VA Information Technology: Progress Made, but Continued 	 
Management Attention Is Key to Achieving Results (13-MAR-02,	 
GAO-02-369T).							 
								 
The information technology (IT) program helps the Department of  
Veteran Affairs (VA) effectively serve veterans. However, there  
are challenges in VA's management of IT. VA has laid the	 
groundwork for an integrated, departmentwide enterprise 	 
architecture--a blueprint for evolving its information systems	 
and developing new systems to optimize their mission value.	 
Crucial executive support has been established and the department
has a strategy to define products and processes critical to its  
development. VA is currently recruiting a chief architect to	 
assist in implementing and managing the enterprise architecture. 
VA has taken steps to strengthen its department-level program in 
information security management, including mandating information 
security performance standards and, greater management		 
accountability for senior executives. It has also updated	 
security policies, procedures, and standards to implement	 
critical security measures. However, VA continues to report	 
pervasive and serious information security weaknesses. The	 
Veterans Benefits Administration is still far from a modernized  
system to replace its aging benefits delivery network. The	 
Veterans Health Administration's (VHA) has made good progress in 
expanding the use of its decision support system (DSS) for	 
clinical and financial decision making. The use of DSS data for  
the fiscal year 2002 resource allocation process, and a 	 
requirement that veteran integrated service network directors	 
better account for their use of this system, have raised	 
awareness of, and promoted its use among VHA facilities. Lastly, 
VA has made limited progress in its  efforts to share data with  
the Department of Defense and Indian Health Service as part of a 
computer-based patient record initiative. Implementation	 
strategies continue to be revised, the scope of the initiative	 
has been substantially narrowed, and it continues to operate	 
without clear lines of authority or comprehensive, coordinated	 
plans.								 
-------------------------Indexing Terms------------------------- 
REPORTNUM:   GAO-02-369T					        
    ACCNO:   A02891						        
  TITLE:     VA Information Technology: Progress Made, but Continued  
Management Attention Is Key to Achieving Results		 
     DATE:   03/13/2002 
  SUBJECT:   Information resources management			 
	     Information systems				 
	     Information technology				 
	     Performance measures				 
	     DOD/IHS/VA Government Computer-Based		 
	     Patient Record Project				 
								 
	     VA Compensation and Pension Benefit		 
	     Payment System					 
								 
	     VA Decision Support System 			 
	     VA Information Technology Program			 

******************************************************************
** This file contains an ASCII representation of the text of a  **
** GAO Product.                                                 **
**                                                              **
** No attempt has been made to display graphic images, although **
** figure captions are reproduced.  Tables are included, but    **
** may not resemble those in the printed version.               **
**                                                              **
** Please see the PDF (Portable Document Format) file, when     **
** available, for a complete electronic file of the printed     **
** document's contents.                                         **
**                                                              **
******************************************************************
GAO-02-369T
     
United States General Accounting Office

GAO Testimony

Before  the  Subcommittee  on  Oversight and  Investigations,  Committee  on
Veterans' Affairs, House of Representatives

For Release on Delivery Expected at 10 a.m. EST Wednesday, March 13, 2002

VA INFORMATION TECHNOLOGY

Progress Made, but Continued Management Attention Is Key to Achieving
Results

Statement of David L. McClure
Director, Information Technology Management Issues

GAO-02-369T

Mr. Chairman and members of the subcommittee:

We are pleased to participate in today's continuing dialogue on the
Department of Veterans Affairs' (VA) information technology (IT) program. IT
is key to helping VA effectively serve our nation's veterans, and over the
years, the department has expended substantial resources (more than $6
billion over the last 6 years) in support of its IT needs. As you know,
however, VA has encountered persistent challenges in managing IT to produce
results and improve performance.

When we testified before the subcommittee last April, a new secretary of
veterans affairs had just been confirmed and an executive-level security
officer had been hired.1 To his credit, the secretary readily seized upon
the seriousness of the issues that have been raised concerning VA's IT
program, and committed to reforming how the department uses information
technology. Since then, VA has also hired a department-level chief
information officer (CIO) to lead its IT program. We view this executive
leadership as a positive and significant step forward in the department's
attempt to achieve better returns on its IT investments. However, VA's IT
investment and management challenges are significant, and its ability to
resolve them with the right combination of people, processes, and technology
that are focused on achieving solid results will take sustained time,
effort, and commitment.

At your request, we have been reviewing VA's continuing actions to address
critical weaknesses in its overall IT program. Today, we will share with you
the results of our work to date regarding VA's actions since last April to

* develop an enterprise architecture;

* improve information security;

* implement the Veterans Benefits Administration's veterans service network
project that is intended to replace its existing compensation and pension
payment system with a new system;

* extend the usage of, and standardize data collection for, the Veterans
Health Administration's decision support system, being used to facilitate
managers' and clinicians' analyses of patient care and cost of providing
health care services; and

* implement jointly with the Department of Defense and Indian Health
Service, the government computer-based patient record initiative,

1U.S. General Accounting Office, VAInformation Technology: Important
InitiativesBegun,YetSerious Vulnerabilities Persist,GAO-01-550T (Washington,
D.C.: April 4, 2001).

which was intended to allow physicians and users to access data in each
others' health information systems.

In doing this work, we analyzed relevant documentation and interviewed key
agency officials to identify and assess VA's progress in implementing
specific actions since April 2001 related to developing an enterprise
architecture, improving information security, developing the Veterans
Benefits Administration's veterans service network compensation and pension
replacement system, extending usage of the Veterans Health Administration's
decision support system, and advancing data sharing via the government
computer-based patient record project. We performed our work in accordance
with generally accepted government auditing standards, from June 2001
through March 2002.

                             Results in BriefEUR

Over the past year, VA has clearly benefited from the commitment of the
secretary and other top leaders to addressing critical weaknesses in the
department's management of information technology. As a result of their
leadership, VA has made important strides in raising corporate awareness of
the department's needs and in articulating and acting upon a vision for
achieving improvements in key areas of IT performance. Despite this
progress, however, many aspects of VA's IT environment remain troublesome,
and our message today reflects concerns that we have long viewed as
significant impediments to the department's effective use of IT to achieve
optimal agency performance. As such, VA has more work to accomplish before
it can point to real improvement in overall program performance and be
assured that it has a stable, reliable, and modernized systems environment
to effectively support critical agency decisionmaking and operations.

In an area of growing importance, VA has taken key steps in laying the
groundwork for an integrated, departmentwide enterprise architecture-a
blueprint for evolving its information systems and developing new systems
that optimize their mission value. Crucial executive support has been
established and the department has put in place a strategy to define
products and processes that are critical to its development. VA is also
currently recruiting a chief architect to assist in implementing and
managing the enterprise architecture. Significant work, nonetheless, is
still required before the department will have a functioning enterprise
architecture in place for acquiring and utilizing information systems across
VA in a cost-effective and efficient manner. VA's success in developing,
implementing, and using a complete and enforceable enterprise architecture
hinges upon continued attention to putting in place a sound program
management structure-including a permanent chief architect and an
established program office-to facilitate, manage, and advance this effort
and to be held accountable for its success. In addition, VA must

continue to take steps to identify and collect crucial information
describing essential business functions, information flows, strategic plans,
and requirements, and produce a well-thought-out sequencing plan that
considers management and organizational changes and business goals and
operations. Success also hinges on having proactive management focused on
ensuring that investment management and systems development and acquisition
are closely linked with the enterprise architecture processes. This
integration must be done in a manner that best suits the agency's particular
organization, culture, and internal management practices.

