TITLE:  Rockwell Electronic Commerce Corporation, B-286201.6, August 30, 2001
BNUMBER:  B-286201.6
DATE:  August 30, 2001
**********************************************************************
Rockwell Electronic Commerce Corporation, B-286201.6, August 30, 2001

Decision

Matter of: Rockwell Electronic Commerce Corporation

File: B-286201.6

Date: August 30, 2001

Gerard F. Doyle, Esq., and Ron R. Hutchinson, Esq., Doyle & Bachman, for the
protester.

Kevin P. Mullen, Esq., Carl L. Vacketta, Esq., and Holly Emrick Svetz, Esq.,
Piper Marbury Rudnick & Wolfe, for MCI WorldCom Communications, Inc., the
intervenor.

Seth Binstock, Esq., and Jonathan Cantor, Esq., Social Security
Administration, for the agency.

Henry J. Gorczycki, Esq., and James A. Spangenberg, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.

DIGEST

Protest of agency's corrective action in response to a General Accounting
Office decision sustaining earlier protest is sustained where the agency
reopened discussions and requested proposal revisions from only one offeror
in the competitive range, and where the agency's corrective action did not
resolve the improprieties that were the basis for the prior decision.

DECISION

Rockwell Electronic Commerce Corporation protests the Social Security
Administration's (SSA) implementation of our recommendation in Rockwell
Elec. Commerce Corp., B-286201 et al., Dec. 14, 2000, 2001 CPD para. 65, aff'd,
Social Sec. Admin.; MCI WorldCom Communications, Inc.-Recon., B-286201.4,
B-286201.5, Apr. 19, 2001, 2001 CPD para. __. In that decision, we sustained
Rockwell's protest of an award to MCI WorldCom Communications, Inc. under
request for proposals (RFP) No. SSA RFP-00-3929, issued by SSA for
network-based telephone services to handle the agency's toll free call
traffic from the FTS 2001 network, as well as the agency's associated
administrative call traffic.

We sustain the protest.

The RFP contemplated the award of a fixed-price contract for a base period
with 6 option years. Award was to be made on a "best value" basis with price
being the most important evaluation factor.

The RFP requested proposals for the best solution available in the industry
to handle both the toll-free and administrative call traffic. Offerors were
permitted to use the FTS 2001 network in their proposed solutions; in such
cases the agency would pay the cost of using FTS 2001 services under the FTS
2001 contract [1] rather than under the solicited contract. Since those
payments would be a cost to SSA associated with such a proposal regardless
of which contract applied, the RFP stated that the cost of FTS 2001 services
unique to a given proposal would be included in the price evaluation. As
such, offerors were required to specifically identify in their proposals all
unique FTS 2001 services and the associated costs.

Of the [DELETED] proposals submitted, [DELETED] proposed virtual private
networks (VPN) for both toll-free and administrative call traffic, and the
other [DELETED] proposed using FTS 2001 services to varying degrees.
Rockwell was one of the offerors proposing a VPN-based solution, which had
no FTS 2001 costs for handling administrative call traffic. MCI proposed a
solution which would necessarily entail unique FTS 2001 costs for handling
administrative call traffic; however, MCI's proposal did not specifically
identify those unique FTS 2001 costs as was required by the RFP, and SSA did
not consider such costs in the price evaluation as required by the RFP. The
two proposals that relied on VPN-based solutions were higher priced than
MCI's evaluated price. Under the other evaluation factors, Rockwell's
proposal was rated the same as MCI's, and the other VPN proposal was rated
the same as or better than MCI's proposal.

SSA awarded the contract to MCI. Rockwell's protest was filed within 5 days
of receiving a required debriefing, and the agency was required by law to
suspend performance under MCI's contract unless the head of the procuring
activity authorized in writing the performance of the contract
notwithstanding the protest. 31 U.S.C. sect.sect. 3553(d)(3), (d)(4) (1994). SSA
authorized overriding the required suspension of performance, pursuant to 31
U.S.C. sect. 3553(d)(3)(C)(i)(I), based on a determination that performance was
in the best interests of the government. Rockwell Elec. Commerce Corp.,
supra, at 5 n.3.

