TITLE: Johnson Controls World Services, Inc., B-288636; B-288636.2, November 23, 2001
BNUMBER: B-288636; B-288636.2
DATE: November 23, 2001
**********************************************************************
Decision
Matter of: Johnson Controls World Services, Inc.
File: B-288636; B-288636.2
Date: November 23, 2001
Stuart B. Nibley, Esq., Joseph J. Dyer, Esq., and Robert F. Pezzimenti,
Esq., Seyfarth Shaw, for the protester.
Raymond M. Saunders, Esq., Maj. Howard Roth, and Capt. Ryan M. Zipf,
Department of the Army, for the agency.
Aldo A. Benejam, Esq., and Christine S. Melody, Esq., Office of the General
Counsel, GAO, participated in the preparation of the decision.
DIGEST
1. Protest challenging a cost comparison conducted pursuant to Office of
Management and Budget Circular No. A-76 and alleging that the supporting
management study failed to directly compare all of the positions identified
in the agency's "most efficient organization" with the labor force at the
start of the study is denied, since there is no legal requirement for such a
detailed, "position-by-position" comparison.
2. Protest challenging agency decision to retain in-house logistics and
public works functions as a result of a cost comparison conducted pursuant
to Office of Management and Budget Circular No. A-76 and alleging that
agency improperly failed to include costs for all of the personnel required
to meet the requirements of the performance work statement (PWS), is denied,
where the record provides no basis to question the reasonableness of the
agency's finding that the government's "most efficient organization" had
identified and costed all positions necessary to meet PWS requirements.
DECISION
Johnson Controls World Services, Inc. (JCWSI) protests the decision of the
Department of the Army to retain logistics and public works functions at
Fort Jackson, South Carolina in-house, rather than to contract for these
services under request for proposals (RFP) No. DABT60-99-R-0015. The Army
decided to retain the services in-house based on the results of a cost
comparison conducted pursuant to Office of Management and Budget Circular
No. A-76, which compared JCWSI's proposal to perform the work against the
government's in-house management plan. JCWSI challenges various aspects of
the agency's administrative appeals board (AAB) decision. Although the AAB
agreed with JCWSI on some of the appeal issues and directed that the
in-house estimate be adjusted, the new cost comparison did not change the
agency's initial determination to retain the services in-house. JCWSI
primarily argues that the Army's in-house management plan for a "most
efficient organization" (MEO) failed to reasonably explain reductions in
staffing, and that the Army's in-house estimate does not include costs for
all of the personnel in the MEO.
We deny the protest.
I. BACKGROUND
In 1997, the U.S. Army Training and Doctrine Command (TRADOC) awarded a
contract to Management Analysis, Inc. (MAI) to conduct a study of public
works and logistics functions at 12 TRADOC installations, including Fort
Jackson. For each installation, MAI was to develop a performance work
statement (PWS), document the results of its study, provide a quality
assurance surveillance plan, and include an independent government cost
estimate based on a proposed MEO. (The protester does not challenge the
multiple roles played by MAI.) As written, the PWS categorized the work to
be performed under several maintenance and service areas, including:
buildings and structures, utility systems operation, heating, ventilation,
and air conditioning systems operation, dining facility equipment, grounds,
surfaced area, range, materiel, transportation services, and base supply.
Agency Report (AR) exh. J, PWS, at 1-2.
The document prepared for Fort Jackson consisted of five chapters. AR exh.
M. The first four chapters were MAI products and included an introduction
explaining the overall purpose of the study, scope, and methodology (ch. 1);
a general description of Fort Jackson's operations as of the start of the
study (ch. 2); MAI's analysis and recommendations (ch. 3); and MAI's
proposed MEO (ch. 4).
Chapter 5 was prepared by Fort Jackson staff, hereinafter referred to as the
MEO team. After MAI completed its work, the MEO team analyzed the
recommendations and required functions. During this process, the MEO team
met with all of the section supervisors and key staff to discuss staffing
levels and possibilities for reductions or required additions, and asked
supervisors to suggest improvements and reorganizations to increase
efficiency. AR exh. T, Program Manager Statement, Sept. 19, 2001, at 1. In
chapter 5, the MEO team commented on MAI's recommendations and reorganized
MAI's proposed MEO by functional areas to reflect changes that had taken
place at Fort Jackson, or were proposed to take place, since MAI completed
its work. AR exh. M at 5-1. That section explained that "[t]he workload
analysis performed by MAI is the basis for the additional changes taken by
[the MEO team] and includes those actions necessary to execute [fiscal year
2000] reductions while meeting the requirements of the PWS." Id. The changes
that the MEO team made to MAI's recommendations included consolidating some
of the work and eliminating positions. The final in-house management plan
for an MEO prepared by the MEO team formed the basis for developing the
estimate for the cost comparison at issue here.
TRADOC issued the RFP on February 22, 2000, as part of a public/private cost
comparison under Circular A-76. [1] The RFP contained historical workload
data for each functional area in the PWS. RFP sect. C.1.1.4.3. The RFP
contemplated the award (if the private sector won the cost comparison) of a
cost-plus-award-fee contract for a base year, with up to four 1-year
options, and phase-in/phase-out transition periods. RFP sect.sect. B, L.9.
Section M of the RFP listed staffing and key personnel, past performance/
experience, technical capability, management approach, and subcontracting as
evaluation factors. RFP sect. M.3. Rather than numerically rating or ranking the
private-sector proposals, the RFP stated that individual members of a source
selection evaluation board (SSEB) would assign adjectival ratings to each
proposal as either "technically acceptable," "marginal," or "unacceptable"
under each evaluation factor. The SSEB would then assign an overall
consensus rating for each proposal. The source selection authority (SSA)
would then select the technically acceptable private-sector offer with the
lowest cost for the cost comparison with the MEO. Id.