Information security management is another area in which VA has taken
important steps to strengthen its department-level program, including
mandating information security performance standards and, thus, greater
management accountability for senior executives. It has also updated
security policies, procedures, and standards to guide the implementation of
critical security measures. However, VA continues to report pervasive and
serious information security weaknesses. Thus far, its actions toward
establishing a comprehensive computer security management program have not
been sufficient to ensure that the department can protect its computer
systems, networks, and sensitive veterans health care and benefits data from
unnecessary exposure to vulnerabilities and risks. Moreover, VA's current
organizational structure does not ensure that the cyber security officer can
effectively oversee and enforce compliance with security policies and
procedures that are being implemented throughout the department.

Beyond these two key areas of IT management concern, VA and its
administrations also have continued to pursue several critical information
systems investments that have consumed substantial time and resources, with
mixed success. For example, after about 16 years and at least $335 million
spent on modernization, the Veterans Benefits Administration (VBA) is still
far from a modernized system to replace its aging benefits delivery network,
needed to more effectively support its compensation and pension and other
vital benefits payment processes. VBA has not adequately addressed several
longstanding concerns related to project management, requirements
development, and testing-all of which raise uncertainty about whether the
ongoing veterans service network (VETSNET) project will deliver a
cost-effective solution with measurable and specific program-related
benefits.

Conversely, the Veterans Health Administration's (VHA) managers and
clinicians have made good progress in expanding their use of the decision
support system (DSS) to facilitate clinical and financial decisionmaking.
The use of DSS data for the fiscal year 2002 resource allocation process and
a requirement that veteran integrated service network directors better
account for their use of this system have both raised awareness of and
promoted its utility among VHA facilities. Moreover, VHA has begun steps to
further improve the accuracy and timeliness of DSS data. As VHA-wide

usage of DSS progresses, sustained top management attention will be crucial
to ensuring the continued success of this system.

Lastly, VA has achieved limited progress in its joint efforts with the
Department of Defense and Indian Health Service to create an interface for
sharing data in their health information systems, as part of the government
computer-based patient record initiative. Strategies for implementing the
project continue to be revised, its scope has been substantially narrowed,
and it continues to operate without clear lines of authority or
comprehensive, coordinated plans. Consequently, the future success of this
project remains uncertain, raising questions as to whether it will ever
fully achieve its original objective of allowing health care professionals
to share clinical information via a comprehensive, lifelong medical record.

Promising Beginning, but VA Remains Far from Implementing an Enterprise
Architecture

One of VA's most essential yet challenging undertakings has been developing
and implementing an enterprise architecture to guide the department's IT
efforts. An enterprise architecture-a blueprint for systematically and
completely defining an organization's current (baseline) operational and
technology environment and a roadmap toward the desired (target) state-is an
essential tool for effectively and efficiently engineering business
processes and for implementing their supporting systems and helping them
evolve. Office of Management and Budget (OMB) guidelines2 require VA and
other federal agencies to develop and implement enterprise architectures to
provide a framework for evolving or maintaining existing and planned IT.
Guidance issued last year by the Federal CIO Council3 in collaboration with
us further emphasizes the importance of enterprise architectures in evolving
information systems, developing new systems, and inserting new technologies
that optimize an organization's mission value.

As this subcommittee is well aware, VA has been attempting to develop an
enterprise architecture for several years, but without much overall success.
Our prior reports and testimony4 have documented how VA's previous attempts
have fallen short of their intended purpose and did not reflect an approach
that would result in an integrated, departmentwide

2OMB, Management of FederalInformationResources, Circular A-130 (Washington,
D.C.: November 30, 2000).

3Chief Information Officer Council, APracticalGuideto
FederalEnterpriseArchitecture, Version 1.0 (Washington, D.C., February
2001).

4U.S. General Accounting Office, VAInformation
Technology:ImprovementsNeededto Implement Legislative
Reforms,GAO/AIMD-98-154 (Washington, D.C., July 7, 1998); U.S. General
Accounting Office,Information Technology: UpdateonVAActionsto
ImplementCriticalReforms,GAO/T-AIMD-00-74 (Washington, D.C., May 11, 2000);
U.S. General Accounting Office, VAInformation Technology:
ProgressContinuesAlthough Vulnerab iiesRemain,GAO/T-AIMD-00-321 (Washington,
D.C., September 21, 2000); GAO-01-550T.

blueprint. For example, VA's earlier strategy had called for each of its
administrations-VBA, VHA, and the National Cemetery Administration- to
develop its own logical architecture, which likely would not have resulted
in the department's having an integrated architecture, but rather, at least
three separate, unrelated architectures. In addition, VA's common business
lines had not been adequately involved in prior attempts to develop an
architecture. In July 1998 and August 2000, respectively, we recommended
that VA take actions to develop a detailed implementation plan with
milestones for completing an integrated, departmentwide architecture, and
that it include VA business owners in its architecture development. After
assuming office last year, VA's secretary vowed to take action to address
the inadequacies in the department's approach.

Over the past year, VA has made progress in taking specific actions to lay
the groundwork for its enterprise architecture. Its most recent set of
activities closely adhere to the Federal CIO Council's suggested guidance on
managing the enterprise architecture program.

By effectively implementing an enterprise architecture, VA stands to realize
a number of important and tangible benefits. For example, an enterprise
architecture can

VA Has Taken Important Steps Toward Developing an Enterprise Architecture,
But Much Work Remains

                                     *

                                     *

                                     *

capture facts about the department's mission, functions, and business
foundation in an understandable manner to promote better planning and
decisionmaking;

improve communication among the department's business organizations and IT
organizations through a standardized vocabulary; and

provide architectural views that help communicate the complexity of VA's
large systems and facilitate management of its extensive, complex
environments.

Overall, effective implementation of an enterprise architecture can
facilitate VA's IT management by serving to inform, guide, and constrain the
decisions being made for the department, and subsequently decreasing the
risk of buying and building systems that are duplicative, incompatible, and
unnecessarily costly to maintain and interface.

As depicted in figure 1, developing, implementing, and maintaining an
enterprise architecture is a dynamic, iterative process of changing the
enterprise over time by incorporating new business processes, new
technology, and new capabilities. Depending on the size of the agency's
operations and the complexity of its environment, enterprise architecture
development and implementation requires sustained attention to process

management and agency action over an extended period of time. Moreover, once
implemented, the enterprise architecture requires regular upkeep and
maintenance to ensure that it is kept current and accurate. Periodic
reassessments are necessary to ensure that the enterprise architecture
remains aligned with the department's strategic mission and priorities,
changing business practices, funding profiles, and technology innovation.

