selection process (the select phase), including developing a
business case and project plan that executives and project proponents
follow. Resources for proposal selection activities include project
proponents and the System Coordination Office. As previously noted,
detailed procedures and a template have been defined for developing new IT
proposals. In addition, according to BLM officials, funding decisions are
made through the budget process, which BLM is working on to better
integrate with the investment management process.
Despite these strengths, the key practice associated with analyzing and
prioritizing new proposals according to established criteria has not yet
been executed because the various criteria for doing so have not yet been
fully defined. The Bureau Enterprise Architecture Team has defined
criteria it uses to determine projects* compliance with the bureau
enterprise
architecture*s business processes, data, applications, and technology
components. Another set of criteria is being developed to assess proposals
for their business value. These criteria are intended to be used by the IT
Portfolio Management Council to screen proposals before they are reviewed
by the ITIB. The ITIB members believe that these criteria are key to
analyzing new proposals and have charged the IT Portfolio Management
Council with developing draft criteria. The council intends to finalize
the criteria in time for their use in the spring of 2004 to evaluate
proposals for the fiscal year 2006 budget. Until BLM finalizes its
proposal selection criteria and uses them to analyze and prioritize
proposals, the bureau will not be adequately assured that it is
consistently and objectively selecting proposals that best meet the needs
and priorities of the agency.
Table 7 shows the rating for each key practice required to implement the
critical process for proposal selection at the stage 2 level of maturity
and summarizes the evidence that supports these ratings.
Table 7: Proposal Selection Type of practice Key practice Rating Summary
of evidence
Organizational 1. Executives and managers follow an Executed BLM*s IT
Investment Management Process guide commitments established selection
process. defines a selection process that executives and
project proponents follow. 2. An official is designated to manage the
Executed The IT Investment Management Process guide and proposal selection
process. the ITIB charter assign this responsibility to the ITIB.
Prerequisite 1. Adequate resources are provided for
Executed Adequate resources are provided for proposal proposal selection
activities. selection activities. They include the project
proponents and portfolio managers who develop investment proposals and
business cases and the System Coordination Office who supports them in
these activities. Activities 1. The organization uses a structured
Executed BLM has defined procedures for developing new IT
process to develop new IT proposals. proposals. 2. Executives analyze and
prioritize new IT
Not executed Executives analyze and prioritize new IT proposals; proposals
according to established selection
however, according to BLM officials, prioritization is criteria.
not based on established criteria. 3. Executives make funding decisions
for
Executed According to BLM officials, executives make new IT proposals
according to an funding decisions for new IT proposals through established
process. BLM*s budget process. Source: GAO.
BLM Has Initiated Efforts to Once an agency has attained stage 2 maturity,
it needs to establish Manage Its Investments as a
capabilities for managing its investments as a portfolio (stage 3). Such
Portfolio and Improve Its
capabilities enable the agency to consider its investments comprehensively
Investment Management
so that the collective investments optimally address its mission,
strategic goals, and objectives. Stage 3 capabilities include (1) defining
portfolio Process selection criteria, (2) engaging in project- level
investment analysis, and (3) aligning the authority of IT investment
boards. In addition, establishing higher level stage capabilities* for
example performing postimplementation reviews* can help an agency improve
its investment management process. BLM has initiated efforts to manage its
investments as a portfolio. BLM has
defined procedures for aligning the national ITIB with subordinate boards.
16 Portfolio categories have been defined that correspond to BLM*s
organizational units (e. g., Minerals, Realty, and Resource Protection;
Information Resource Management). Moreover, the board revised its charter
in April 2003 to include portfolio management responsibilities (i. e.,
stage 3) and established an IT Portfolio Management Council to support it
in carrying out these responsibilities. 17 At a higher level stage, BLM
has begun to address postimplementation reviews, a critical process
associated with the most capable organizations. BLM has begun performing
postimplementation reviews on a limited basis to learn lessons for
improving both project management and investment management processes. To
date, the bureau has conducted two such reviews.
Compared with the progress at stage 2, BLM*s progress to date in defining
practices for higher level maturity stages has been limited because,
according to its officials, the ITIB first focused its resources on
establishing
the processes associated with building the IT investment management
foundation. Full implementation of the critical processes associated with
portfolio management will provide BLM with the capability to determine
whether it is selecting the mix of products that best meet the bureau*s
mission needs. Implementing critical processes at higher level stages will
equip BLM with the capabilities it needs to improve its investment
management processes.