The SSEB evaluated technical proposals the agency received from the
private-sector offerors, and based on those initial evaluations, the Army
conducted discussions only with JCWSI and one other offeror. The SSEB
reevaluated those two firms' revised proposals, which resulted in JCWSI's
being the lowest-cost, technically acceptable one. Consequently, the SSA
selected JCWSI's proposal for the cost comparison.
The U.S. Army Audit Agency (USAAA) was the independent reviewer (that is,
the IRO) of the government's in-house plan. See Circular A-76, ch. 3, para. I;
Army Regulation (AR) 5-20 sect. IV.4-14(a) (1997). In that capacity, the USAAA
reviewed the management plan and supporting documentation, including the PWS
and the cost comparison form. AR exh. V, USAAA Memorandum, Sept. 5, 2001. As
part of its review, the USAAA interviewed Fort Jackson representatives,
evaluated the methodology and rationale for efficiencies, and reviewed the
management plan for consistency with the PWS. Based on its review, the USAAA
certified that the management plan reasonably established the government's
ability to perform the PWS's requirements with the staffing levels
identified in the MEO. Id. at 2.
By letter dated November 17, 2000, TRADOC notified JCWSI that its proposal
had been selected for comparison with the in-house cost estimate. By
separate letter on that same date, TRADOC notified JCWSI that based on the
results of the cost comparison, the agency had tentatively decided to retain
the services in-house. In that letter, the Army also notified JCWSI that it
would make available for public review the cost comparison form and
supporting documents, including the management study. Id.
After reviewing the cost comparison and supporting documents, in a December
27 letter, JCWSI appealed the Army's tentative decision to retain the
services in-house. AR exh. N. In addition to challenging several cost
issues, JCWSI generally complained that the materials TRADOC made available
for public review were confusing, and that the in-house cost estimate failed
to include all of the staff required by the MEO. After JCWSI filed that
appeal, the Army informed JCWSI that the decision to retain the services
in-house was not based on the materials it had provided for public review,
but on revisions made to those materials. The Army subsequently provided
JCWSI with corrected documents and extended the time for public review and
for filing an appeal.
On February 28, 2001, JCWSI filed a new appeal of the cost comparison based
on the revised management plan and accompanying documents. In its appeal,
JCWSI raised some new issues and many of the same issues it had raised in
its previous appeal. In its decision, the AAB agreed with some aspects of
JCWSI's appeal, and directed the contracting officer to revise the MEO,
correct errors in the cost comparison form, and recalculate the in-house
cost estimate accordingly. [2] The USAAA audited and certified the revised
cost estimate. See AR 5-20 sect. III, para. 4-13, and sect. IV, para. 4-14; RSH part I,
ch. 3, sect.sect. E.3, I.
The following table shows the result of the cost comparison based on the
revised MEO:
MEO JCWSI
Proposed Costs $63,653,324 $54,325,039
Contract Admin. 0 2,607,516
One-time Conversion 0 1,976,135
Costs
Federal Income Tax 0 <271,626>
Total Adjusted Costs 63,653,324 58,637,064
Conversion Differential 0 5,631,518
Final Adjusted Costs $63,653,324 $64,268,582
AR exh. P, Cost Comparison Form (July 16, 2001), at 1.
Although this cost comparison shows a savings of $5,016,260 in favor of
contracting, these savings did not exceed the minimum conversion
differential of $5,631,518. [3] Thus, the new cost comparison did not change
the agency's initial decision to retain the work in-house. AR exh. Q, AAB
Response to JCWSI's Appeal, Aug. 3, 2001, at 1-2. The agency subsequently
provided JCWSI with a copy of the AAB's decision and the revised cost
comparison form. This protest followed.
II. PROTESTER'S CONTENTIONS
We segregate the protester's numerous allegations into two distinct, but
related categories for purposes of this decision. One line of argument
relates to JCWSI's general challenge to the agency's methodology for
preparing the MEO and the alleged failure of the MEO to justify staffing
reductions from the level of Fort Jackson's current operations. With respect
to this challenge, the protester contends that the agency's allegedly flawed
methodology caused a series of errors, resulting in unexplained staffing
reductions in the MEO.
The second group of contentions in the protest concerns the in-house cost
estimate's alleged failure to include costs for all of the required
personnel. In this regard, JCWSI argues that costs for specific functions
required by the PWS are not included in the in-house cost estimate. The
protester also argues that the MEO overestimates savings from proposed
operation improvements, and that the MEO failed to satisfy various
requirements in the PWS. [4]
III. ANALYSIS
Where, as here, an agency has conducted a cost comparison under Circular
A-76, thus using the procurement system to determine whether to contract out
or to perform work in-house, our Office will consider a protest alleging
that the agency has not complied with the applicable procedures in its
selection process or has conducted an evaluation that is inconsistent with
the solicitation criteria or is otherwise unreasonable. See Trajen, Inc.,
B-284310, B-284310.2, Mar. 28, 2000, 2000 CPD para. 61 at 3. To succeed in its
protest, the protester must demonstrate not only that the agency failed to
follow established procedures, but also that its failure could have
materially affected the outcome of the cost comparison. Aberdeen Technical
Servs., B-283727.2, Feb. 22, 2000, 2000 CPD para. 46 at 5. We have reviewed the
voluminous record developed in this matter, and we conducted a hearing to
obtain testimony concerning specific issues. Based on our review of the
entire record, including the parties' extensive submissions, we find no
basis to question the reasonableness of the agency's decision to retain the
services in-house.