Figure 1: The Enterprise Architecture Process

Source: A Practical Guide to Federal Enterprise Architecture, Version 1.0,
2001

A prerequisite to development of the enterprise architecture is sustained
sponsorship and strong commitment achieved through buy-in of the agency
head, leadership of the CIO, and early designation of a chief architect.
Further, the establishment of an architectural team is necessary to define
an agency-specific architectural approach and process. The cycle for
completing an enterprise architecture highlights the need for constant
monitoring and oversight of architectural activities and progress, and for
architecture development teams to work closely with agency business line
executives to produce a description of the agency's operations, a vision of
the future, and an investment and technology strategy for accomplishing
defined business goals. The architecture is maintained through continuous

modification to reflect the agency's current baseline and target business
practices, organizational goals, vision, technology, and infrastructure.

In initiating its enterprise architecture process, VA has applied key
principles of the Federal CIO Council's guidance and has put in place some
core elements of the council's enterprise architecture framework. For
example, in the area of executive commitment, the department has obtained
crucial buy-in and support from the secretary, department-level CIO, and
other senior executives and business teams; this is essential to raising
awareness of and leveraging participation in developing the architecture. As
evidence of his commitment, last April the secretary established a team made
up of VA senior management business line and information technology
professionals to develop an enterprise architecture strategy. The team met
on weekends over the course of about 60 days and, in August 2001, issued an
executive enterprise architecture strategy that articulates the department's
policy and principles governing the development, implementation, and
maintenance of VA's enterprise architecture.

VA is in the process of establishing committees to manage, control, and
monitor activities and progress in fully developing and implementing its
enterprise architecture. For example, VA's information technology board has
begun functioning as the department's enterprise architecture executive
steering committee, with responsibility for directing, overseeing, and
approving core elements and actions of the enterprise architecture program.
As part of VA's actions to develop and advance its enterprise architecture,
it has also chartered an enterprise architecture council- which when
activated-is expected to assist in developing project priorities and
performing management reviews and evaluations of IT project proposals. In
addition, VA is in the process of establishing an enterprise architecture
program management office and, over the last 8 months, has been recruiting a
permanent chief architect to provide overall leadership and guidance for the
enterprise architecture program. These management entities are essential for
ensuring that the department's IT investments are aligned with the
enterprise architecture and optimize the interdependencies and
interrelationships among business operations and the underlying IT that
supports them.

Further, as part of its enterprise architecture strategy, VA has chosen a
highly recognized enterprise architecture framework that will be used to
organize the structure of the architecture.5 To facilitate its selection of

a framework, VA consulted with experts from the private sector and

5Among the experts that VA consulted was John Zachman, author of "A
Framework for Information Systems Architecture," referred to as the Zachman
framework (IBMSystemsJournal,vol. 26(3), 1987). This framework provides a
common context for understanding a complex structure and enables
communication among those involved in developing or changing the structure.

borrowed lessons learned from officials involved in architecture development
at other federal agencies.

VA has begun defining its current architecture, an important step for
ensuring that future progress can be measured against such a baseline, and
is also developing its future (target) telecommunications architecture. In
addition, to assist in the management of new IT initiatives, VA is
considering using a system that it has designed to link the management of
its enterprise architecture program to the department's capital planning and
project management. It is also considering using a Web-based tool that it
has designed to collect data on business rules, requirements, and processes
that will be integrated into the enterprise architecture management process.

While VA has taken several important steps forward, it is important to note
that the department has many more critical work steps ahead in implementing
and managing its enterprise architecture. Using the Federal CIO Council's
enterprise architecture guide as a basis for analysis, table 1 illustrates
some key steps that have been accomplished, along with examples of the many
critical actions VA must still address to implement and sustain its
enterprise architecture program. Accomplishing these remaining steps will
require continued and substantial time, effort, and commitment.

 Table 1: VA's Progress in Developing, Implementing, and Using an Enterprise
                                Architecture

aChief Information Officer Council.
bA repository is an information system used to store and access
architectural information, relationships among the information elements, and

work products.

Source: GAO analysis.

Among the key activities requiring immediate attention is establishment of a
program management office headed by a permanent chief architect to manage
the development and maintenance of the enterprise architecture. VA has begun
establishing such an office and is currently recruiting a chief architect.
However, until the department has an office that is fully staffed with
experienced architects and hires a chief architect with the requisite core
competencies, it will continue to lack the management and oversight
necessary to ensure the success of its enterprise architecture program.
Further, until the department has completed an implementation plan that
delineates how it will develop, use, and maintain the enterprise
architecture, it will lack definitive guidance for effectively managing the
enterprise architecture program.

Further, a lot of work lies ahead related to VA's efforts toward developing
its baseline and target architectures. A crucial first step in building the
enterprise architecture is identifying and collecting existing products that

describe the agency as it exists today and as it is intended to look and
operate in the future. While VA has developed a baseline application
inventory to describe its "as is" state, it has not yet completed validating
the inventory, or completed detailed application profiles for the inventory,
including essential information such as business functions, information
flows, and external interface descriptions. Similarly, to define its vision
of future business operations and supporting technology, VA must still
collect crucial information for its target architecture, including
information on its proposed business processes, strategic plans, and
requirements.

Beyond these planning and development activities, VA will also have to
ensure the successful transition and implementation of its enterprise
architecture. Evolving the agency from its baseline to the target
architecture will require concurrent, interdependent activities and
incremental development. As such, VA will need to develop and maintain a
sequencing plan to provide a step-by-step approach for moving from the
baseline to the target architecture. Development of this sequencing plan
should consider a variety of factors, including sustaining of operations
during the transition, anticipated management and organizational changes,
and business goals and operational priorities. Ultimately, VA's success in
using the architecture will depend on active management and receptive
project personnel, along with effective integration of the enterprise
architecture process with other enterprise life cycle processes.

A key aspect of VA's enterprise architecture program is the integration of
security practices into the enterprise architecture. The CIO Council has
articulated guidelines for doing so.6 For example, the architecture policy
should include security practices and the architecture team should include
security experts. In its enterprise architecture strategy document, VA has
committed to including security in all elements of its enterprise
architecture. Further, VA's executive-level security officer served as a
member of its architecture team. As VA moves forward in developing,
implementing, and using its enterprise architecture, we would expect it to
include information security details relating to the design, operations,
encryption, vulnerability, access, and use of authentication processes. A
commitment to building information security into all elements of its
enterprise architecture program is essential to helping VA meet the
challenges that it faces in protecting its information systems and sensitive
data.

As VA moves forward with its enterprise architecture management program, it
should ensure that remaining critical process steps outlined in the federal
CIO guidance are sufficiently addressed and completed within reasonable
timeframes. With the enhanced management capabilities

6Chief Information Officer Council, APracticalGuideto
FederalEnterpriseArchitecture,Version 1.0 (Washington, D.C., February 2001).

