TITLE: B-298277, MadahCom, Inc., August 7, 2006
BNUMBER: B-298277
DATE: August 7, 2006
****************************************
B-298277, MadahCom, Inc., August 7, 2006
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: MadahCom, Inc.
File: B-298277
Date: August 7, 2006
Joel Singer, Esq., Sidley Austin LLP, for the protester.
Rod McCracken, Esq., and Amy Pereira, Esq., Army Corps of Engineers, for
the agency.
Jonathan L. Kang, Esq., and Michael R. Golden, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
Solicitation requirements requiring compliance with specific radio
frequency standard and minimum transmission range for equipment are unduly
restrictive of competition where agency fails to provide reasonable basis
for their inclusion in the solicitation.
DECISION
MadahCom, Inc. protests the terms of request for proposals (RFP) No.
W912GB-06-R-0019, issued by the Army Corps of Engineers for provision and
installation of mass notification systems (MNSes). The protester contends
that various technical requirements of the RFP are unduly restrictive of
competition because they are not reasonably related to the agency's needs
for an MNS.
We sustain the protest.
BACKGROUND
An MNS is a system designed to transmit alert messages and related
information to personnel in or near buildings during emergency situations.
An MNS can be provided for a single building or for multiple buildings in,
for example, a military base-wide system. Alert messages are triggered by
an individual user authorized to use the MNS. In the case of a
single-building MNS, the user triggers an alert message through the
autonomous control unit (ACU) in the building. In the case of a base-wide
MNS, the user triggers an alert message from the primary control center
for the base, which in turns sends the alert message to the ACU in each
building. Once an ACU receives the alert message, it is sent to various
devices, such as indoor and outdoor speakers and visual displays, that
relay the alert to personnel.
The Department of Defense (DoD) requires that buildings provide "timely
means to notify occupants of threats and instruct them what to do in
response to those threats." Unified Facilities Criteria (UFC) 4-010-01,
DoD Minimum Antiterrorism Standards for Buildings, para. B-4.7. A separate
UFC provides specific guidance for when an MNS is required in a DoD
building, as well as design and operation requirements:
Beginning with the fiscal year 2004 construction program, mass
notification is required in all new inhabited buildings, including new
primary gathering buildings and new billeting. Mass notification is
required in existing primary gathering buildings and existing billeting
when implementing a project exceeding the replacement cost threshold
specified in UFC 4-010-01. Mass notification is recommended in other
existing inhabited buildings when implementing a project exceeding the
replacement cost threshold. Mass notification is required for leased
buildings, building additions, and expeditionary and temporary
structures (see UFC 4-010-01).
UFC 4-021-01, Design and O&M: Mass Notification Systems, para. 1-6.1.
As discussed below, DoD has sought to procure MNSes for its bases in
Europe under several different types and versions of solicitations. The
current RFP seeks proposals to provide MNSes at U.S Army Europe (USAREUR)
facilities in Germany. The RFP anticipates a fixed-price contract to
install an MNS at Landstuhl; subject to availability of funds, the awardee
may also be instructed to install MNSes at Camp Vilseck, Camp Grafenwoehr,
and Kleber Kaserne. RFP at 3. Offerors are required to propose
all necessary personnel, materials, equipment, tools, supervision and
other items and services to furnish, install, test and provide a custom
emergency mass notification System (MNS), comprising of all hardware,
software, controllers, speakers, wiring, and all other components of
this system in a fully operational and operable condition inside of key
installation buildings, administrative areas, and community areas to
facilitate emergency notifications.
RFP, Specifications for Mass Notification System, at 4.
The USAREUR originally issued a solicitation for MNS requirements at 17
bases in Europe in December 2003. Contracting Officer's Statement para. 1.
The procurement of these requirements was subsequently assigned to the
Corps in December 2004. Decl. of USAREUR Consequence Management Program
Manager at 1. The Corps received the USAREUR's statement of requirements
(SOW) and issued a new solicitation based on those requirements in July
2005. Contracting Officer's Statement para. 6. The RFP anticipated award
of an indefinite-delivery/ indefinite-quantity (ID/IQ) contract, and
included requirements that the MNS equipment be "Motorola, system ASTRO
25, repeater site trunking system or equal." Id. para. 8. MadahCom engaged
in discussions with the Corps regarding various requirements, including
the Motorola-based specifications and the ID/IQ contract type, arguing
that they were unduly restrictive of competition. Id. para. 10. The Corps
subsequently suspended the RFP "until further notice" on July 29, 2005.
Id. para. 11.