A. Justification for Staffing Reductions
The protester focuses its protest on whether the MEO provided an adequate
rationale for staffing reductions from the level of Fort Jackson's
operations at the beginning of the study. The protester asserts that MAI
described Fort Jackson's operations as consisting of 379 authorized
positions at the beginning of the study. Based on that figure, MAI then
recommended various staffing reductions and organizational changes which,
according to JCWSI's calculations, resulted in MAI recommending a total of
301.5 full-time equivalents (FTE). JCWSI maintains, however, that the final
MEO does not provide any justification for eliminating a significant number
of positions from the initial 379 FTEs. The protester contends that the
agency's methodology, which it characterizes as a "top-down" approach (i.e.,
performed by taking reductions from the initial 379 FTEs), was defective and
caused several material errors.
In our view, the protester's focus is fundamentally flawed. Our Office's
review, in considering a private-sector offeror's challenge to the conduct
of a public/private competition, addresses whether the agency reasonably
found that the in-house plan satisfies the PWS requirements and whether the
public/private competition was conducted on a level playing field. See,
e.g., BAE Sys., B-287189, B-287189.2, May 14, 2001, 2001 CPD para. 86 at 19;
Aberdeen Technical Servs., supra, at 8. The protester here would have us
find, instead, that, in order to pass muster in a bid protest, an agency
conducting a cost comparison pursuant to Circular A-76 is required to
specifically identify each position under study prior to taking into account
efficiencies, and to compare that labor force to the MEO in order to support
staff reductions. We do not believe that the protester's approach is legally
required.
It is true that the RSH requires that the in-house management plan for an
MEO explain and document the assumptions that an agency relies upon in
developing the MEO and in-house cost estimate, including "[a]n overall
comparison of the current organization with the MEO and a review of any
special initiatives or assumptions, including equipment or productivity
changes." RSH, part I, ch. 3, sect. E.4. Rather than the detailed
position-by-position comparison the protester maintains is required,
however, the RSH thus provides that the MEO is to include "an overall
comparison" with the current operation, and that the MEO is to "reflect the
scope of the PWS." Id. The RSH further provides that the management plan
"should identify the organizational structures, staffing, and operating
procedures, equipment, transition and inspection plans necessary to ensure
that the in-house activity is performed in an efficient and cost effective
manner." Id. sect. E.1. The RSH thus simply requires that in forming the MEO,
agencies determine what positions will be needed to perform the work
reflected in the PWS. As the protester itself states, "This is required to
ensure that the public-private competition will be conducted on an
'apples-to-apples' basis, since it is the PWS from which the contractor must
work in preparing its proposal." Protester's Comments, Oct. 5, 2001 at
21-22. The focus of our Office's review is generally to determine whether
there is a reasonable basis for the IRO's certification that the in-house
plan for an MEO is capable of performing the PWS requirements with the level
of staffing proposed, not whether there is a precise "cross-walk" from the
staffing levels existing prior to the study or whether the reductions from
those staffing levels were justified (even though we recognize that these
latter questions may be important for the agency internally and may in some
circumstances be relevant to the question of the reasonableness of the IRO's
certification).
While our review focuses on the reasonableness of the agency's certification
of the MEO's compliance with the PWS requirements, we recognize that the
agency and the AAB did, in fact, devote considerable effort to tracking
positions and intervening changes in Fort Jackson's operations. Thus, the
Army argues that the protester fails to take into account modifications the
MEO team made to MAI's recommendations [5] as reflected in chapter 5 of the
management plan, as well as significant staff reductions as a result of
organizational changes that occurred at Fort Jackson before MAI completed
its work, but unrelated to the study. [6] The most notable of these changes
included consolidation of the Directorate of Logistics and Directorate of
Public Works to form the current Department of Logistics and Engineering
(DLE), and combining the logistics supply and functions into one division.
It is undisputed that this was a major reorganization affecting several
areas under study. According to TRADOC, the new consolidated organization,
DLE, provided improvements in the area of customer service and led to
identifying other areas that could be restructured to achieve increased
efficiencies, resulting in the final MEO.
In addition, during consideration of JCWSI's appeal, the AAB requested that
the MEO team provide additional information in order to better understand
and respond to JCWSI's appeal issues. AR exh. O, AAB Memo., Apr. 13, 2001,
at 1-2. In response, the MEO team provided detailed explanations for MAI's
recommended MEO and for the changes that resulted in the final MEO. The MEO
team described the history of various functions and provided reasons for the
final proposed MEO. Also, in response to the AAB's request for a "visible
audit" from the initial number of FTEs referenced in the management plan to
the final MEO, the MEO team provided spreadsheets attempting to track all of
the changes from the initial number of 379 FTEs MAI described, to the 250.98
FTEs identified by the MEO team. [7] AR exh. N1.3b App. A.
In this protest, JCWSI devotes considerable effort to pointing out numerous
discrepancies, calculation errors, and omissions between the initial 379
FTEs MAI described and the 250.98 FTEs the MEO team identified in the final
MEO. [8] In doing so, the protester identifies several documents which it
believes existed prior to April 13, 2001, when the AAB requested the
additional information from the MEO team, and compares them to other
documents JCWSI states were created in response to the AAB's request for
additional information. The protester then points to a series of apparent
inconsistencies across and within those two sets of documents, to argue that
TRADOC has not provided an auditable trail tracking staff reductions from
the initial 379 authorized positions to the 250.98 FTEs in the final MEO. In
a supplemental protest, JCWSI refines its argument in this regard,
identifying approximately 36 FTEs which it claims were improperly eliminated
without explanation from the initial 379 FTEs. According to JCWSI, these
inconsistencies had a domino effect throughout the process, resulting in a
"heap of spaghetti, all winding back on itself, inconsistent and
irreconcilably twisted, which cannot withstand scrutiny." Protester's
Comments, Oct. 5, 2001, at 39. JCWSI maintains that these uncertainties show
not only that the Army's "top-down" approach to developing the MEO was
flawed from the beginning, but that the agency did not follow the procedures
for conducting a cost comparison prescribed by Circular A-76 and the RSH.