Information Security Challenges Continue to Require Top Management Attention

provided by an enterprise architecture framework, VA should be able to (1)
better focus on the strategic use of emerging technologies to manage its
information, (2) achieve economies of scale by providing mechanisms for
sharing services across the department, and (3) expedite the integration of
legacy, migration, and new systems.

Information security continues to be among the top challenges that the
department must contend with. As you know, in carrying out its mission, VA
relies on a vast array of computer systems and telecommunications networks
to support its operations and store the sensitive information that it
collects related to veterans' health care and benefits. VA's networks are
highly interconnected, its systems support many users, and the department is
increasingly moving to more interactive, Web-based services to better meet
the needs of veterans. Effectively securing these computer systems and
networks is critical to the department's ability to safeguard its assets,
maintain the confidentiality of sensitive veterans' health and disability
benefits information, and ensure the reliability of its financial data.

Mr. Chairman, when we last testified, VA had just established a
department-level information security management program and hired an
executive-level official to head it.7 VA had also finalized an information
security management plan to provide a framework for addressing longstanding
departmentwide computer security weaknesses. However, as our testimony
noted, the department had not implemented key components of a comprehensive,
integrated security management program that are essential to managing risks
to business operations that rely on its automated and highly interconnected
systems. This condition existed despite our previous recommendation that VA
effectively implement and oversee its computer security management program
through assessing risks, implementing policies and controls, promoting
awareness, and evaluating the effectiveness of information system controls
at its facilities. As with its enterprise architecture, the Secretary
expressed his intent to implement measures that would remedy existing
deficiencies in the department's security program.

The effects of not having a fully integrated computer security management
program in place remain evident. Since the subcommittee's hearing on this
topic last April, VA and its Office of Inspector General have continued to
report pervasive computer security challenges. VA's September 2001 report on
compliance with recently enacted government information

7GAO-01-550T.

8U.S. General Accounting Office,
VAInformationSystems:ComputerSecurityWeaknessesPesistat
theVeteransHealthAdministration, GAO/AIMD-00-232 (Washington, D.C.:
September 8, 2000).

9

security reform legislation revealed that the department had not implemented
effective information security controls for many of its systems and major
applications. Last October, VA's inspector general also reported that it had
found significant problems related to the department's control and oversight
of access to its systems, including that VA had (1) not adequately limited
the access of authorized users or effectively managed user identifications
and passwords, (2) not established effective controls to prevent individuals
from gaining unauthorized access to its systems, (3) not provided adequate
physical security to its computer facilities, and (4) not updated and tested
disaster recovery plans to ensure continuity of operations in the event of a
disruption in service.

Many of these access and other general control weaknesses mirror
deficiencies we have reported since 1998, and that VA's inspector general
continues to report as a material weakness in the department's internal
controls.10 Based largely on weaknesses of this type, last fall the House
Government Reform Subcommittee on Government Efficiency, Financial
Management and Intergovernmental Relations gave VA a failing grade in
computer security.11

Progress Being Made, But Important Elements of a Comprehensive Computer
Security Management Program Still Lacking

VA's senior leadership has shown greater awareness of and concern for the
severity of the department's computer security problems, and since last
April has taken steps aimed at strengthening VA's overall security posture.
Specifically, to provide greater management accountability for information
security, the secretary has mandated information security performance
standards for members of the department's senior executive service. In
addition, VA's cyber security officer-the department's senior security
official-has organized his office to focus more directly on the

9The government information security reform provisions of the fiscal year
2001 Defense Authorization Act (P.L. 106-398) require annual agency program
reviews and annual independent evaluations for both non-national security
and national security information systems.

10Department of Veterans Affairs Office of Inspector General, Report
oftheAudit of theDepartment of VeteransAffairs
ConsolidatedFinancialStatementsforFiscalYears2001and2002(Washington, D.C.,
February 27, 2002).

11House Committee on Government Reform. Subcommittee on Government
Efficiency, Financial Management and Intergovernmental Relations,
ComputerSecurity:How Isthe Government Doing? 107th Cong., 1st sess., 9
November 2001.

critical elements of information systems control that are defined in our
information system controls audit methodology.12 Further, the department has
adopted the National Institute of Standards and Technology's federal
information technology security assessment framework to use in determining
the current status of these controls and measuring the progress of
information security program improvements.

The cyber security officer also recently revised the department's security
management plan to update security policies, procedures, and technical
standards. The updated plan outlines actions for developing risk-based
security assessments, improving the monitoring and testing of systems
controls, and implementing departmentwide virus-detection software and
intrusion-detection systems. The plan places increased emphasis on
centralizing key security functions that previously were decentralized or
nonexistent, including virus detection, systems certification and
accreditation, network management, configuration management, and incident
and audit analysis.

Yet even with this positive direction, VA's actions do not fully address
remaining problems, and are inadequate to cover the breadth of matters
essential to a comprehensive security management program. Our 1998 report on
effective security management practices used by several leading public and
private organizations13 and a companion report on risk-based security
approaches in 199914 identified key principles that can be used to establish
a management framework for more effective information security programs.
This framework is depicted in figure 2. The leading organizations we
examined applied these principles to ensure that information security
addressed risks on an ongoing basis. Further, these have been cited as
useful guidelines for agencies by the Federal CIO Council and incorporated
into the council's information security assessment framework,15 intended for
agency self-assessments.

12U.S. General Accounting Office, FederalInformation
SystemControlsAuditManual,GAO/AIMD-12.19.6 (Washington, D.C., January 1999).

13U.S. General Accounting Office, Information SecurityManagement:Learning
FromLeading Organizations,GAO/AIMD-98-68 (Washington, D.C., May 1998).

14U. S. General Accounting Office,InformationSecurityRiskAssessmen:
PracticesofLeading Organizations,GAO/AIMD-00-33 (Washington, D. C., November
1999).

15Chief Information Officer Council, FederalInformation Technology Security
Assessment Framework (Washington, D.C., November 28, 2000).

Figure 2: Information Security Risk Management Framework

Source: GAO/AIMD-98-68.

Using our information security risk management framework as criteria, table
2 summarizes both the actions that VA has taken and those still needed to
ensure that it has a comprehensive computer security management program. As
shown, while VA has completed a number of important steps, its efforts in
each of the five key areas of effective computer security program
management-central security management, security policies and procedures,
risk-based assessments, security awareness, and monitoring and
evaluation-have not yet included key actions that are essential for
successful and effective program implementation.