BLM Does Not Have a We have previously reported that to effectively
implement ITIM processes,
Plan to Guide IT agencies need to be guided by a plan that (1) is based on
an assessment of
strengths and weaknesses; (2) specifies measurable goals, objectives, and
Investment milestones; (3) specifies needed resources; and (4) assigns
clear
Management responsibility and accountability for accomplishing well-
defined tasks. In
addition, these plans should be approved by senior management. 18
Improvement Efforts
Although a plan was developed a few years ago to establish the practices
currently in place, BLM does not have a plan to guide further improvement
of its investment management process. An independent assessment of BLM's
ITIM process relative to stage 2 of our IT investment management framework
was completed in January 2003, but BLM has not yet used the
results of this assessment to develop an improvement plan. According to
the CIO, this is because BLM intends to develop a plan integrating
16 Most state and center offices have their own boards for managing IT
investments that fall below the thresholds of the national IT investments*
criteria. 17 The Portfolio Management Council was formed in July 2002 and
has met several times since. The council*s charter was approved in June
2003. 18 GAO- 02- 314, GAO- 03- 3, GAO- 03- 751.
improvements for IT investment management and other IT management areas,
and the results of the comprehensive assessment to be used as a basis for
this integrated plan were not received until June 2003. BLM officials
recognize the importance of having a plan to guide their improvement
efforts, however, and stated their commitment to developing one, although
they do not have a specific time frame for doing so. Until BLM develops
this plan, the bureau risks losing the momentum it has gained in
implementing its ITIM process. Conclusions BLM has made good progress in
defining and establishing its investment
management process in the 2 years since we reported that the lack of such
a process had largely contributed to the failure of a key program. By
establishing most of the key practices associated with building the
investment foundation, the bureau has strengthened its basic capabilities
for selecting and controlling projects and positioned itself to develop
the processes for managing its investments as a portfolio. Critical to
BLM*s success going forward will be the development of an implementation
plan* preferably integrated with implementation plans for improving other
IT management areas* to (1) guide and establish accountability for
executing the stage 2 key practices that we noted needed to be addressed
and (2) proceeding with efforts to define and implement stage 3 key
practices. Without this plan, BLM risks not being able to sustain the
progress made to date in establishing its investment management process.
Recommendations for To strengthen BLM*s IT investment management
capability and address the
Executive Action weaknesses discussed in this report, we recommend that
the Secretary of
the Department of the Interior direct the BLM Director to develop and
implement a plan for improving its IT investment management process that
is based on GAO*s ITIM stage 2 and 3 critical processes. The plan should,
at a minimum, provide for accomplishing the following:
implementing the recently approved procedures for determining corrective
actions for projects that have not met performance expectations;
defining and implementing policies and procedures for collecting
project and system information in the Budget Planning System for
investment management purposes;
fully defining criteria for analyzing and prioritizing new IT proposals;
and
proceeding with plans to define and implement all stage 3 critical
processes, which are necessary for portfolio management. In developing the
plan, the BLM Director should ensure that it (1) is based on the results
of the bureau*s recent assessment of ITIM stage 2 capabilities; (2)
specifies measurable goals, objectives, milestones, and outcomes; (3)
specifies needed resources; and (4) assigns clear responsibility and
accountability for accomplishing well- defined tasks. In
implementing the plan, the Director should ensure that the needed
resources are provided and that progress is measured and reported
periodically to the Secretary of the Interior.
Agency Comments and In written comments on a draft of this report
(reprinted in app. II), BLM*s
Our Evaluation Director agreed with our findings and recommendations and
stated that
they represented a fair and accurate evaluation of the bureau*s status and
progress towards IT investment management maturity. The Director also
noted that BLM has begun developing a plan, in accordance with our
recommendations, to (1) complete the key practices for reaching GAO*s ITIM
stage 2 maturity and (2) identify the goals, time frames, outcomes, and
resources needed to reach stage 3 maturity. BLM provided additional
technical comments, which we have incorporated into the report as
appropriate.