In order to better understand the record, our Office conducted a hearing at
which we heard testimony from the program manager (PM), who had a pivotal
role as a member of the MEO team. That testimony, which we found fully
credible, was useful to our Office in explaining the factual background of
the MEO plan. At the hearing, the PM consistently testified that the MEO
staffing was based primarily on historical workload data and the PWS
requirements. Hearing Transcript (Tr.) at 76-79, 168-70, and 179-80. This
approach is confirmed by the Fort Jackson Garrison Commander. In a letter
responding to the AAB's request for additional information, the Commander
explained that "in developing the Fort Jackson MEO, MAI and local personnel
tried to determine the minimal staffing necessary to accomplish the mission.
Great care was taken to identify the staffing necessary to provide what was
required by the PWS, not what has been provided in the past." AR exh. N1,
Garrison Commander Memo. for AAB, Apr. 23, 2001, para. 2. The record is thus
clear that while the management study does reference 379 FTEs at the
beginning of MAI's work, that figure is largely irrelevant, as the record
shows that the MEO team ultimately staffed the in-house plan based on the
historical workload data and the PWS requirements. [9]
The key question for our Office here is the reasonableness of the
certification by the USAAA, in its capacity as the IRO, that the MEO
satisfied the PWS requirements. With the exception of the specific,
relatively limited challenges that we find nonmeritorious for the reasons
explained below, the protester has provided us no basis to question the
reasonableness of the USAAA's certification. Moreover, the record shows that
the in-house cost estimate included the costs for all of the FTEs included
in the MEO. Indeed, JCWSI concedes this point, stating that "it appears that
the Army's in-house cost estimate does price out the number of FTEs included
in the Army's MEO (i.e., 250.98 FTEs)," and "the Army's in-house cost
estimate does appear to price the FTEs that are reflected in the Army's
final MEO." Protester's Comments, Oct. 5, 2001 at 45-46, and 72.
In our view, the management plan clearly explains and documents the
assumptions MAI and the MEO team made in developing the in-house plan for
the final MEO. In doing so, both MAI and the MEO team provided an overall
comparison of Fort Jackson's organization with the proposed MEO, and
explained initiatives and assumptions made in reaching their
recommendations. JCWSI recognizes that the RSH's reference to the "current
organization" is intended merely as a "realism check and balance to ensure
that the agency does not construct an MEO that is wholly unreasonable" or so
vastly different from the existing organizational structure as to call into
question the MEO's ability to perform the work required by the PWS.
Protester's Comments, Oct. 5, 2001, at 22. Here, MAI recognized that Fort
Jackson was in the process of a major reorganization and took that into
account in making its recommendations, and the MEO team adjusted those
recommendations to develop the final MEO. In our view, the management plan
provides a sufficient description of Fort Jackson's operations to reasonably
permit a "realism check" of the MEO. Contrary to JCWSI's assertions, neither
the Circular nor the RSH requires more.
In addition to the lack of a legal requirement for the detailed comparison
JCWSI seeks, we believe that JCWSI's approach would unjustifiably require
agencies to focus on tracking intervening staffing level changes, rather
than focusing on building an MEO that satisfies the PWS requirements.
Changes occurring during the course of a study (such as the reorganization
that occurred here) can affect the size of the labor force, for reasons
unrelated to study recommendations. Given the length of time generally
required to complete an A-76 study, such changes may be inevitable. See DOD
Competitive Sourcing: Results of Recent Competitions. (GAO/ NSIAD-99-44,
Feb. 23, 1999) (summarizing the length of time various DOD agencies required
to complete a study). Here, for example, the study was announced in 1997,
MAI actually began its work with respect to Fort Jackson in 1999, and the
management study was completed in March 2000. Under JCWSI's theory, TRADOC,
and any agency conducting a study pursuant to Circular A-76, would be
expected to stop the study each time a significant event occurs in order to
determine whether it has the most current staffing data available. That
effort would distract from what we view as the central concern, which is
constructing an in-house plan adequate to meet the PWS requirements.
The protester also argues that TRADOC ignored JCWSI's superior performance
as evidenced by the fact that it proposed more total hours than the MEO.
This argument is without merit. The RFP clearly announced that the agency
would select the lowest-priced, technically acceptable proposal for the cost
comparison. Thus, TRADOC was not required to assess or rank proposals based
on "technical superiority," nor was it required to go through the "leveling"
process as must be done where the solicitation calls for a comparative
technical evaluation. See, e.g., BAE Sys., supra. In addition, the protester
maintains that the fact that it offered substantially more hours supports
its assertion that the MEO did not explain the overall reductions in
staffing. In our view, this assertion, without more, does not call into
question the reasonableness of the in-house plan or of the IRO's
certification that the in-house plan is adequate to meet the PWS
requirements.