In September 2005, the Corps sought to procure the MNS requirements
through a competition for task orders open only to those firms that had
earlier been awarded a multiple-award task order contract (MATOC) for
construction of family housing. Id. para. 12. MadahCom, which did not have
one of the MATOCs, filed a protest with our Office challenging the
solicitation on grounds that the anticipated task orders exceeded the
scope of the underlying contracts. MadahCom Protest, Sept. 20, 2005, at 2.
During the course of the protest, the agency advised our Office that the
task-order proposals submitted by the MATOC holders had expired, and that
the agency would not seek to obtain new or extended proposals. The agency
stated that it would instead reissue the July 2005 version of the RFP.
Contracting Officer's Statement para. 14. The agency requested that our
Office dismiss the protest based on the decision to take corrective
action; we did so on February 3, 2006.
The agency reissued the July 2005 version of the RFP on February 3, 2006.
On February 17, 2006, MadahCom filed a protest of this solicitation,
arguing that numerous provisions were unduly restrictive of competition.
MadahCom Protest, Feb. 17, 2006, at 2. The agency and protester's counsel
engaged in discussions regarding the protest counts, and appeared to have
reached an agreement regarding corrective action that would amend the
solicitation. Protest, exh. 18, MadahCom Protest Withdrawal, Mar. 14,
2006. The agency then advised our Office that it intended to issue a
revised solicitation, and MadahCom withdrew its protest. Id.
The agency issued a revised solicitation on March 30, 2006. Although many
of the issues raised in MadahCom's prior protest had been resolved, the
firm believed that the RFP still contained unduly restrictive provisions
and submitted a series of questions to the agency. Contracting Officer's
Statement paras. 23-26. The agency addressed these questions in a
solicitation amendment dated April 25, 2006. Following the issuance of the
amendment, MadahCom filed the current protest on May 5, 2006, again
alleging that several requirements of the solicitation were unduly
restrictive of competition or ambiguous, and also alleging that the agency
had failed to take adequate corrective action in response to its prior
protest.
DISCUSSION
In preparing a solicitation, a contracting agency is generally required to
specify its needs and solicit offers in a manner designed to achieve full
and open competition, so that all responsible sources are permitted to
compete. 10 U.S.C. sect. 305(a)(1)(A)(i), (B)(i) (2000). A solicitation
may include restrictive provisions or conditions only to the extent
necessary to satisfy the agency's needs or as authorized by law. 10 U.S.C.
sect. 2305(a)(1)(B)(ii). Where a solicitation provision is challenged as
unduly restrictive of competition, the procuring agency has the
responsibility of establishing that the specification is reasonably
necessary to meet its needs. ViON Corp., B-256363, June 15, 1994, 94-1 CPD
para. 373 at 4-5. Our Office reviews the adequacy of the agency's
justification by examining whether it is reasonable, that is, whether the
explanation can withstand logical scrutiny. Chadwick-Helmuth Co., Inc.,
B-279621.2,
Aug. 17, 1998, 98-2 CPD para. 44 at 3.
As discussed below, we believe the agency has not demonstrated that
solicitation requirements for (1) compliance with the Association of
Public-Safety Communications Officials International Project 25 (APCO 25)
standard for radio transmissions, and (2) a 10-kilometer range for
transmission and receiving stations are reasonably related to the agency's
needs for an MNS.[1] We also believe that the protester's challenges to
three solicitation provisions that the agency has now addressed through
proposed corrective action in response to the protest are clearly
meritorious and, therefore, warrant reimbursement of the protester's costs
of pursuing the protest.
(1) APCO 25 STANDARD
The RFP requires that the wireless transmissions and equipment for
offerors' proposed MNSes comply with the APCO 25 Statement of Requirements
for land mobile radios (LMRs). An LMR is a handheld or vehicle-mounted
non-tactical radio device operating within a specific frequency range that
allows its user to communicate with another LMR user. Decl. of Agency
Engineer, exh. 2, Army Supplement to DOD Policy for LMR Systems para. 3.a.
As explained below, the RFP requires two field radios, a general category
of radio which may include LMRs. RFP, Specifications for Mass Notification
System, at 6.
APCO is an association of public safety organizations that publishes
standards for communications technologies and advocates that governmental
agencies adopt those standards. See APCO website, available at:
http://www.apcointl.org. APCO 25 is a set of standards for digital radios
for use by public safety agencies intended to enable them to procure and
operate compatible LMRs. See Project 25 Statement of Requirements,
available at:
http://www.apco911.org/frequency/documents/03-20-06-PublishFinalVersionofReformattedP25SoR.pdf.