We are sending copies of this report to interested congressional
committees. We are also sending copies to the Director of the Office of
Management and Budget, the Secretary of the Interior, and BLM*s Director
and CIO. We also will make copies available to others upon request. In
addition, the report will be available at no charge on the GAO Web site at
www. gao. gov. Should you or your offices have questions on matters
discussed in this report, please contact me at (202) 512- 6240, or Lester
P. Diamond, Assistant
Director, at (202) 512- 7957. We can also be reached by E- mail at at
koontzl@ gao. gov, or diamondl@ gao. gov, respectively. Key contributors
to this assignment were Jamey A. Collins, Sabine R. Paul, and Sophia
Harrison.
Linda D. Koontz Director, Information Management Issues
Appendi Appendi xes x I
Objectives, Scope, and Methodology The objectives of our review were to
(1) evaluate the Bureau of Land Management*s (BLM) IT investment
management capabilities against the key practices defined in GAO*s IT
investment management assessment framework and (2) determine the agency*s
plans for improving these capabilities.
To address our first objective, we assessed the extent to which BLM
satisfied the five critical processes identified in stage 2 of GAO*s
Information Technology Investment Management (ITIM) framework. 1 We
applied the framework as it is described in the exposure draft, except
that we used a revised version of the IT Asset Inventory critical process,
called
IT Project and System Identification, after discussions with departmental
officials at the beginning of this engagement. This revised critical
process has been used in our evaluations since June 2001. We did not
formally assess BLM*s progress in establishing capabilities found in
stages 3, 4, and 5 because BLM acknowledged that it had so far primarily
focused on stage 2 and had not executed many key practices in higher
maturity stages. In addition, we limited our review to BLM*s management of
its national investments because they represent the investments of greater
cost and impact to the organization.
To determine whether BLM had implemented the critical processes associated
with stage 2, we reviewed the results of a self- assessment of stage 2
practices using GAO*s ITIM framework and validated and updated the results
of the self- assessment through document reviews and
interviews with officials. We reviewed written policies, procedures, and
guidance and other documentation providing evidence of executed practices,
including BLM*s IT Investment Management Process guide, various board/
council charters, and instruction memorandums. We also reviewed national
Information Technology Investment Board (ITIB) meeting materials,
including quarterly status reports, meeting minutes,
records of decision, and matrices tracking action items through
completion. We interviewed several BLM officials, including system
coordination office officials, portfolio managers, and ITIB members. We
also attended a 2- day national ITIB meeting in March 2003.
As part of our analysis, we selected three IT projects as case studies to
verify application of the critical processes and practices. We selected
projects that (1) supported different BLM functional areas (directorates),
1 GAO/ AIMD- 10.1.23.
(2) were in different life- cycle phases, and (3) required various levels
of funding. The three projects are the following:
PayCheck* The objective of PayCheck, currently in the evaluate phase, is
to allow employees to input their time and attendance data using an
automated system. Previously, the employee developed a hard- copy time
sheet, and then a timekeeper keyed the same information into the payroll
system. By allowing the employees to enter their own data, PayCheck
changed the business process and eliminated the duplication of manual
effort. This project, with an estimated life- cycle cost of $1,681,000, is
the responsibility of the National Human Resources Management Center,
which supports BLM*s human resources function.
National Integrated Land System* The objective of this system, which is
currently in a mixed life cycle, 2 is to provide a process to collect,
maintain, and store survey- and parcel- based land information that meets
the common, shared business needs of land title and land resource
management. This system will provide agencies, BLM*s
partners, and the public with business solutions for the management of
cadastral records and land parcel information in a Geographic Information
System environment, accessible via the Internet. This project, which has
an estimated life- cycle cost of $31.3 million, is under the Minerals,
Realty, and Resource Protection directorate. This directorate is
responsible for managing commercial energy and mineral production from the
public lands. Antivirus* The objective of Antivirus, currently in the
control phase, is to renew or replace BLM*s existing antivirus contract
that is expiring to
provide antivirus coverage to all simple mail transfer protocol gateways,
mail servers, other servers, desktops, and laptops. In addition, BLM is
seeking to provide improved enterprise management and reporting
capabilities, as well as a more automated methodology for deploying
virus update files across the bureau. This project is being carried out by
the Information Resources Management directorate, which provides IT
services to BLM states, centers, and partners in support of the bureau*s
mission. The estimated life cycle cost for Antivirus is $800, 600.