B. Specific Errors Alleged in the Cost Comparison
We now turn to the protester's allegations concerning specific errors in the
in-house cost estimate. In this regard, the protester argues that the agency
overestimates cost savings from eliminating unproductive travel. JCWSI also
argues that functions required by the PWS are either not included in the
in-house cost estimate or were eliminated altogether from the MEO. These
functions are related to material management, moving and shipping, clothing
initial issue point, electrical equipment repair, and the hazardous material
manager. We address each of these contentions separately below.
1. Unproductive Travel
The MEO team decided to eliminate unproductive travel to and from job sites
for lunch and one of two authorized daily breaks. The MEO team calculated
the savings associated with eliminating the unproductive travel time as .75
hour (45 minutes) for each work day (222 days), per employee, and it assumed
that 75 percent of the 56 employees (42 individuals) would be affected by
enforcing this policy. Based on these assumptions, the MEO team calculated
that 6,993 hours (or approximately 4 FTEs) could be eliminated from its
staffing. AR exh. T at 8. [10]
JCWSI argues that the MEO overstates the savings associated with eliminating
the unproductive travel time. Essentially, the protester is contesting the
factual basis of the finding that there is unproductive travel time
associated with the break and lunch, as well as the assumption that the MEO
team will be able to reduce the amount of unproductive time as much as
promised. The protester's objection centers around the agency's assumption
that 75 percent of all affected employees always travel to and from their
job sites for breaks and lunch. JCWSI points out that MAI's observation was
quite different: it found that employees stopped working before the end of
the day in order to return to their shop to complete paperwork. [11] As
such, the protester asserts that there is no evidence in the record to
support the notion that all employees were traveling to and from their job
sites for breaks and lunch, or that 75 percent of all affected employees
were doing so all of the time--i.e., on all of the 222 work days of the
year. The protester argues that, even assuming that the record contains some
evidence of unproductive travel, the MEO unreasonably extrapolates observed
behavior from a relatively small number of employees to 56 employees
potentially affected by the policy.
With respect to this issue, the PM testified that based on his personal
experience and observations during his 20-year tenure at Fort Jackson, all
of the service personnel who leave the shop to perform service work return
to the shop for their breaks and for lunch. Tr. at 79-81. We view this as a
factual matter as to which the PM was a credible witness. As a result of
MAI's observations, and his own personal experience, the PM further
testified that the MEO team determined that it could improve productivity by
eliminating the unproductive travel time by requiring that employees take
their morning breaks and lunch on the job site. Id. at 79. The PM further
explained that the percentage (75) of employees that could be affected by
this policy was a conservative estimate, because virtually all employees
return to the shop for breaks and lunch. Id. at 80. He also explained that
using these conservative estimates provided sufficient flexibility to ensure
that the in-house plan could perform all of the work required by the PWS
with its proposed staffing levels.
JCWSI points out that on cross-examination on this issue, the PM testified
that rather than 75 percent of employees currently abiding by the policy, in
practice, it is conceivable that, at this point, only 50 percent of
employees actually have changed their behavior to conform to the policy. Tr.
at 121-22. The PM went on to emphasize, however, that transition to the MEO
is not yet complete. Id. at 122.
It is not our Office's role to determine the appropriate staffing levels for
either the in-house team or the private-sector offeror. Instead, our role is
to determine whether there was a reasonable basis for the agency's
determinations in this regard. Here, the protester has questioned whether
there was a factual basis for one specific aspect of the in-house plan, and
we heard testimony that, in our view, provides an adequate factual basis
responding to the protester's concern. Whether the agency has already
implemented this aspect of the in-house plan, or whether it fully implements
that approach once the MEO is implemented, is a matter outside the scope of
our bid protest jurisdiction, akin to a contract administration matter that
we do not review. See 4 C.F.R. sect. 21.5(a) (2001).
2. Clothing Initial Issue Point (CIIP)
The CIIP provides clothing to new soldiers and includes a variety of related
functions such as fitting, altering uniforms, and warehouse operations.
JCWSI contends that the MEO team improperly eliminated two positions within
this section based on an erroneous assumption. In this connection, the
record shows that before recommending any staff reductions, MAI assumed that
the CIIP section consisted of 43 FTEs, in addition to some 91,000
intermittent hours. The agency explains, however, that MAI misinterpreted
the staffing data the MEO team provided, and incorrectly concluded that the
intermittent hours were in addition to the 43 FTEs identified within the
CIIP. Based on the data the MEO team provided, MAI then recommended
eliminating three FTEs related to CIIP operations--one fabric worker
position within the alterations unit; and one motor vehicle operator
position and one materiel handler position, both within the warehouse unit.
The MEO team adopted MAI's recommendation, but only with respect to
eliminating one fabric worker position and one materiel handler position in
the final MEO.
The protester objects that the Army cannot, on the one hand, maintain that
MAI based its recommendations on an erroneous interpretation of the staffing
data, and also adopt MAI's recommendation with respect to eliminating two
FTEs. In the protester's view, since MAI's recommendations were based on its
erroneous interpretation of the total staff required to perform the CIIP
functions, the MEO is understaffed by the two FTEs the MEO team eliminated.
During the hearing, the PM testified that upon review of MAI's recommended
MEO, he realized that MAI had incorrectly included 91,000 hours for
intermittent work and he corrected that error. Tr. at 94, 136-37, 140. The
PM further explained that the MEO team staffed the CIIP section by analyzing
the actual reported hours of each individual in that section, including
whether each individual performing CIIP functions was a permanent or
intermittent employee. As a result of that analysis, the PM testified that
he was then able to develop the staffing required for the CIIP function. Tr.
at 94. Thus, the hearing testimony clarified the factual background and
established, in our view, that there is no basis for the protester's
allegation regarding the impact of MAI's misunderstanding of the staffing
hours. [12]
3. Moving and Shipping
The PWS called for various tasks to be performed in connection with
transporting materials, including loading and unloading of vehicles,
packing, wrapping, and labeling items, preparing documentation, moving
vehicles to and from storage areas, and performing and documenting safety
checks, to name a few. AR exh. J, PWS para. 5.10.3.12. The protester maintains
that the MEO did not identify any staff positions to perform these tasks.