     Table 2: Actions Needed to Ensure a Comprehensive Computer Security
                             Management Program

  Important elements of a
     computer security
   management program c       Actions VA has taken         Actions still needed
                                                       Ensure full-time security
                                                       officers or staff with
                           Established a               primary duty for security
Central security           department-level informationare assigned to information
management function to     security officer Began      security officer positions,
guide and oversee          requiring full-time securityand clearly define their
compliance with            officers or staff with      roles and responsibilities
established policies and   primary duty for security atDevelop guidance to ensure
procedures and review      all facilities Established aauthority and independence
effectiveness of the       CIO subcommittee to improve for security officers
security environment       departmentwide coordination Develop policies and
                           on security issues          procedures to ensure
                                                       departmentwide coordination
                                                       of security functions
   Security policies and
 procedures that govern a                              Refocus department policy to
     complete computer                                 address security from an
   security program and    Updating department securityinterconnected VA systems
  integrate all security       policy and guidance     environment perspective in
       aspects of an       Developed technical securityaddition to that of
      organization's        standards for some network individual systems Develop
  environment, including            platforms          and implement technical
 local area networks, wide                             security standards for
    area networks, and                                 mainframe and other systems
    mainframe security                                 and security software
                                                       Include best minimum
Periodic risk assessments  Developed abbreviated risk  standards or guidance for
to assist management in    methodology as part of the  performing risk assessments
making decisions on        Government Information      in methodology Develop
necessary controls to      Security Reform Act process guidance for determining
help ensure that security  Established policy requiringwhen an event is a
resources are effectively  risk to be assessed when    significant change and
distributed to minimize    significant changes are madeexplaining the level of risk
potential loss             to computer systems         assessment required for
                                                       these system changes
 Important elements of a
    computer security
  management program c         Actions VA has taken         Actions still needed
  Security awareness to
   educate users about
   current information     Implemented a departmentwide    Establish a process to
security risks, policies,   security awareness program   ensure program compliance
     and procedures
                                                         Develop specific
                                                         requirements for
                                                         conducting compliance
                                                         review program Develop an
                                                         ongoing program for
                                                         testing controls to
                                                         include assessments of
                          Issued contract for            both internal and external
                          independent compliance reviews access to VA systems;
                          of ongoing initiatives related expand current tests to
                          to security controls Performed identify unauthorized or
                          penetration testing of its Web vulnerable external
                          sites from the Internet        connections to VA's
                          Implemented computer           network Establish a
Monitoring and evaluating virus-detection software       process for tracking the
   computer controls to   departmentwide Began           status of security
       ensure their       developing an inventory of     weaknesses, corrective
  effectiveness, improve  security weaknesses            actions taken, and
    them, and oversee     Established a process for      independent validation of
       compliance         reporting computer security    the corrective actions
                          incidents and piloted          Develop a process for
                          intrusion-detection systems at routinely analyzing the
                          selected locations Developed a results of computer
                          certification and              security reviews to
                          accreditation framework for    identify trends and
                          its general support and major  vulnerabilities and apply
                          applications                   appropriate
                                                         countermeasures to improve
                                                         security Develop a
                                                         proactive security
                                                         incident response program
                                                         to monitor user access for
                                                         unusual or suspicious
                                                         activity

CU.S. General Accounting Office, Executive Guide: Information Security
Management, GAO/AIMD-98-68 (Washington, D.C.: April 7, 1998).

Source: GAO analysis.

As the table illustrates, VA's security management program continues to lack
essential elements required to protect the department's computer systems and
networks from unnecessary exposure to vulnerabilities and risks. For
example, while VA has begun to develop an inventory of known security
weaknesses, it continues to be without a comprehensive, centrally managed
process that will enable it to identify, track, and analyze all computer
security weaknesses. Further, the updated security management plan does not
articulate critical actions that VA will need to take to correct specific
control weaknesses or the time frames for completing key actions. While the
plan calls for monitoring VA's computer control environment to ensure
compliance, the plan does not provide a framework to guide the monitoring
activities by, for example, identifying the specific security areas to be
reviewed, the scope of compliance work to be performed, the frequency of
reviews, reporting requirements, or the resolution of reported issues.

VA also lacks a mechanism for collecting and tracking performance data,
ensuring management action as needed and, when appropriate, providing
independent validation of program deliverables. Without these essential

elements, VA will have only limited assurance that its financial information
and sensitive medical records are adequately protected from unauthorized
disclosure, misuse, or destruction. Accordingly, as VA continues to improve
upon its information security management, it should move expeditiously to
address the gaps we are highlighting in table 2.

In commenting on the department's current security posture, VA's cyber
security officer stated that efforts are planned or underway to address the
actions not yet completed. He added that by August 31, 2002, the department
expects to have a plan for completing all of the necessary corrective
actions.

Overarching Organizational and Management Issues Could Hinder VA's Ability
to Fully Address Information Security Challenges

While VA is clearly placing greater emphasis on its information security,
its cyber security officer will be challenged to manage the security
function on a departmentwide basis. As the department is currently
organized, more than 600 information security officers in VA's three
administrations

16

and its many medical facilities throughout the country are responsible for
ensuring that appropriate security measures are in place. These information
security officers report to their facility's director or the chief
information officer for their administration. However, there is neither
direct nor indirect reporting to VA's cyber security officer, thus raising
questions about this official's ability to enforce compliance with security
policies and procedures and ensure accountability for actions taken
throughout the department. Further, because VA's information security budget
relies on funding by its component administrations, the cyber security
officer lacks control and accountability over a significant portion of the
financial resources that the security program depends on to sustain

17

its operations.

Successfully managing information security under this organizational
structure, therefore, will in large part depend on the extent to which VA's
business managers assume responsibility for implementing the appropriate
policies and controls to mitigate risks, and work collaboratively and
cooperatively with the cyber-security officer. Consequently, it will be
essential for VA to hold its senior managers accountable for information
security at their respective facilities and administrations. VA has taken a
critical step toward achieving this by establishing security performance
standards for its senior executives. These standards must be effectively
applied and enforced, however, to ensure a successful outcome.

16VHA provides medical care at 163 hospitals, more than 800 community and
facility-based clinics, 135 nursing homes, 43 domiciliaries, 206
readjustment counseling centers, and various other facilities.

17For example, to help support its fiscal year 2002 security program budget
request of about $55 million, VA expects to receive about $22 million in
funding from VHA and $12 million from the department's other administrations
and offices.

Progress on the Compensation and Pension Replacement System Is Disappointing

The VETSNET compensation and pension replacement effort grew out of an
initiative that VBA undertook in 1986 to replace its outdated benefits
delivery network (BDN) and modernize its compensation and pension,
education, and vocational rehabilitation benefits payment systems. VBA had
expected these modernized systems to provide a rich source for answering
questions about veterans' benefits and enable faster processing of benefits.
In 1996, after experiencing numerous false starts and spending approximately
$300 million on the overall modernization, VBA revised its strategy and
began focusing on modernizing the compensation and pension (C&P) payment
system. At that time, VBA estimated that the C&P replacement project would
cost $8 million and be completed in May 1998.