The RFP identified the following requirement for the MNS: "For the radio
transmission of the alarm to the MNS in the buildings and any loudspeaker
systems, a radio network shall be established with digital signal
transmission according to APCO 25 standard." RFP, Specifications for Mass
Notification System, at 24; see also id. at 25-26. Although the APCO 25
standard applies specifically to LMRs, the agency explained that the APCO
25 standard for purposes of this solicitation applies to all wireless
communications in the MNS, such as those from the base's primary control
center to each building's ACU, and not just LMR transmissions:
GAO: Where is an APCO 25 compliant radio used in an MNS?
PROGRAM MANAGER: The entire system is APCO 25 compliant. . . . This is
mostly dealing with the wireless communications portion of it so this
would be getting the communications from the control station to the
building itself. But when it's transmitted in the building, it goes over
a hard wire into speakers.
GAO: As a global requirement, under the solicitation, does every
wireless transmission need to be APCO 25 compliant?
PROGRAM MANAGER: Yes.
Hearing Transcript (Tr.) at 19:14-20:4.
The protester contends that the APCO 25 requirement is unduly restrictive
of competition because it is not required by UFC 4-021-01 and is not
necessary to meet the agency's general requirements for an MNS. The
protester further contends that it is prejudiced by the requirement
because its MNS does not comply with the APCO 25 standard, and MadahCom is
thus effectively precluded from competing for the contract award. Protest
at 15-16. The agency cites three primary rationales in support of the APCO
25 compliance requirement, which we discuss below.
(a) UFC 4-021-01 Requirements
The agency initially argued that APCO 25 compliance was required under DoD
policy regarding MNSes: "UFC 4-021-01, which governs the solicitation,
designates
APCO 25 compliance for wireless MNS, as an advanced technology, which will
increase functionality, reliability, and security." Agency Memorandum of
Law at 4. In its supplemental report, however, the agency conceded that
the UFC did not require the APCO 25 standard. Supplemental Agency
Memorandum of Law at 2.
During a telephone hearing conducted by our office, an agency engineer
testified that she was the individual responsible for adding the APCO 25
compliance requirement to the RFP. Tr. at 25:3-8.[2] Despite the agency's
prior acknowledgment that UFC 4-021-01 does not require compliance with
the APCO 25 standard, the agency engineer explained that APCO 25
compliance had been included in the solicitation because the standard was
required under the UFC:
GAO: [D]o you know who introduced the APCO 25 standard? Was it the Army
Corps or was it USAREUR? . . .
AGENCY ENGINEER: We set our specifications based on the UFC. In the
appendix B, in specific, B 1, it actually speaks of the APCO 25 as being
required.
Tr. at 24:3-13.
UFC 4-021-01, however, does not require use of the APCO 25 standard for an
MNS. The only reference to APCO 25 in the UFC is found in a table of
"Expected Near-term Mass Notification System Improvements," at the section
cited by the agency engineer in her testimony above:
+------------------------------------------------------------------------+
|Function |Current Capability |Expected Improvement |
|-------------+--------------------------------+-------------------------|
|Wireless |Many of the mass notification |Adoption of the encrypted|
|Communication|system radios available today |Association of Public |
| |are transmitting analog voice |Safety Communications |
| |and frequency-shift keying (FSK)|Officials (APCO) Project |
| |telemetry. Manufacturers have |25 Protocol (when fully |
| |developed mechanisms for adding |deployed and more broadly|
| |security that significantly |available) will further |
| |reduces the chance of |reduce the chances of |
| |unauthorized commands being |unauthorized commands |
| |accepted. However, a person with|being accepted and will |
| |a receiver tuned to the correct |make interception of |
| |frequency can listen to the |messages and commands |
| |analog voice transmissions, and |very difficult. |
| |once voice communications are | |
| |enabled, nearby unauthorized | |
| |transmitters could be used to | |
| |distort or override messages. | |
+------------------------------------------------------------------------+
Protest, exh. 1, UFC 4-021-01, at B-1.
As shown above, the UFC provision cited by the agency engineer neither
requires nor recommends APCO 25 compliance for an MNS. Rather, the UFC
identifies APCO 25 as a possible future improvement.[3] On this record, it
is clear that UFC 4-021-01 does not require inclusion of the APCO 25
standard in a solicitation for an MNS. Further, we believe that the record
shows that the agency engineer incorrectly believed that the APCO 25
standard was required by the UFC at the time she added this requirement to
the RFP.