2 The National Integrated Land System has four different modules. Three of
these modules are in the *control* phase and the fourth is in the
*evaluate* phase.
For these projects, we reviewed project management documentation, such as
business cases, project plans, and quarterly reports. We also reviewed
user- group meeting minutes and analyzed national ITIB decision documents
related to each of the projects. We also interviewed the project managers
for these projects. We compared the evidence collected from our document
reviews and interviews to the key practices in ITIM. We rated the key
practices as *executed* on the basis of whether the agency demonstrated
(by providing evidence of performance) that it had met the criteria of the
key practice. A key practice was rated as *not executed* when we found
insufficient evidence of a practice during the review, or when we
determined that there were significant weaknesses in BLM*s execution of
the key practice.
To address our second objective, we interviewed officials from the System
Coordination Office, whose main responsibility it is to oversee and ensure
that BLM*s IT investment management process is implemented and followed;
the chief information officer; and other national ITIB members to
determine efforts undertaken to improve IT investment management
processes. We also reviewed an improvement plan developed about 3 years
ago based on strengths and weaknesses of BLM*s IT investment management
process at that time, and the results of the comprehensive IT
management assessment BLM officials stated they plan to use as a basis for
an integrated plan for improving IT investment management and other IT
management areas.
We conducted our work at BLM Headquarters in Washington, D. C., from March
through July 2003, in accordance with generally accepted government
auditing standards.
Comments from the Bureau of Land
Appendi x II
Management (310363)
GAO*s Mission The General Accounting Office, the audit, evaluation and
investigative arm of Congress, exists to support Congress in meeting its
constitutional responsibilities
and to help improve the performance and accountability of the federal
government for the American people. GAO examines the use of public funds;
evaluates federal programs and policies; and provides analyses,
recommendations, and other assistance to help Congress make informed
oversight, policy, and funding decisions. GAO*s commitment to good
government is reflected in its core values of accountability, integrity,
and reliability.
Obtaining Copies of The fastest and easiest way to obtain copies of GAO
documents at no cost is
through the Internet. GAO*s Web site (www. gao. gov) contains abstracts
and fulltext GAO Reports and
files of current reports and testimony and an expanding archive of older
Testimony
products. The Web site features a search engine to help you locate
documents using key words and phrases. You can print these documents in
their entirety, including charts and other graphics.
Each day, GAO issues a list of newly released reports, testimony, and
correspondence. GAO posts this list, known as *Today*s Reports,* on its
Web site daily. The list contains links to the full- text document files.
To have GAO e- mail this
list to you every afternoon, go to www. gao. gov and select *Subscribe to
e- mail alerts* under the *Order GAO Products* heading. Order by Mail or
Phone The first copy of each printed report is free. Additional copies are
$2 each. A check
or money order should be made out to the Superintendent of Documents. GAO
also accepts VISA and Mastercard. Orders for 100 or more copies mailed to
a single address are discounted 25 percent. Orders should be sent to:
U. S. General Accounting Office 441 G Street NW, Room LM Washington, D. C.
20548 To order by Phone: Voice: (202) 512- 6000 TDD: (202) 512- 2537 Fax:
(202) 512- 6061
To Report Fraud, Contact:
Waste, and Abuse in Web site: www. gao. gov/ fraudnet/ fraudnet. htm E-
mail: fraudnet@ gao. gov Federal Programs
Automated answering system: (800) 424- 5454 or (202) 512- 7470 Public
Affairs Jeff Nelligan, Managing Director, NelliganJ@ gao. gov (202) 512-
4800 U. S. General Accounting Office, 441 G Street NW, Room 7149
Washington, D. C. 20548
a
GAO United States General Accounting Office
BLM has made progress in establishing its ITIM capabilities. Specifically,
* BLM has established most of the key practices associated with building
an
investment foundation (see table). For example, the bureau has established
a board for managing IT investments, implemented processes to ensure that
IT projects support business needs and meet users* requirements, and
established a process for selecting IT proposals. In addition, the bureau
has efforts under way to address the key practices it has not yet
established.
BLM has also initiated efforts to manage its investments as a portfolio.