Since its inception, however, VBA has been plagued with problems in carrying
out the C&P replacement initiative. As detailed in the attachment, our
various publications since 1996 have highlighted consistent and longstanding
concerns in several areas, including project management, requirements
development, and testing. Our testimony last April noted that VBA had made
some progress in developing and testing software products that would become
part of the system. Nevertheless, we also noted that VBA had not addressed
several important issues that were key to its successful implementation,
including the need to develop an integrated project plan and schedule
incorporating all of the critical areas of this system development effort.18
As our prior work has pointed out, a significant factor contributing to
VBA's continuing problems in developing and implementing the system has been
the level of its capability to develop and maintain high-quality software on
any major project within existing cost and schedule constraints-a condition
that we identified during our

19

1996 assessment of the department's software development capability.

Critical Actions Have Not Been Taken to Ensure Successful Implementation of
the C&P Replacement System

After 6 years of work-4 years beyond what its initial estimate called for-
VBA has spent at least $35 million, without much demonstrable progress
toward implementing the replacement system. Since last April, it has not
made substantial progress in addressing the concerns raised by our earlier
work. Although, last year, VBA indicated that it had implemented its rating
board automation tool and had completed developing and testing its four
other software products, 20 the administration stated during our recent
review that two of the software products that will support its award
processing and finance and accounting systems still need further

18GAO-01-550T.

19U.S. General Accounting Office,SoftwareCapabityEvaluaion:
VA'sSoftwareDevelopmentProcess isImmature, GAO/AIMD-96-90 (Washington, D.C.:
June 19, 1996).

20The current C&P replacement strategy incorporates five software products:
Search and Participant Profile, Rating Board Automation 2000, Modern Award
Processing-Development, Award Processing, and Finance and Accounting System.
The first product deployed in November 2000-Rating Board Automation 2000-was
to assist veterans service representatives in rating benefits claims.

development. Moreover, VBA has not increased the number of payments using
these new software products beyond the 10 original claims that it had pilot
tested in February 2001. In addition, it continues to lack an integrated
project plan and schedule that incorporate all of the critical areas of this
system development activity. Further, VBA still has not obtained essential
support from the field office staff that will be required to use the new
software, and requirements for the new software have not yet been validated.
These deficiencies are significant, given that the software application that
VBA developed to assist veterans service representatives in rating benefits
claims (Rating Board Automation 2000) did not meet users' needs and achieved
less timely claims processing results.

At this time, VBA also is without a project manager to oversee the project.
Progress made early in 2000 toward creating a project control board to
manage the C&P replacement was curtailed when the project manager departed
last April. Until VBA provides appropriate management and oversight for all
aspects of the project's development and implementation, it will not be
positioned to ensure that this project will deliver a cost-effective
solution with measurable and specific program-related benefits.

Further, the schedule for implementing the replacement system continues to
undergo change, resulting in additional delays. Last April, VBA had planned
to deploy VETSNET in all of its 58 regional offices in July 2002. However,
VBA officials have since modified the deployment time frame twice, with its
latest proposal being to deploy each of the five applications separately
over 2 years, beginning in June 2003. VBA management has not yet approved
this latest strategy.

Studies Highlight the Need for Additional Testing and Information to Support
Continued Systems Development

Last year, the secretary expressed concerns about the VETSNET project and
called for an independent audit of the C&P replacement system to facilitate
his decision on whether to continue the initiative. Accordingly, a
contractor was hired in May 2001 to assess (1) whether the system
architecture will be capable of supporting VBA's projected future workload,
and (2) whether the system being developed will meet future functional,
performance, and security needs. The contractor reported last September that
the system architecture would be able to process VBA's projected future
workload.

However, the contractor neither assessed nor reported on whether the system
will meet future functional business needs, and the scope of its review did
not generate sufficient information to fully evaluate and make an informed
decision on whether the project should proceed. The review focused primarily
on the system's ability to perform efficiently under a heavy workload, and
did not include user acceptance or the functional testing that is needed to
ensure that the system can fully satisfy user requirements and that deployed
software can be used without significant errors. Further, the review did not
fully address the security requirements

for the new system. VA's department-level CIO agreed that the scope of the
contractor's review had been limited to a technical review of whether
VETSNET could handle the anticipated workload. He also acknowledged the need
for functional testing and an integrated project plan.

Similar concerns about VBA's strategy for the C&P replacement project were
also documented in an October 2001 report issued by the VA claims processing
task force.21 In its report, the task force emphasized that limited user and
functional testing posed a major problem for VBA in developing and
implementing its systems. The task force highlighted material deficiencies
in VBA's strategic planning and its implementation and deployment of new and
enhanced information technology products and initiatives, as had been
pointed out in an earlier report. Further, the task force questioned whether
VETSNET represented a viable long-term solution, in part because it does not
provide support for a redesigned and integrated claims process across VA's
administrations and offices.

In commenting on these reports' findings, VBA's CIO stated that, by the end
of March 2002, her office anticipated completing a remediation plan that
will address the most critical concerns identified in the contractor's
review. She stated that the office is in the process of developing a
statement of work to obtain contractor support to develop additional
functional testing capability. The statement of work is scheduled for
completion in June 2002. In addition, the CIO is negotiating with relevant
VBA business groups to secure subject matter experts to validate business
requirements and assist with the functional testing.

21The claims processing task force was formed in May 2001, when the
secretary of veterans affairs asked a group of individuals with significant
VA experience to assess and critique VBA's compensation and pension
organization, management, and processes and to develop recommendations to
significantly improve VBA's ability to process veteran claims for disability
compensation and pension.

Without additional maintenance, it is uncertain that the BDN will be able to
continue accurately processing the many benefits payments that VBA must
make.22 In its report, the claims processing task force warned that the
system's operations and support were approaching a critical stage, with the
potential for performance to degrade and eventually cease. The task force
recommended that the BDN be sustained and upgraded to ensure that payments
to veterans would remain prompt and uninterrupted until VBA is able to field
a replacement system. VBA officials have stated that they are working on a
plan to address this issue. This plan is expected to include purchasing an
additional mainframe computer to help extend the system's operation until
2007-the date by which new systems are planned to be operational for all
three benefits payment business lines.

As you can see, Mr. Chairman, despite many years of work, VBA still has a
number of fundamental tasks to accomplish before it can successfully
complete development and implementation of the VETSNET project. Before
proceeding with this project, VBA must assess and validate users'
requirements for the new system to ensure that business needs are met. It
also needs to complete testing of the system's functional business
capability, as well as end-to-end testing to ensure payments are made
accurately. Finally, it must establish an integrated project plan to guide
its transition from the old to the new system. Until VBA performs a complete
analysis of the initiative, as the secretary has indicated he would do, it
is questionable whether additional resources should be expended on continued
systems development activities.