(b) Interoperability
The agency next contends that the APCO 25 standard requirement ensures
that an MNS purchased by the agency under the contract will not commit the
agency to proprietary technology for its MNS needs, and, therefore, the
MNS procured under the solicitation will be interoperable with other MNSes
and related communications systems. This argument, however, was first
raised in the agency's memorandum of law, and was not supported by any
statements by contracting officials or citations to written requirements
or policy statements. See Agency Memorandum of Law at 3-4. During the
hearing, we requested that the agency explain the basis for its position
that APCO 25 compliance would achieve "interoperability." The agency
program manager responded as follows:
The push for mass notification in facilities came in 2004 when it was
mandated all new designs and buildings under current design were
required to have mass notification. With that stated, USAREUR went
forward with soliciting for a EUCOMM-wide mass notification contract.
They could not get it to go forward and they turned it over to the Corps
of Engineers in December 2004 for further action and then the research
and everything ensued based on their requirements. The push was for
USAREUR to get homogenous systems USAREUR-wide. Before then, individual
facilities, even military components on those facilities were installing
their own brand or type or favorite systems and many of them were not
adherent to the UFC but we also know that the systems we are about to
install or want to install will not be compatible with every system on
all these facilities. It is future upgradable to when those systems are
replaced that they will communicate with . . . each facilit[y's] central
control station.
Tr. at 36:12-37:9.
During the hearing, we noted that the record to date had not addressed or
supported the Corps's claim that its client, the USAREUR, had requested
interoperability as a requirement for the MNS procurement or that the UFC
requires the compatibility described by the agency. We requested that the
Corps supplement the record in its post-hearing comments with
documentation of any policies or guidance that supported the agency's
position. Tr. at 37:10-38:4. In its response, the agency cited the
USAREUR's initial MNS SOW that was provided to the agency when the Corps
assumed responsibility for procuring the USAREUR's MNS needs. Decl. of
Agency Engineer at 2. The USAREUR SOW provision cited by the agency,
however, merely states that the MNS must "support expansion, be easily
expandable, and modular." SOW for USAREUR MNS (Dec. 2, 2003), at 44. This
SOW requirement does not clearly relate to the type of interoperability
cited by the agency as its rationale for APCO 25 compliance, i.e.,
ensuring compatibility with other systems and avoiding use of proprietary
technology.
The agency has also not identified any requirements or policy statements
that showed that APCO 25 had been adopted or will be adopted in the future
for MNS requirements so as to provide for interoperability in the manner
argued by the agency. [4] Conversely, the agency has not demonstrated that
use of non-APCO 25 standards for MNSes binds the agency to proprietary
technology in a manner that would preclude the interoperability described
by the agency. On this record, we believe that the agency's rationale
regarding interoperability does not reasonably support the inclusion of
the APCO 25 standard in the solicitation.
(c) Land Mobile Radios
The agency finally argues that because APCO 25 is a standard for land
mobile radios (LMRs), requiring the entire MNS to comply with that
standard will allow for potential benefits to be realized from the use of
LMRs as part of an MNS. Supplemental Memorandum of Law at 3. In this
regard, the agency suggests that, in the future, use of LMRs could allow
individuals to trigger MNS alerts remotely, as opposed to relying on a
central command station to issue an alert. Id. The agency's argument
regarding LMRs reverses somewhat the assumptions of its previous two
rationales, namely, that the APCO 25 standard is a general requirement for
an MNS. Here, by contrast, the agency's argument presupposes a need for an
LMR that complies with APCO 25, and then asserts that the entire MNS,
i.e., the wireless transmission equipment which relays alert messages
throughout the system, must comply with APCO 25 in order to accommodate
the LMRs.
The RFP, however, does not require an APCO 25 compliant LMR. During the
hearing, the agency program manager acknowledged that the RFP does not
require LMRs that comply with APCO 25, but rather requires only two "field
radios" requested by the client: "Our solicitation doesn't require the use
of [APCO 25 compliant LMRs] but we do have the offeror providing two field
radios under our solicitation which is applicable to APCO 25 standards."
Tr. at 18:2-5.
The agency further acknowledged that the future capability for remote
triggering of alarms through the use of LMRs was not specifically
requested by its client, the USAREUR, and is not required by the RFP. In
fact, the agency does not know how the field radios will be used as part
of the MNS; instead, individual base commands will determine such use:
GAO: . . . [W]hat would the present use of those two mobile radios be in
the MNS?
AGENCY PROGRAM MANAGER: We don't have the specific answer to that other
than these radios are to be turned over to the -- who is it? No, it's
the installations communication officer. And the use of these others is
per their discretion.
GAO: . . . [Y]ou don't have a specific use for these mobile radios
anticipated?
AGENCY PROGRAM MANAGER: Negative. These systems are going to be turned
over to the installation communications officers per installation. They
are the ones responsible for the mass notification and emergency
notification systems at each installation. Our task was to provide the
base mass notification systems with the equipment that they requested
and what they do with it and how they implement it is purely up to their
coordination and SOPs.