For example, it has established a council to support portfolio management
activities and begun defining portfolio selection criteria. BLM has also
begun performing postimplementation reviews to learn lessons that will
help define and implement an IT investment evaluation process. However
BLM*s progress to date in defining practices for managing its investments
as a portfolio has been limited because, according to its officials, its
investment board first focused its resources on establishing the processes
associated with building the IT investment management foundation.
Although BLM has made progress in developing its IT investment process, it
has not yet developed a plan to guide its efforts in this area and, as a
result, may not be able to successfully establish more mature ITIM
processes. According to the chief information officer, this is because BLM
wanted to develop an ITIM plan that is integrated with improvement plans
for other IT management areas, and the results of the comprehensive
assessment that were to be used as the basis for such a plan were obtained
only in June 2003. BLM officials agree that this plan is necessary for
guiding improvement efforts and stated their intention to develop one.
Developing such a plan will help BLM sustain progress made to date.
Summary of Results for Investment Foundation Critical Processes and Key
Practices Critical process Purpose
Percentage of key practices executed
IT investment board operation To define and establish the governing board(
s) responsible for selecting, controlling, and evaluating IT investments.
100% IT project and system identification To create and maintain an IT
project inventory to assist in managerial decision making. 42% IT project
oversight To regularly determine each IT project's progress toward cost
and schedule milestones using established criteria and take corrective
actions when milestones are not achieved. 91% Business needs
identification To ensure that each IT project supports the organization's
business needs and meets users' needs. 100% Proposal selection To ensure
that an established, structured process is used to select new IT
proposals. 83% Total 84% Source: GAO. The mission of the Department of the
Interior*s Bureau of Land Management (BLM) is to maintain
the health, diversity, and productivity of the public lands for the use
and enjoyment of present and future generations. BLM employs about 11, 000
people, with information technology (IT) playing a critical role in
helping
BLM perform its responsibilities. The bureau estimates that it will spend
about $146 million on IT initiatives in fiscal year 2003. GAO was asked to
evaluate BLM*s
IT investment management (ITIM) capabilities and determine the bureau*s
plans for improving these capabilities. GAO*s evaluation was based on
applying its ITIM maturity
framework, which identifies critical processes for successful IT
investment management.
GAO recommends that the Secretary of the Interior direct BLM*s Director to
develop and implement a plan for making ITIM
improvements that is based on GAO*s ITIM stage 2 and 3 critical processes;
specifies measurable goals, outcomes, and needed resources; and assigns
clear responsibility for tasks. Progress should be measured and reported
periodically to Interior.
BLM agreed with our findings and recommendations and noted that it had
begun developing a plan for making ITIM improvements in accordance with
our recommendations.
www. gao. gov/ cgi- bin/ getrpt? GAO- 03- 1025. To view the full product,
including the scope and methodology, click on the link above. For more
information, contact Linda D. Koontz at (202) 512- 6240 or koontzl@ gao.
gov. Highlights of GAO- 03- 1025, a report to the
Subcommittee on Interior and Related Agencies, Committee on
Appropriations, House of Representatives September 2003
BUREAU OF LAND MANAGEMENT
Plan Needed to Sustain Progress in Establishing IT Investment Management
Capabilities
Page i GAO- 03- 1025 BLM*s IT Investment Management Process
Contents
Page ii GAO- 03- 1025 BLM*s IT Investment Management Process
Page 1 GAO- 03- 1025 BLM*s IT Investment Management Process United States
General Accounting Office Washington, D. C. 20548
Page 1 GAO- 03- 1025 BLM*s IT Investment Management Process
A
Page 2 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 3 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 4 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 5 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 6 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 7 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 8 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 9 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 10 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 11 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 12 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 13 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 14 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 15 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 16 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 17 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 18 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 19 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 20 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 21 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 22 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 23 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 24 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 25 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 26 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 27 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 28 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 29 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 30 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 31 GAO- 03- 1025 BLM*s IT Investment Management Process
Appendix I
Appendix I Objectives, Scope, and Methodology
Page 32 GAO- 03- 1025 BLM*s IT Investment Management Process
Appendix I Objectives, Scope, and Methodology
Page 33 GAO- 03- 1025 BLM*s IT Investment Management Process
Page 34 GAO- 03- 1025 BLM*s IT Investment Management Process
Appendix II
United States General Accounting Office Washington, D. C. 20548- 0001