Among other things, Rockwell protested that the evaluation was unreasonable
and inconsistent with the RFP because SSA did not evaluate all of FTS 2001
costs associated with MCI's proposed solution. In the agency's report and
supplemental report responding to the protest, the agency contended that the
RFP did not require the agency to evaluate unique FTS 2001 costs for
handling administrative call traffic. However, late in the protest process
(at the hearing), the agency began to assert that, even if its evaluation
did not comply with the RFP, the protester was not prejudiced because the
level of administrative call traffic at issue was insignificant, such that
any associated FTS 2001 costs for MCI's proposal would be immaterial.

Our decision sustained Rockwell's protest on the basis that the RFP required
SSA to evaluate the FTS 2001 costs that MCI's proposed solution would incur
for distribution of administrative call traffic, and SSA did not evaluate
these costs. Rockwell Elec. Commerce Corp., supra, at 7-8. Indeed, we
observed that since MCI had failed to provide the information required by
the RFP for the price evaluation, SSA could not evaluate MCI's price. Id. at
7; Social Sec. Admin.; MCI WorldCom Communications, Inc.--Recon., supra, at
2. We determined that Rockwell was prejudiced by this improper evaluation
regardless of whether the level of administrative call traffic in question
and associated costs were significant or insignificant. This was so because
the RFP called for the best solutions available within the industry to deal
with administrative call traffic, but SSA never informed offerors that its
administrative call traffic was insignificant. As indicated, Rockwell stated
that its price was higher than MCI's due to the cost of the portion of its
VPN solution associated with handling the administrative call traffic in
question. Rockwell (and [DELETED]) never had the opportunity to submit a
proposal knowing either that the agency did not intend to evaluate costs of
delivering this administrative call traffic if FTS 2001 services were used,
or that the level of that traffic (and thus the associated cost) were
insignificant. Rockwell Elec. Commerce Corp., supra, at 8-9; Social Sec.
Admin.; MCI WorldCom Communications, Inc.--Recon., supra, at 3-4. We
recommended that SSA reopen the competition, amend the solicitation as may
be appropriate, request and evaluate revised proposals, and make a new award
decision consistent with the terms of the RFP and our decision. Rockwell
Elec. Commerce Corp., supra, at 11. The agency and MCI subsequently
requested reconsideration, which we denied.

Following our decisions, the agency requested proposal revisions from MCI
limited to the identification of its FTS 2001 costs for handling
administrative call traffic that were not previously identified in its
proposal. Agency Report, Tab 1, Request for Revised Proposal. MCI's revised
proposal identified those additional costs as $[DELETED] [2] (a very small
percentage of MCI's total evaluated cost of $[DELETED]). Agency Report, Tab
3, MCI's Revised Proposal; Tab 6, Price Evaluation of Revised Proposal, at
1. The agency did not request or receive proposal revisions from Rockwell or
any other offeror. Agency Report, Tab 8, Source Selection Recommendation for
Award, at 3. The prior technical evaluations remained unchanged, and the
agency again selected MCI's proposal as representing the best value to the
government. Id. at 2.

Following notice of the agency's actions, Rockwell protested to our Office.
Rockwell contends that the agency's actions are not consistent with
applicable laws and regulations or our recommendation. The agency responds
that it did act consistent with our recommendation because it corrected the
problem identified by our decision, i.e., that the agency had not evaluated
FTS 2001 costs consistent with the terms of the RFP. [3] Since Rockwell did
not propose using FTS 2001 services for handling administrative calls, SSA
claims that there was nothing to discuss with Rockwell, and there was no
corresponding portion of Rockwell's proposal that could be revised. SSA
states that limiting discussions and proposal revisions in this manner was
justified to protect the integrity of the procurement system, given that
MCI's proposed price and other information had been disclosed after award.

As a general matter, the details of implementing our recommendations for
corrective action are within the sound discretion and judgment of the
contracting agency. Rel-Tek Sys. & Design, Inc.--Modification of Remedy,
B-280463.7, July 1, 1999, 99-2 CPD para. 1 at 3. Such discretion must be
exercised reasonably and in a fashion that remedies the procurement
impropriety that was the basis for our protest recommendation. The Futures
Group Int'l, B-281274.5 et al., Mar. 10, 2000, 2000 CPD para. 148 at 8; CitiWest
Properties, Inc., B-274689.4, Nov. 26, 1997, 98-1 CPD para. 3 at 6. Here, the
agency did not act reasonably in reopening discussions only with MCI, nor
did the agency's remedy resolve all the improprieties that were the basis
for our decision sustaining the prior protest.