Tr. 21:8-22:5
On this record, given that the RFP did not require the field radios to be
APCO 25 compliant LMRs, and that the agency does not know how the
requested field radios will be used by installations that receive an MNS
under the contract, we believe that the agency's rationale for requiring
an APCO 25 compliant MNS lacks a reasonable basis.[5]
In sum, we agree with the protester that all three of the agency's
rationales fail to establish that the APCO 25 standard is reasonably
necessary to meet its needs for an MNS, and we sustain the protest because
the requirement is unduly restrictive of competition.
(2) 10-Kilometer Range
The protester next contends that the RFP requirement for a 10-kilometer
range for the required radio transmitting and receiving station is unduly
restrictive of competition because it excludes an MNS that could achieve
the required coverage with multiple stations, each of which may have a
range of less than 10 kilometers. The RFP requirements for radio
transmission ranges are as follows:
Basis station consisting of transmitting and receiving station for a
function radius of at least 10 km, consisting of antenna and supply unit
with all required switch and control elements, transmitting units such
as a transmitter, receiver, etc., UPS and power supply should be
furnished, installed and put into operation.
RFP, Specifications for Mass Notification System, at 30.
The protester argues that the MNS transmitting and receiving station range
requirement should be stated in terms of coverage for the individual
installations at which an MNS will be provided. The protester contends
that the agency has not demonstrated why an overlapping system of smaller
transmitting and receiving stations could not achieve the same
functionality as a single station with a
10-kilometer range. MadahCom argues, for example, that the station used in
its own MNS provides a 5-kilometer range, but that multiple stations with
overlapping ranges can be configured to achieve whatever coverage is
required for an MNS at each installation. Tr. at 104:22-105:7.
The agency first argued that a 10-kilometer range "allows future
integration of other sites or buildings into the base-wide MNS," and
"keeps the system flexible and allows future integration of other
buildings." Supplemental Agency Memorandum of Law
at 5. The protester responded that its proposed MNS could achieve such
coverage, if the single-station 10-kilometer range were abandoned in favor
of a more general requirement to provide coverage for the installation.
During the hearing, the agency argued that the protester's suggestion that
system of multiple, overlapping stations could provide the same benefits
as a single station with a 10-kilometer range was not a feasible solution,
due to technical and regulatory barriers. The agency was unable, however,
to fully articulate its rationale for its position during the hearing in
response to questions from our Office. See Tr.
at 100:1-108:8. We requested that the agency clarify its position in its
post-hearing comments. See Tr. at 109:20-110:20. In its comments, however,
the agency did not address its argument that technical difficulties would
result from overlapping signal ranges, but instead the agency engineer
provided a new justification for the
10-kilometer range that pertained to the use of the field radios:[6]
[I]f there are to be field radios that can connect to the network, a
large radius gives them a great benefit. The larger radius allows the
field radios to have a connection to the system from a larger area,
including off-base. If an emergency occurs and someone in charge such as
the provost marshall is not on base at the time, that person can still
utilize the MNS directly from where he is off-base. I had to choose a
distance for this, and ten kilometers is a good range. The greater the
range beyond ten kilometers, the greater the cost to the Government, so
I needed to balance utility with cost. Ten kilometers seemed a very cost
effective range that would leave all bidders on equal footing.
Decl. of Agency Engineer at 2.
The agency engineer's statement therefore explains that the 10-kilometer
range was selected as a compromise between a larger and smaller potential
range. We agree with the protester that the agency's rationale does not
reasonably explain why other technical solutions that could also achieve a
10-kilometer range, or could otherwise provide coverage for the actual
size of an installation, fail to meet the agency's needs. In this regard,
the agency has not demonstrated that alternatives, such as those raised by
the protester, could not meet the agency's needs.
On this record, we believe that the agency has not demonstrated that a
single transmission and receiving station with a 10-kilometer range is
necessary to meet the agency's needs, and sustain the protest on this
ground.
(3) Corrective Action Regarding Other Issues
In addition to the two requirements discussed above, the protester also
challenged three other solicitation provisions as unduly restrictive of
competition or ambiguous: restrictions on the frequency ranges allowed for
radio transmissions, requirements to provide optical radios and a wireless
local area network (WLAN), and a requirement for "remote amplifiers."
During the hearing, the agency stated that it would take corrective action
to address these three issues, and the agency issued a proposed amendment
to the solicitation in its comments on the hearing. Based on the agency's
statement that it would take corrective action with regard to these three
issues, we consider them to have been rendered academic. Since it is not
our practice to consider academic questions, the protest is dismissed with
regard to these three issues. Dyna-Air Eng'g Corp., B-278037,
Nov. 7, 1997, 97-2 CPD para. 132.