VHA Continues to Expand Its Use of DSS

Unlike VBA's work on VETSNET, VHA continues to make progress in expanding
overall use of its decision support system (DSS). As you know, DSS is an
executive information system designed to provide VHA managers and clinicians
with data on patterns of patient care and patient health outcomes, as well
as the capability to analyze resource utilization and the cost of providing
health care services. VHA completed its implementation of DSS in October
1998. However, in September 2000, we testified that DSS had not been fully
utilized since its implementation, and noted that DSS was not being used for
all the purposes intended.23

Last April, we testified that VHA had shown moderate progress in increasing
usage of DSS among its veterans integrated service networks (VISN) and
medical centers, and encouraged VA to continue providing top management
support to ensure that the system is fully utilized and that financial and
clinical benefits are realized. Our testimony noted several

22The current C&P payment system alone processes about 3.2 million payments
each month. Altogether, the three benefits payment business lines process
about 3.5 million payments monthly.

23 GAO/T-AIMD-00-321.

efforts that VHA had undertaken to encourage greater use of DSS, including
using DSS data to support the fiscal year 2002 resource allocation process
and as a consideration in preparing VISN directors' year-end performance
appraisals, requiring VISN directors to provide examples of their reports
and processes that rely on DSS data, and ensuring that medical centers'
processing of DSS data is current (no more

24

than 60 days old).

VHA's initiatives to encourage greater use of DSS have yielded results. The
use of DSS data in the fiscal year 2002 allocation process has clearly
raised VHA's awareness about the importance of this information. VHA's most
recent DSS processing report, dated January 31, 2002, revealed that all 22
VISNs had completed processing fiscal year 2001 DSS data and that seven
VISNs had begun processing fiscal year 2002 data. Further, every VISN has
provided both clinical and financial examples of DSS usage, and this
information is now being considered in the quarterly reviews of the VISN
directors' performance. As a result, VHA's managers have grown more
knowledgeable about and have begun to make more informed decisions regarding
the cost of care being provided by their facilities.

Initiatives Are Being Taken to Improve the Accuracy, Timeliness, and
Availability of DSS Data

VHA continues to explore other initiatives to improve the accuracy and
completeness of DSS data. In response to a report issued by VA's inspector
general in March 1999,25 regarding the failure of some medical facilities to
follow the DSS basic structure for capturing workload data and associated
costs, VHA has taken several actions, including

* implementing a VHA decision support system standardization directive that
requires annual standardization audits and the reporting of consecutive
repeat occurrences of non-compliance to the assistant deputy under secretary
for health;

* developing an audit tool for use in determining a facility's compliance
with the DSS basic model for capturing workload data and associated costs;
and

* performing a standardization audit in September 2001 to assess the extent
to which each facility's DSS departments and products complied with national
standards.26

24GAO-01-550T.

25Department of Veterans Affairs, Office of Inspector General, Audit
ofVeteransHealthAdministration Decision Support SystemStandardization,
Report No. 9R4-A19-075 (Washington, D.C., March 31, 1999).

26The standardization audit revealed a 99.6 percent compliance rate with the
National Department List, a 98.8 percent compliance rate with the National
Product List, and a 99.5 percent match between facilities' cost centers and
DSS departments.

Further, in response to managers' concerns that DSS data are not timely and
easy to access, the DSS program office initiated several actions. These
include establishing a working group last July to identify best practices
and recommend actions for improving processing efficiency and the timeliness
and availability of DSS data. To date, the working group has provided all
DSS sites with an updated monthly guide detailing each step of the process,
and has distributed a pharmacy rejects database and a step-by-step guide for
processing these rejects. These products should help increase the efficiency
of the monthly processing and facilitate more accurate and timely data. In
addition, the program office has authorized two sites to pilot test an
application aimed at providing the end user or manager with a user-friendly
front end to display DSS information and allow patient inquiry.

In addition, several VISNs have independently begun exploring options for
providing easier access to DSS data. For example, one is examining the
feasibility of establishing a data warehouse where data extracted from DSS
can be transformed into a format that will facilitate queries and reports
that are simple to create and quick to run.27 Another has begun building a
data repository for use in creating an application to compile and

28

deliver data requested by managers or clinicians.

Even with these accomplishments, however, top management involvement and
continued support will be critical to ensuring that VHA continues to make
progress in improving the operational efficiency and effectiveness of DSS,
and that it realizes the full clinical and financial benefits of this
system. In March 2001, oversight for the DSS program was transferred from
VHA's chief information officer to its chief financial officer. Since that
time, VHA has also assigned three different acting directors to lead the
program. However, VHA has not yet selected a permanent director to provide
consistent management and oversight. In addition, of 56 personnel positions
allotted to the DSS program office, 19 positions had not been filled at the
end of January 2002. Without a permanent director to lead the DSS program or
full staffing to support the system's operation, VHA runs the risk that
continued increases in usage of DSS, along with its associated benefits,
could be imperiled.

27 Veterans integrated service network 16 (Jackson, Mississippi).

28 Veterans integrated service network 13 (Minneapolis, Minnesota)

The Government Computer-based Patient Record Initiative Is Moving Away From
Its Original Goal

Mr. Chairman, you also asked us to update you on VA's progress, in
conjunction with the Department of Defense (DOD) and the Indian Health
Service (IHS), in achieving the ability to share patient health care data as
part of the government computer-based patient record (GCPR) project. Having
readily accessible data to facilitate services to our nations' military
personnel and others has proved particularly significant in light of recent
terrorist actions and the associated responses that have been required.

The GCPR project developed out of VA and DOD discussions about ways to share
data in their health information systems and from efforts to create
electronic records for active duty personnel and veterans. As you know, the
patients served by VA's and DOD's systems tend to be highly mobile, and
consequently, their health records may be at multiple federal and nonfederal
medical facilities, both in and outside of the United States. In November
1997, the president called for the two departments to develop a
"comprehensive, life-long medical record for each service member," and in
August 1998-8 months after the GCPR project was officially
established-issued a directive requiring VA and DOD to develop a
"computer-based patient record system that will accurately and efficiently
exchange information."29 IHS later became involved because of its expertise
in population-based research and its longstanding relationship with VA in
caring for the Indian veteran population.

As originally envisioned, GCPR was not intended to be a separate
computerized health information system, nor was it meant to replace VA's,
DOD's, and IHS's existing systems. Rather, it was intended to allow
physicians and other authorized users at these agencies' health facilities
to access data from any of the other agencies' health facilities by serving
as an electronic interface among their health information systems. The
interface was expected to compile requested patient information in a
temporary, "virtual" record, that could be displayed on a user's computer
screen.

In April 2001, we reported that expanding time frames and cost estimates, as
well as inadequate accountability and poor planning, tracking and oversight,
had raised doubts about GCPR's ability to provide the benefits expected.30
In particular, we noted that the project's time frames had significantly
expanded and that its costs had continued to increase. In

29National Science and Technology Council, ANationalObligation:Planningfor
Health Preparedness for andReadjustmentof theMitary,Veterans,andTheir
FamiesAfter FutureDeployments, Presidential Review Directive 5 (Washington,
D.C., Executive Office of the President, Office of Science and Technology
Policy, August 1998).