JCSWI contends that this failure is particularly significant because during
discussions with the firm, TRADOC criticized JCWSI's proposed hours to
perform the moving and shipping tasks described in the PWS. Based on the
agency's estimate that historically the Army required 14,112 hours to
perform these tasks, JCWSI states that it included [DELETED] FTEs in its
proposal to perform these functions, and that these FTEs should be added
into the MEO. [13]
In response to the AAB's request for additional information on this issue,
the MEO team explained that, consistent with the PWS, the responsibilities
for performing the various tasks related to moving and shipping are
scattered throughout the MEO. AR exh. N1.I-C-3 at 98. In its response, the
MEO team explained that 14.5 FTEs included within different areas of the MEO
would be responsible for performing moving and shipping tasks. The AAB
concurred, finding that the MEO provided 14.5 FTEs dedicated to performing
the moving and shipping tasks, which the board considered a "full
complement" of positions to accomplish the required tasks and denied this
issue. AR exh. Q, AAB Decision, I-C-3, at 1.
The agency explains that the PWS requirements related to moving and shipping
are actually distributed among more than the 14.5 FTEs previously identified
to the AAB. In this connection, the agency has provided a table describing
specific responsibilities, locations, and the number of FTEs included in the
MEO for each position responsible for some aspect of moving and shipping.
AR exh. T at 12-15. Our review of the record further shows that the job
descriptions for all of the positions described show that, in fact, their
responsibilities include work described in the PWS under the moving and
shipping area. We conclude that the agency is reasonable in contending that,
when all of these positions are considered, the MEO proposed 45.5 FTEs whose
duty descriptions include various aspects of moving and shipping tasks.
Especially in light of the protester's proposing [DELETED] FTEs to perform
these functions, we have no basis to disagree with the AAB's conclusion that
the MEO provided sufficient staff to meet the PWS requirements in this area.
[14]
4. Electrical Equipment Repair
JCWSI maintains the MEO fails to provide adequate staffing to perform the
electrical equipment repair functions of the PWS. In this connection, the
protester states that TRADOC had criticized JCWSI's proposed hours for this
function, and indicated that the function required a minimum of 24,509
hours, or 13.8 FTEs. The protester maintains, however, that the MEO does not
provide sufficient FTEs for this function.
TRADOC states that the MEO included a total of 17 FTEs for the electrical
equipment repair work, or the equivalent of 30,192 hours, and the agency
included those costs in the in-house cost estimate. AR exh. P, Line 1, Base
Personnel Cost Worksheet. While the protester does not challenge the
agency's statement in this regard, JCSWI notes that TRADOC states that it
included the equivalent of 2 FTEs to perform some radio work by contract,
but argues that these contract costs are not included in the Army's in-house
estimate. [15]
At the hearing, the PM testified that the MEO team determined that it would
be more cost effective to have some of the radio repair work previously done
in-house, performed by contract. Tr. at 98-99. The PM further explained that
the MEO estimated these contract costs at approximately $36,000 per year.
Tr. 100; AR exh. L, Original Cost Comparison Form, Line 3, Other
Specifically Attributable Costs, Summary Worksheet. The PM further testified
that these costs are captured in the initial cost estimate of in-house
performance, specifically under "Other Specifically Attributable Costs." AR
exh. L, Original Cost Comparison Form, Line 3 (Nov. 17, 2000).
The protester complains, however, that while the final Cost Comparison Form
(i.e., the form completed after the AAB's decision on JCWSI's appeal)
includes $112,696 for the first year, and higher amounts in subsequent
years, for a total of $580,322 under the "Other Specifically Attributable
Costs" category, the record does not contain any backup documentation
explaining how these costs were calculated.
The protester's contention is factually unsupported by the record. While the
protester is technically correct in its assertion regarding the final cost
comparison form, it is not accurate to characterize the record as lacking
any explanation as to "how those costs were calculated, or what accounts for
those costs," as JCWSI contends. Post-Hearing Comments, Oct. 29, 2001, at
21. As already explained, the record contains the MEO team's contemporaneous
calculations of how it arrived at the estimates for performing the radio
repair work by contract. Those estimates were based on the anticipated
number of weekly repairs and average costs for each occurrence, for
approximately $36,000 per year. AR exh. L, Original Cost Comparison Form,
Radio Repair Contract. The record shows that the MEO team estimated one
contract for radio repair work at $25,000 per year, while a second contract
for similar work was estimated at approximately $9,375 per year. AR exh. L,
Radio Repair Contract Worksheet. The protester offers no basis to question
the reasonableness of these amounts. The total amount included in that
initial cost comparison form for the "Other Specifically Attributable
Costs," including the estimated contract electrical repair work, is more
than $569,000. Id. The record further shows that following implementation of
the AAB's decision, the estimated amount included for these costs increased
by approximately $10,000, to more than $580,000. The AAB did not question
the agency's original estimates for performing the radio repair work by
contract; the increase can thus be presumed to be attributable to items
unrelated to the radio repair work, and there is no reason to believe that
TRADOC's original supporting calculations for performing the radio repair
work by contract did not support the estimates for this work included in the
revised cost comparison. There is thus no factual support for the
protester's assertion that the record does not contain backup documentation
explaining how these costs were calculated.