Although we consider the merits of these issues academic, the protester
has also requested that we recommend that it be reimbursed its protest
costs regarding the issues. As a general rule, we recommend reimbursement
of a protester's costs incurred with respect to all issues pursued, not
merely those upon which it prevails. Honeywell Tech. Solutions,
Inc.-Costs, B-296860.3, Dec. 27, 2005, 2005 CPD para. 226
at 3-4. In appropriate cases we have limited the recommended reimbursement
of protest costs where a part of the costs is allocable to an issue on
which the protester did not prevail and which is so clearly severable as
to essentially constitute a separate protest. Id. Here, although the
agency agreed to take corrective action, it does not concede that any of
the provisions were unduly restrictive of competition or ambiguous and
thus argues, in effect, that we should treat these issues as severable for
purposes of determining whether the protester should be reimbursed its
protest costs.
We need not determine whether these three issues are severable from the
issues as to which we sustain the protest, discussed above, because we
believe that the protester's challenges to the three issues here are
clearly meritorious and would each have provided an independent basis to
sustain the protest, had the agency not taken corrective action. In this
regard, our Bid Protest Regulations provide that, where the contracting
agency decides to take corrective action in response to a protest, we may
recommend that the protester be reimbursed the costs of filing and
pursuing its protest, including reasonable attorneys' fees. 4 C.F.R. sect.
21.8(e) (2006). Our Office will recommend reimbursement only where an
agency unduly delayed its decision to take corrective action in the face
of a clearly meritorious protest, that is, where a reasonable agency
inquiry into the protester's allegations would reveal facts showing the
absence of a defensible legal position. Department of the Army--Recon.,
B-270860.5, July 18, 1996, 96-2 CPD para. 23 at 3. As discussed below, we
believe that the protester's allegations clearly identified flaws or
ambiguities in the solicitation, and the agency failed to take prompt
corrective action.[7]
(a) Frequency range
The protester first argued that the RFP prohibited the use of certain
radio frequencies that MadahCom intends to use in its MNS, namely those in
the 2.4 GHz range. The RFP explained the radio frequencies restrictions as
follows:
2. An infrastructure shall be set up which enables wireless networking
between the central control stations in the Emergency Operations Center
(EOC) of the individual buildings, the outdoor loudspeaker system and
the central control stations (EOC Office, MP stations or Fire
Department). The radio network shall be operated preferably with the
approved radio frequency authorized in the host nation and facility. If
the frequency band is not available for the respected facility another
charge-free frequency shall be used. Only frequencies shall be used that
are released by the respective frequency coordinator and provided
free-of-charge by the national regulatory authority.
3. If in exceptional cases no usable frequency is available, frequencies
in the 2.4 GHz range and in the 5 GHz range may be used, these ranges
are released for general use IAW [in accordance with] international
standards. This would correspond to the wireless LAN standard IAW
802.11.
RFP, Specifications for Mass Notification System, at 14-15.
The protester argues that the plain language of the solicitation must be
interpreted to state that: (1) the radio network shall operate with a
host-nation-approved frequency, (2) if that frequency is not available,
another charge-free frequency shall be used, and (3) if in "exceptional
cases" no usable frequency is available, then a 2.4 or 5 GHz frequency may
be used. Under this interpretation, a 2.5 or 5 GHz frequency may not be
used unless other frequencies are unavailable.
The agency argues that the protester misreads the RFP, and that offerors
are allowed to use the 2.5 or 5 GHz frequencies. The agency also states
that, even if the RFP "was not worded as well as it should have been," the
agency did not intend to limit use of these frequencies to only
"exceptional cases" where other frequencies are not available.
Supplemental Agency Memorandum of Law at 4. During the hearing, the agency
stated that it would revise the solicitation to better reflect the
agency's understanding of the frequency requirements. The agency's
proposed amendment to the RFP clarifies the provision, as follows:
2. An infrastructure shall be set up which enables wireless networking
between the central control stations in the Emergency Operations Center
(EOC) of the individual buildings, the outdoor loudspeaker system and
the central control stations (EOC Office, MP stations or Fire
Department). The radio network shall be operated with an approved radio
frequency authorized in the host nation and city. If the frequency band
is not available for the respected facility another charge-free
frequency shall be used. Only frequencies shall be used that are
free-of-charge.
3. Frequencies in the 2.4 GHz range and in the 5 GHz range may be used,
these ranges are released for general use IAW international standards.
