TITLE: Trawick Contractors, Inc., B-291237, November 20, 2002
BNUMBER: B-291237
DATE: November 20, 2002
**********************************************************************
Trawick Contractors, Inc., B-291237, November 20, 2002
DOCUMENT FOR PUBLIC RELEASE
The decision issued on the date below was subject to a GAO Protective
Order. This redacted version has been approved for public release.
Decision
Matter of: Trawick Contractors, Inc.
File: B-291237
Date: November 20, 2002
John T. Flynn, Esq., Smith, Currie & Hancock LLP, for the protester.
Catherine L. Horan, Esq. and Damon Martin, Esq., Naval Facilities
Engineering Command, for the agency.
Sharon L. Larkin, Esq., and James A. Spangenberg, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest that agency improperly evaluated technical qualifications of key
personnel is denied where protester failed to correct deficiencies,
despite discussions, and the agency's conclusions were reasonable and in
accord with the solicitation's stated evaluation criteria.
DECISION
Trawick Contractors, Inc. protests the award of a contract to TJC
Engineering, Inc. under request for proposals (RFP) N62467-01-R-0372,
issued by the Naval Facilities Engineering Command, Southern Division, for
the renovation of military family housing at the Naval Air Station in
Meridian, Mississippi. Trawick challenges the reasonableness of the
Navy's evaluation of the qualifications of two proposed key construction
personnel.
We deny the protest.
The RFP provided for the award of a fixed-price contract for the second
phase of a renovation and construction project for 118 military housing
units.[1] Award was to be made on a *best value* basis, considering four
technical factors--past performance, small business subcontracting plan,
technical qualifications, and technical solutions--and price.[2]
Competition was restricted to selected offerors who submitted proposals
for the first phase of construction.
With respect to the technical qualifications factor (the only factor at
issue here), the RFP stated that the ratings would be the same as from the
first phase evaluation *unless conditions change.* Offerors were required
to submit the names and technical qualifications of all key design
personnel and lead construction personnel, as well as provide any changes
to their first phase submissions. RFP S: 00200 P: 2.3 (Factor
C--Technical Qualifications).
After proposals were submitted, the Navy held two rounds of discussions
and twice sought proposal revisions. In both instances, the Navy informed
Trawick of its concerns over Trawick's proposed superintendent and quality
control manager. Trawick twice revised its proposal. The Navy evaluated
the proposal submissions and gave Trawick a marginal rating for the
technical qualifications factor and an overall marginal rating for
Trawick's proposal. Trawick contends that the Navy unreasonably evaluated
the qualifications of its proposed superintendent and quality control
manager.[3]
In reviewing protests of allegedly improper evaluations, we will not
substitute our judgment for that of the contracting agency. DAVSAM Int'l,
Inc., B-228429.5, Mar. 11, 1988, 88-1 CPD P: 252 at 3. We will, however,
review a technical evaluation to ensure that it is reasonable and
consistent with the evaluation criteria and with procurement statutes and
regulations. Telos Field Eng'g, B‑251384, Mar. 26, 1993, 93‑1
CPD P: 271 at 4. A protester's disagreement with the agency's judgment is
not sufficient to establish that an agency acted unreasonably. Id. In
this instance, we find that the Navy's evaluation was reasonable.
As is clear from the record, Trawick was given a number of opportunities
to address the Navy's concerns. During the first round of discussions,
the Navy asked Trawick how it intended to approach staffing, since its
proposed superintendent and quality control manager were already
designated to work the first phase of construction, which would not be
completed before the second phase began, and these *persons cannot work on
both projects at the same time.* The Navy also informed Trawick that it
was a *requirement* for the individuals filling these positions to be
*dedicated to only* this second phase. Agency Report (AR), Tabs 10 and
11, First Round Discussions with Trawick.
In response, Trawick revised its proposal, providing resumes for a new
superintendent and quality control manager. The Navy's technical
evaluation board (TEB) reviewed these new resumes and expressed concerns
over these individuals' qualifications. AR, Tab 15, TEB Report (June 20,
2002), at 11.
The Navy held a second round of discussions, explained its concerns about
the qualifications of Trawick's newly proposed superintendent and quality
control manager, and provided Trawick with another opportunity to revise
its proposal. Specifically, Trawick was told that: (1) its proposed
superintendent and quality control manager were not as qualified as those
performing the first phase of construction; (2) the superintendent's
experience was for projects that were *smaller [and] less complex,* and
his resume did not include *lead, asbestos or HAZMAT experience;* and (3)
the quality control manager's qualifications *do not meet the minimum
requirements of [the] RFP.* AR, Tab 20, Second Round Discussions with
Trawick. In response, Trawick revised the two resumes with some details
and reiterated its belief that this proposed superintendent and quality
control manager were qualified. [4] AR, Tab 21, Trawick's Response to
Second Round Discussions.
After reviewing Trawick's second revised proposal, the Navy determined
that the superintendent's resume still did not *demonstrate the experience
to manage a project of this size, scope and complexity,* and that the
quality control manager's resume still *did not meet the minimum
qualifications set forth in the RFP.* Consequently, the Navy gave
Trawick's proposal a marginal rating for the technical qualifications
factor and an overall marginal rating for its proposal.[5] AR, Tab 23,
TEB Report (July 17, 2002), at 11, 16.
Trawick contends that the Navy's evaluation of the superintendent's and
quality control manager's qualifications was unreasonable.