5. Hazardous Material Manager
The PWS required the contractor to comply with all applicable environmental,
fire, safety, and transportation regulations controlling the proper handling
and storage of hazardous materials (HM). AR exh. J, PWS para. 1.4.5.1. In order
to carry out the functions associated with this requirement, the PWS called
for an HM Manager. According to the protester, the MEO does not provide this
required position. JCWSI also argues that the HM manager identified in the
MEO is not costed as a manager-level position, and should be costed at a
higher level.
TRADOC states that to meet the PWS requirement at issue, the MEO included a
HM Program Coordinator at a General Schedule (GS)-9 level. The MEO reflects
a cost of $52,055.94 for this position. See AR exh. P, Base Year Personnel
Costs, Line 26 (HAZ MAT PGM COORD). Thus, the protester's assertion that the
MEO does not include costs for the HM Manager position is not supported by
the record.
The agency further explains that prior to Fort Jackson's reorganization this
position was staffed at the GS-7 level. TRADOC states that the predecessor
position performed the tasks described in the PWS, and continues to perform
those same tasks even after the reorganization at Fort Jackson. The agency
further explains that notwithstanding the title, the HM "Manager" does not
involve managing or supervising personnel, as JCWSI maintains. Based on the
agency's explanation, and our independent review of the record, the
protester's insistence that the HM Manager position was required to be
compensated at a higher pay level, is not supportable.
IV. SUPPLEMENTAL ISSUE
In its comments on the agency report, JCWSI asserts that TRADOC rejected
MAI's findings and recommendations "when they felt the need to find more
FTEs to eliminate." Protester's Comments, Oct. 5, 2001, at 32. In support of
this assertion, JCWSI provided an attachment, entitled "Table of Challenged
Positions In DOL," where it lists various positions the protester claims
TRADOC improperly reclassified as GIN functions. Id. exh. 1. The protester
also attached this table to a supplemental protest submission. A review of
that table shows that JCWSI primarily relies on TE-2001, a technical exhibit
included in the management study, as a basis for its argument concerning the
allegedly reclassified positions.
With respect to challenges to cost comparisons under Circular A-76
procedures, we have adopted a policy, for the sake of comity and efficiency,
of requiring protesters to exhaust the available administrative appeal
process. Thus, we have held that where, as here, there is a relatively
speedy appeal process for the review of an agency's cost comparison
decision, we will not consider objections to the cost comparison that were
not appealed to the agency. See Professional Servs. Unified, Inc.,
B-257360.2, July 21, 1994, 94-2 CPD para. 39 at 3; Direct Delivery Sys.,
B-198361, May 16, 1980, 80-1 CPD para. 343 at 2. Nevertheless, there is no
statutory or regulatory requirement that an offeror exhaust available
agency-level remedies before protesting to our Office, and we retain the
discretion to waive the policy requiring the exhaustion of the Circular A-76
appeals process where good cause is shown. BAE Sys., supra, at 17. Here, it
is clear that the protester had sufficient information to have raised this
basis for challenging the cost comparison after it reviewed the management
study, which TRADOC made available to JCWSI during the public review period
following the cost comparison, and there is nothing in the record that would
warrant waiving our policy requiring exhaustion of the appeals process.
The protest is denied.
Anthony H. Gamboa
General Counsel
Notes
1. The procedures for determining whether the government should perform an
activity in-house or by a contractor are set forth in Circular A-76 and the
Revised Supplemental Handbook (RSH) to it, which have been made expressly
applicable to the Department of Defense (DOD) and its military departments.
See 32 C.F.R. sect. 169a.15(d) (2001). The process set out in the Circular and
the RSH broadly encompasses the following steps in conducting the
public/private competition. First, after the PWS has been drafted, the
agency ensures, through certification by an independent reviewing official
(IRO), that the government's in-house plan satisfies the requirements of the
PWS. See RSH, part I, ch. 3, para. I. Second, there is a competition among
private-sector offerors, which is conducted much as any competed federal
procurement. Third, if that competition is done on the basis of a
comparative technical evaluation (that is, if a cost/technical tradeoff is
contemplated), the government's in-house plan is compared with the winning
private-sector offer to assess whether or not they are based on a comparable
level of performance and performance quality--and if not, to make all
changes necessary to make the level of the in-house plan comparable to that
of the private-sector proposal. Id. para. H.3.d.e. Finally, once the playing
field is thus leveled, there is a cost comparison between the private-sector
offer and the in-house plan. Id. para.para. H, J.
2. The RSH provides that the AAB should generally issue its decision within
30 days of the filing of a cost appeal. RSH part II, ch. 3, sect. K.8; see also
AR 5-20, sect. IV.4-16. Here, the AAB issued its decision on August 3, 2001.
While the AAB's delay in issuing the decision did not prevent JCWSI from
pursuing this protest, we note that this delay--more than 7 months after
JCWSI filed its initial appeal, and more than 5 months after JCWSI filed its
second appeal--was well beyond the period contemplated by the RSH and the
Army's own guidance.
3. To ensure that the government does not convert between sectors for only
marginal estimated savings, the RSH provides that services should not be
converted from in-house performance to contract (or vice-versa) unless the
cost savings exceed a minimum conversion differential. RSH, Part II, ch. 4,
sect. A.1. That differential is the lesser of $10 million or 10 percent of the
personnel costs of providing the required services in the sector currently
performing (here, in-house).
4. In its protest, JCWSI also argued that the MEO failed to meet certain PWS
requirements related to cyclic maintenance and processing local
procurements. JCWSI also argued that TRADOC's revised cost comparison failed
to reflect the AAB's decision. The agency responded to the protester's
allegations with respect to each of these points, and JCWSI did not pursue
these issues in its comments. Accordingly, we deem these issues abandoned
and do not discuss them further.