This would correspond to the wireless LAN standard IAW 802.11.
Agency Hearing Comments, exh. 8, Proposed Amended Specifications for Mass
Notification System (emphasis added to denote changes).
We agree with the protester that the plain language of the RFP was, at
best, ambiguous to the extent that a reasonable offer could conclude that
the RFP did not permit use of the 2.4 GHz range except in "extraordinary
circumstances." See C. Lawrence Constr. Co., Inc., B-290709, Sept. 20,
2002, 2002 CPD para. 165. Additionally, the agency's explanations prior to
the protest and prior to the hearing did not clearly resolve this issue.
On this record, we believe that the protester's challenge to this
requirement was clearly meritorious.
(b) Optical Radio and Wireless Local Area Network
The protester next argued that the RFP did not contain adequate
information regarding two types of equipment, an optical radio and a
wireless local area network (WLAN). See RFP, Specifications for Mass
Notification System, at 33-34. The protester contended that while the RFP
provided detailed requirements for each type of equipment, it failed to
explain how each was intended to be used or incorporated into an MNS
during contract performance.
In response to questions posed by MadahCom prior to the protest, the
agency generally restated the definition for an optical radio and WLAN,
but did not explain how they were to be used in an MNS. See RFP amend. 1,
at 5-6. In its report on the protest, the agency argued that the
requirements were clearly stated in the RFP and responses to questions in
Amendment 1 to the RFP. Memorandum of Law at 6-7. In its supplemental
report on the protest, however, the agency for the first time clarified
that "W-LAN, optical radio . . . are not specifically listed as necessary
items.
. . . They do not need to be used; the contractor is to decide what items
are needed at each location." Supplemental Agency Memorandum of Law at 5.
During the hearing, the agency affirmed that the optical radio and WLAN
were optional elements that could be proposed by offerors. Tr. at
111:7-112:3.
The agency's proposed amendment to the RFP clarifies the requirements
regarding the optical radio and WLAN, as follows: "When required by the
contractor's scope and in accordance with MNS requirements listed in
previous sections, the specifications for specific items in this section
will be complied with." Agency Hearing Comments, exh. 8, Proposed Amended
Specifications for Mass Notification System. Thus, the requirements now
clearly state that offerors must provide an optical radio or WLAN that
complies with the specifications only in the event that the offeror's
proposed MNS relies on such equipment.
We agree with the protester that the RFP was unclear prior to the agency's
corrective action as to whether offerors were required to propose these
two types of equipment. For example, the description of the WLAN stated
that "[t]he system shall be set up as [a] point-to-point and
point-to-multipoint system." RFP, Specifications for Mass Notification
System, at 32. The responses by the agency in Amendment 1 to the RFP were
similarly unclear in that they referred to the RFP requirements but did
not also explain the agency's subsequent position that the two types of
equipment were not required, but rather were optional approaches. We
therefore agree with the protester that a reasonable offeror could
conclude that the RFP did not clearly explain how these types of equipment
would be used under the requirements. See C. Lawrence Constr., supra.
Additionally, the agency's explanations prior to the hearing did not
clearly resolve this issue. On this record, we believe that the
protester's challenge to these requirements was clearly meritorious.
(c) Remote Amplifiers
The protester finally argued that the solicitation's requirement that
offerors provide "remote amplifiers" for speakers that broadcast MNS
messages was unduly restrictive of competition, and not justified as
compared to other types of equipment, such as internal amplifiers, which
MadahCom uses in its MNS. Protest at 23. The RFP stated that offerors were
required to "provide remote amplifiers, as required, for the MNS." RFP,
Specifications for Mass Notification System, at 9. MadahCom submitted the
following questions to the agency following the issuance of the revised
RFP on March 30, 2006, which the agency addressed in amendment 1 to the
RFP on April 25, 2006:
Question: What is the purpose of the "Remote Amplifiers?"
Answer: See Specifications bullet 3 of Section 1.9 for the purpose of
Remote Amplifiers.
Question: Would a system be acceptable if it can provide the necessary
coverage throughout the covered areas and do so with intelligible sound
but without needing "Remote Amplifiers."
Answer: No. A remote amplifier is requested.
RFP amend. 1, at 4.
In its agency report, the Corps stated that the RFP reasonably explained
that offerors must propose "an amplifier that must operate away from the
main unit." Memorandum of Law at 8. During the hearing, however, the
agency engineer responsible for drafting the MNS specifications clarified
that the term "remote" had been used as the result of a mistranslation
from German to English, and that the intended term was a "backup"
amplifier. See Tr. at 84:22-85:22. In its proposed amendment to the
solicitation, the agency deletes the requirement for "remote" amplifiers,
and clarifies that offerors are required to provide independent amplifiers
that are "redundant." Agency's Hearing Comments, exh. 8, Proposed Amended
Specifications for Mass Notification System. We thus believe that the
protester's challenge to this requirement was clearly meritorious.