With respect to its superintendent, Trawick concedes that this individual
has less experience on large projects than the individual holding the
position for the first phase of construction. In fact, the resume of the
proposed second phase superintendent demonstrates experience only with
projects ranging in value from $200,000 to $500,000, which is far less
than the approximately $8 million value of this project.
Nonetheless, Trawick contends that its second phase superintendent need
not have experience on larger or more complex projects because of how the
work is sequenced to be performed. As Trawick argues, the RFP provides
that construction would occur on a rolling basis until the 118 housing
units are constructed. The successful offeror would initially be given 12
units to renovate; as each unit was completed and accepted by the Navy,
another unit would take its place so that the contractor could maintain
the construction of 12 units at any one time. See RFP amend. 009 at 3.
According to Trawick, the experience of its superintendent should thus be
measured against the *true scope* of the work, which is the construction
of 12 units, as opposed to the total scope of work, which is the
construction of 118 units. We disagree.
Section 00202 of the RFP, setting forth the evaluation factors for award,
clearly explained that the *General Project Requirements* involved the
*design and complete revitalization* of up to 118 units. This work
involved the demolition, reconstruction, and improvement of both the
exterior and interior of these units, and included extensive work to all
of the major building systems. RFP S: 00202 P: 1.3. As acknowledged by
the protester, paragraph 1.3 provides the work requirements against which
the superintendent's qualifications were to be measured. The reference to
12‑unit sequencing is discussed as a *work restriction* in amendment
009. It seems apparent from the RFP that the project scope involved
extensive renovations to an entire military housing complex and that the
12‑unit increments were a matter of scheduling and not scope. We
thus find that the Navy could reasonably determine that the
superintendent's experience was deficient, consistent with the RFP's
requirements.[6]
With respect to its quality control manager, Trawick argues that this
individual satisfies the requirements of the RFP because he has 15 years
experience as a construction company owner, prior experience as Trawick's
lead carpenter and/or superintendent, and has recently completed a quality
control course administered by the Army Corps of Engineers. However, as
the Navy reasonably determined, these qualifications do not meet the
minimum requirements of the RFP. Section 01450, paragraph 1.5.1.2, of the
RFP specifies that the quality control manager must possess:
a minimum of 10 years experience as a superintendent, inspector, [quality
control] [m]anager, project manager, or construction manager on similar
size and type construction contracts which included the major trades that
are part of this Contract. The individual must be familiar with the
requirements [in an Army Corps of Engineers safety manual], and have
experience in the areas of hazard identification and safety compliance.
The submitted resume does not establish compliance with the 10‑year
requirement in the specified positions of paragraph 1.5.1.2, and does not
reflect experience in hazard identification[7] or safety compliance. In
this resume, four relevant projects are listed, three of which are as a
*lead carpenter* (which is not a specified position), and one is as a
superintendent. No dates are included to establish the length of time in
any of the positions. The fact that the proposed individual has 15 years
experience in home building and has owned his own construction company
does not per se satisfy the RFP's quality control requirements because
there is no indication that, as a business owner, this individual
performed in any of the required roles or acquired the necessary
experience with hazard identification or safety compliance. The Navy's
conclusion that the resume did not satisfy the requirements of the RFP is
thus reasonable, particularly since Trawick was provided an opportunity to
correct this deficiency.[8]
In sum, Trawick's arguments objecting to the Navy's evaluation of the
proposed resumes reflect only Trawick's disagreement with the agency's
judgment, which does not render the Navy's evaluation under the technical
qualifications factor unreasonable. Telos Field Eng'g, supra.
The protest is denied.
Anthony H. Gamboa
General Counsel
------------------------
[1] The first phase of construction, which involved the renovation and
construction of another 120 housing units, is currently being performed by
Trawick under a separate contract.
[2] The four technical evaluation factors were of equal importance.
Combined, these technical factors were equal in significance to price.
Offers were evaluated using adjectival ratings of excellent, acceptable,
marginal, or unacceptable.
[3] In its protest, Trawick also argued that its overall technical rating
was incorrect because the Navy failed to properly average the ratings for
all of the technical evaluation factors. The agency responded in depth to
this allegation. We do not address this issue because Trawick failed to
address it in its comments, and we consider the issue to be abandoned.
Analex Space Sys., Inc.; PAI Corp., B-259024, B‑259024.2, Feb. 21,
1995, 95-1 CPD P: 106 at 8.
[4] Trawick alternatively proposed to utilize the first phase
superintendent and quality control manager and provide the agency with a
credit. Trawick similarly proposed this approach during the first round
of discussions, which the Navy rejected because it found that individuals
dedicated solely to the second phase were required.
[5] In contrast, TJC (the awardee) received an overall excellent rating
for its proposal. Although TJC's proposal was $163,461 higher than
Trawick's, the Navy determined that TJC provided the best value to the
government based upon its superior technical qualities. AR, Tab 15,
Source Selection Board Report, at 3-4.
[6] Trawick also argues that the only requirement for the superintendent
is that the individual speak English. This position is not supported by
the RFP.
[7] The resume contains one reference to *removal of hazardous material*
performed during a recent job as lead carpenter, but no further
explanation of whether this work also involved hazard identification, as
well as removal, as specified by the RFP.
[8] Trawick contends that the Navy should have been more specific during
discussions as to precisely why it believed the quality control manager's
resume did not satisfy Section 01450 of the RFP. To the extent that
Trawick argues that discussions were inadequate, this allegation, raised
for the first time in Trawick's comments, is untimely. 4 C.F.R. S:
21.2(2) (2002). In any event, we believe that under the circumstances,
the Navy provided sufficient information to provide Trawick with a fair
opportunity to address the agency's concerns.