5. While we view the dispute as having little relevance to the outcome of
this protest, we note that the protester and the agency disagree on the
number of FTEs that were in MAI's initial recommended MEO. The agency states
that the 301.5 FTE figure that JCWSI relies on as MAI's recommendation is an
inaccurate figure. TRADOC explains that JCWSI arrived at that number by
starting with 265.5 FTEs recommended by MAI, subtracting (correctly, in the
agency's view) 10.1 FTEs because they are "government-in-nature" positions,
and adding (incorrectly) 46.1 FTEs of intermittent hours for one facility.
The agency explains (as addressed further in the "clothing initial issue
point" discussion below), that the intermittent hours should not be added
(doing so would lead to double counting). The agency states that using
correct calculations would delete the added 46.1 FTEs and thus lead to the
conclusion that MAI recommended an initial MEO consisting of 254.9 FTEs.
(This 254.9 FTE figure seems to have resulted from a small calculation error
(265.5 - 10.1 = 255.4).) We have no basis to question the agency's position
in this regard.
6. The agency states that the net result of the review performed by the MEO
team was a reduction of 3.92 FTEs from the figure recommended by MAI,
yielding a total of 250.98 FTEs (254.9 - 3.92 = 250.98). DLE Crosswalks; AR
exh. T at 1-2. The 250.98 FTE figure was then used as the basis for the
initial cost comparison--i.e., before adjustments were made as a result of
JCWSI's appeal. (In addition to directing that other cost adjustments be
made to the MEO, the AAB directed Fort Jackson to add 5 FTEs to the in-house
cost estimate. AR exh. O, AAB Decision, Aug. 7, 2001. After implementing the
AAB's decision, the MEO staffing thus increased to 255.98 FTEs. AR exh. P,
Personnel Costs Worksheet, Aug. 8, 2000.)
7. The protester argues that the AAB improperly considered the MEO team's
explanations, and complains that JCWSI was excluded from participating in
the appeals process. According to the protester, the fact that the AAB
requested additional information leads to a conclusion the management plan
did not adequately support the cost comparison. We disagree. The extent of,
or limits on, participation by the various sides in the agency appeal
process is not a matter for review by our Office. Moreover, we see nothing
wrong with the AAB requesting further explanations to assist in reaching its
decision, and the fact that the request was made does not compel a
conclusion that the management plan was inadequate to support the cost
comparison.
8. The record shows that the 379 FTE figure was based on staffing data the
MEO team provided to MAI during the course of the study.
9. The protester's contention that the agency used a "top-down" method thus,
in our view, misses the mark, since the initial 379 FTEs referenced in the
management study was nothing more than a snapshot of the labor force MAI
used to describe Fort Jackson's operations at the beginning of its work, and
it did not determine the efficiencies, reorganizations, or staff reductions
proposed.
10. Although there seems to be some inconsistency in the record as to
whether the anticipated savings amount to 1 hour or 45 minutes, the PM's
testimony at the hearing indicated that the MEO team based its calculations
on eliminating 45 minutes of unproductive travel.
11. MAI reported that it had observed that cyclic maintenance employees
returned to the shops a half-hour before the end of the work day to complete
paperwork and handle other administrative tasks. AR exh. M, MS, ch. 3, at
3-10, 3-11. MAI viewed this practice as inefficient, leading MAI to
recommend "to hold employees to the standard 30 minutes break per day and 30
minute lunch per day." AR exh. M, para. 3.3.4, at 3-11. (The MEO team's proposal
regarding travel at the morning break and lunch apparently grew out of this
recommendation.) MAI explained that the result of enforcing existing break
and travel policies "is a considerable increase in the amount of hours
available for productive work." AR exh. M, TE 4001-1.
12. JCWSI also argued in its protest that the MEO team adopted MAI's
recommendation to reduce the number of overtime hours in clothing
alterations from its historical figure of 3,215 hours to zero, without
justification. The record shows that the MEO team did not adopt MAI's
recommendation in this regard, and actually included more than 6,000
overtime hours in the CIIP section to meet surges in demand during peak
periods. AR exh. M, ch. 5 at 5-5. These hours are accounted for in the cost
comparison. AR exh. P; AR exh. L, Base Year Personnel Costs Worksheets. In
its comments, JCWSI essentially concedes that the Army's explanation
resolves this basis of protest. Comments, Oct. 5, 2001, at 77.
13. The RSH requires that regular hours be converted at the rate of 1,776
hours/FTE. RSH, Part II, ch. 2, para. B.5. Applying that formula, JCWSI divided
[DELETED] regular hours by 1,776, to yield [DELETED] FTEs.
14. Although the agency concedes that the MEO team failed to specify which
positions will perform the moving and shipping tasks, the job descriptions
provided reasonably establish which positions are responsible for performing
these requirements. This situation is thus distinguishable from one where an
agency claims that the MEO includes sufficient FTEs to absorb work called
for by the PWS, but neither the management plan nor the in-house cost
estimate supports that assumption. See, e.g., Trajen, Inc., supra, at 4.
15. Although the PM's statement in response to JCWSI's contentions regarding
this issue indicates that the MEO team "also included the equivalent of
2 FTEs to accomplish other electrical repair (radio) electrical on a
contract basis," PM Statement, at 17, the record is clear that the MEO was
staffed, and costed, 17 FTEs to perform the electrical work in-house, and
the additional costs of radio repair work were reflected as "Other
Specifically Attributable Costs."