In sum, because the clarification of these three issues was first made
during the hearing, after the filing of the protest, the production of the
agency report and supplemental agency report, two rounds of comments by
the protester, and discussion of the merits of the issues during the
hearing, we believe that the agency did not take prompt corrective action.
We conclude that the challenges raised to these three solicitation
provisions were clearly meritorious and we recommend that the protester be
reimbursed its reasonable protest costs for all three of the issues
discussed above.
RECOMMENDATION
We recommend that the agency amend the solicitation to delete the APCO 25
compliance requirements and the 10-kilometer range requirement. We further
recommend that the agency reimburse the protester the reasonable costs of
pursuing its protest regarding the APCO 25 and 10-kilometer range issues,
and the three areas for which the agency has taken corrective action
discussed above. The protester's certified claim for costs, detailing the
time expended and the costs incurred on this issue, must be submitted to
the agency within 60 days of receiving this decision.
4 C.F.R. sect. 21.8(f)(1).
The protest is sustained.
Gary L. Kepplinger
General Counsel
------------------------
[1] The agency contends that it should be afforded additional deference
here in our review of the manner in which it has solicited its needs,
noting our decisions that have recognized that an agency may "define
solicitation requirements to achieve not just reasonable results, but the
highest level of reliability and effectiveness." Caswell Int'l Corp.,
B-278103, Dec. 29, 1997, 98-1 CPD para. 6 at 5. As discussed in the
decision, however, the agency here has failed to provide any reasonable
basis for its restrictive requirements, and did not demonstrate that the
APCO 25 or 10-kilometer range requirements related to actual requirements,
much less requirements pertaining to heightened levels of reliability and
effectiveness.
[2] All of the agency engineer's testimony herein has been translated from
German. A translator participated in the hearing for the purpose of
translating questions and responses for the engineer.
[3] The protester notes that several proposed revisions to UFC 4-021-01
delete any reference to APCO 25. Protester's Comments at 8-9. These
versions, however, have not received final approval from DoD and thus only
the version discussed above, dated December 2002, is current. See
Supplemental Agency Memorandum of Law at 2-3. As relevant here, DoD has
not issued a revision to this document that adopts
APCO 25 as a required or recommended standard.
[4] The agency also cites a February 2002 Army memorandum that states that
Army LMRs are anticipated to achieve greater interoperability with other
systems when the radios support the APCO 25 standard. Decl. of Agency
Engineer, exh. 1, Army Plan for Narrowband Systems Operating in the Land
Mobile Radio (LMR) Service, at 1. This memorandum, however, does not
address MNS requirements and, as discussed below, the agency has not
demonstrated that APCO 25 compliant LMRs are required for an MNS.
[5] Additionally, the agency acknowledged during the hearing that a
non-APCO 25 compliant radio could allow authorized users to remotely
trigger MNS alerts.
Tr. 62:25-64:4. That is, there is nothing in the APCO 25 standard that
makes it uniquely suitable for remote triggering of alerts, nor is there
any barrier to a non-APCO 25 compliant radios doing the same.
[6] The agency engineer also noted in her declaration that the
10-kilometer range was included "for several reasons, some of which are no
longer relevant." Decl. of Agency Engineer at 1.
[7] The protester also argues that it should be reimbursed its costs
associated with its February 17, 2006 protest. MadahCom advised our Office
on March 14, 2006 that it was withdrawing that protest based on an
agreement with the agency regarding corrective action. The agency
subsequently issued an amendment to the solicitation on March 30, 2006. We
do not believe that this time frame represents an undue delay in
implementing corrective action that warrants the reimbursement of protest
costs. Additionally, the current protest does not clearly relate back to
issues raised in the February 17 protest. With regard to the current
protest of the APCO 25 standard, the prior protest challenged the
Motorola-based specifications and trunking requirements. The protester now
contends that the agency's deletion of the Motorola and trunking
specifications, while retaining the APCO 25 requirement, resulted in
incomplete and non-meaningful corrective action because APCO 25 is
synonymous with the other two specifications. The protester, however, did
not specifically challenge the APCO 25 requirement in its February 17
protest, nor did it argue that the Motorola-or-equal and trunking
requirements were synonymous with the APCO 25 standard. Under these
circumstances, we do not recommend that the protester be reimbursed the
costs of its February 17 protest.