30U. S. General Accounting Office,Computer-BasedPaientRecords:
BeterPlanningandOversightby VA,DOD,andIHS Would EnhanceHealth
DataSharing,GAO-01-459 (Washington, D.C., April 30, 2001).

addition, basic principles of sound IT project planning, development, and
oversight had not been followed, creating barriers to progress. For example,
clear goals and objectives had not been set; detailed plans for developing,
testing, and implementing the new software had not been established; and
critical decisions regarding goals, costs, and time frames were not binding
on all parties. Further, data exchange and privacy and security issues
critical to the project's success remained to be addressed.

As a result of these concerns, we recommended that the three agencies (1)
designate a lead entity with final decisionmaking authority and establish a
clear line of authority for the GCPR project and (2) create comprehensive
and coordinated plans that included an agreed-upon mission and clear goals,
objectives, and performance measures, to ensure that the agencies can share
comprehensive, meaningful, accurate, and secure patient health care data. In
commenting on the report, VA, DOD, and IHS all concurred with our findings
and recommendations.

Nonetheless, progress on the GCPR initiative continues to be disappointing.
The scope of the project increasingly has been narrowed from its original
objectives and it continues to proceed without a comprehensive strategy. For
example, in responding to our report, VA, DOD, and IHS provided information
on a new, near-term strategy for GCPR. However, this revised strategy is
considerably less encompassing than the project was originally intended to
be. Specifically, rather than serve as an interface to allow data sharing
across the three agencies' disparate systems, as originally envisioned, a
first phase of the revised strategy calls only for a one-way transfer of
data from DOD's current health care information system to a separate
database that VA hospitals can access. While even this degree of data
sharing is a positive development, VA's clinicians, nonetheless, will only
be allowed to read, but not perform any calculations on the data received.
VA and DOD officials had initially planned to implement this near-term
capability in November 2001, but recently stated that they now expect to do
so by this July 2002. Further, the officials stated that they plan to change
the name of the project to the Federal Health Information Exchange.

Subsequent phases of the effort that were to further expand GCPR's
capabilities have also been revised. A second phase that would have enabled
information exchange among all three agencies-VA, DOD, and IHS-is now
expected to enable only a bilateral read-only exchange of data between VA
and IHS.

Further, according to VA officials, plans for a third phase, which was to
expand GCPR's capabilities to public and private national health information
standards groups, are no longer being considered for the project. Instead,
the third phase is now expected to focus only on expanding the data exchange
between VA and IHS and allowing limited data calculations and some
translation of terminology between the two

agencies. Under the revised strategy, there are no plans for DOD to receive
data from VA.

In addition, concerns expressed in our April 2001 report still need to be
addressed. For example, the GCPR project continues to operate without clear
lines of authority or a lead entity responsible for final decisionmaking.
Last August, the VHA CIO informed us that a draft memorandum of agreement,
designating VHA as the lead entity, was being considered within VA, DOD, and
IHS. However, this memorandum had not been approved or implemented at the
time that we concluded our review. The project also continues to move
forward without comprehensive and coordinated plans, including an
agreed-upon mission and clear goals, objectives, and performance measures.
Without clearly defined lines of authority and a comprehensive and
coordinated strategy, even the revised GCPR initiative is destined to
continue on an uncertain course-one that is unlikely to deliver substantial
results.

                                 * * * * *

In summary, VA has made good progress toward addressing a number of
important information technology concerns, but it still has much work to do.
Its current leadership is to be commended for the dedication that it has
demonstrated regarding VA's information technology problems. However, in
totality, the steps taken to date have not been sufficient to overcome the
wide range of deficiencies that threaten VA's operational effectiveness.
Many of VA's problems are longstanding and pervasive, and can be attributed
to fundamental weaknesses in management accountability- some of which can
only be overcome through serious restructuring of current reporting
relationships and lines of authority. Until VA makes a concerted effort to
ensure that all necessary processes and controls exist to guide the
management of its information technology program, it will continue to fall
short of its goals of enhancing operational efficiency and, ultimately,
improving service delivery to our nation's veterans.

Mr. Chairman, this concludes my statement. I would be pleased to respond to
any questions that you or other members of the subcommittee may have at this
time.

Contacts and For information about this testimony, please contact me at
(202) 512-6257

Acknowledgments ~or by e-mail at [email protected]. Individuals making key

contributions to this testimony included Nabajyoti Barkakati, Amanda C.
Gill, David W. Irvin, Tonia L. Johnson, Valerie C. Melvin, Barbara S.
Oliver, J. Michael Resser, Rosanna Villa, and Charles M. Vrabel.

GAO Products Highlighting Concerns with VETSNET C&P Replacement

Issuance date
Report/testimony Summary of report findings and conclusions

April 4, 2001 The project's viability was still a concern. It continued to
lack an integrated

GAO-01-550T ~project plan and schedule addressing all critical systems
development areas, to be used as a means of determining what needs to be
done and when. A pilot test of 10 original claims that did not require
significant development work may not have been sufficient to demonstrate
that the product was capable of working as intended in an organizationwide
operational setting.

September 21, 2000 VBA's software development capability remained ad hoc and
chaotic. The

GAO/T-AIMD-00-321 ~VETSNET implementation approach lacked key elements,
including a strategy for data conversion and an integrated project plan and
schedule incorporating all critical systems development areas. Further, data
exchange issues had not been fully addressed.

May 11, 2000 $11 million had reportedly been spent on VETSNET C&P; both the
May 1998

GAO/T-AIMD-00-74 ~completion date and revised completion date of December
1998 were not met. Contributing factors included lack of an integrated
architecture defining the business processes, information flows and
relationships, business requirements, and data descriptions, and VBA's
immature software development capability.

September 15, 1997 VBA's software development capability remained ad hoc and
chaotic, subjecting

GAO/AIMD-97-154  ~ the agency  to  continuing  risk of  cost overruns,  poor
quality software, and schedule delays in software development.

May 30, 1997 VETSNET experienced schedule delays and missed deadlines
because (1) it

GAO/AIMD-97-79 ~employed a new software development language not previously
used by the development team, one that was inconsistent with the agency's
other systems development efforts; (2) the department's software development
capability was immature and it had lost critical systems control and quality
assurance personnel, and (3) VBA lacked a complete systems architecture; for
example, neither a security architecture nor performance characteristics had
been defined for the project.

June 19, 1996 VETSNET had inherent risks in that (1) it did not follow sound
systems

GAO/T-AIMD-96-103 ~development practices, such as validation and
verification of systems requirements; (2) it employed a new systems
development methodology and software development language not previously
used; and (3) VBA did not develop the cost-benefit information necessary to
track progress or assess return on investment (for example, total software
to be developed and cost estimates).

June 19, 1996 VBA's software development capability was immature and it
could not reliably

GAO/AIMD-96-90 ~develop and maintain high-quality software on any major
project within existing cost and schedule constraints, placing its software
development projects at significant risk. VBA showed significant weaknesses
in requirements management, software project planning, and software
subcontract management, with no identifiable strengths.

(310419)EUR
*** End of document. ***