Specifically, if a procuring agency holds discussions with one offeror, it
must hold discussions with all offerors whose proposals are in the
competitive range. Federal Acquisition Regulation (FAR) sect. 15.306(d);
International Resources Group, B-286663, Jan. 31, 2001, 2001 CPD para. 35 at 6.
Similarly, if discussions are reopened with one offeror after receipt of
final revised proposals, they must be reopened with all offerors whose
proposals are in the competitive range, even where the discussions are
corrective action on improper awards. International Resources Group, supra;
The Futures Group Int'l, supra, at 10; Patriot Contract Servs., LLC et al.,
B-278276.11 et al., Sept. 22, 1998, 98-2 CPD para. 77 at 5 n.3. Moreover, where,
as here, revised proposals are proper for remedying a flawed procurement,
requesting proposal revisions after an offeror's price or other information
has been revealed is not improper. [4] RS Info. Sys., Inc., B-287185.2,
B-287185.3, May 16, 2001, 2001 CPD para. 98 at 4; Computing Devices Int'l,
B-258554.3, Oct. 25, 1994, 94-2 CPD para. 162 at 3-4. Since discussions were
reopened with MCI to advise MCI of the defect in its proposal, and MCI was
permitted to revise its proposal, SSA was required to conduct discussions
with all offerors whose proposals had been found in the competitive range
and allow those offerors to submit proposal revisions.

Furthermore, the agency's limitations on reopening of discussions failed to
address all of the improprieties identified by our decision. The initial
protest record prior to the hearing, as well as the general framework for
our decision, was developed around the issue of MCI's proposal not
identifying FTS 2001 costs and the agency's vigorous insistence that it did
not have to evaluate them. This is the only impropriety that the agency has
attempted to remedy following our decisions.

The agency, however, introduced information during and after the hearing
showing that the actual conditions of this procurement are significantly
different than those under which the competition was conducted. That is, the
agency introduced late in the protest process evidence that the level of
administrative call traffic in question was so insignificant that it could
be that proposals using solutions other than FTS 2001 would be, from that
fact alone, undesirable from a cost perspective. Indeed, during the protest,
when this was revealed, Rockwell indicated that it would not have proposed
this solution if the RFP had stated that administrative call traffic was
insignificant (or that FTS 2001 costs would not be considered in the price
evaluation). Since the RFP solicited the best solutions within the industry
for distributing administrative call traffic, the agency's post-award
revelations that it did not contemplate solutions for distributing the
administrative call traffic in question using other than FTS 2001 services,
and that the level of that call traffic was so insignificant as to render
nominal the associated FTS 2001 costs of handling such calls, revealed
another impropriety. At that point it became apparent that the RFP was
misleading, such that the offerors who proposed a VPN solution did not have
a fair opportunity to compete for this award. [5] We clearly identified this
impropriety in our decision sustaining the initial protest and explained it
in greater detail in our decision denying the requests for reconsideration.
Rockwell Elec. Commerce Corp., supra, at 7-9; Social Sec. Admin.; MCI
WorldCom Communications, Inc.--Recon., supra, at 2-5.

The agency's corrective action does nothing to remedy this impropriety. This
impropriety can only be remedied by advising the competitive range offerors
that the agency's administrative call traffic needs are insignificant--a
fact which was not apparent from, and which (as detailed in our prior
decisions) seemed inconsistent with, the RFP--and requesting revised
proposals permitting offerors to consider this information in preparing
their technical and price proposals. [6]

Finally, SSA requests that we find reasonable its actions in limiting
corrective action because MCI has already activated its service solution at
all of SSA's locations and SSA has incurred over $[DELETED] million in
start-up costs under MCI's contract. [7] SSA essentially alleges that no
recompetition can be expected to offset this expenditure for the government.
Agency Report at 28.

The agency overrode the statutorily required stay of performance of this
contract based on a finding that continued performance would be in the best
interests of the government (rather than that urgent and compelling
circumstances that significantly affect interests of the United States
existed.) In such circumstances, the Competition in Contracting Act of 1984
(CICA) requires our Office to make our recommendation on a protest without
regard to any cost or disruption from terminating, recompeting or reawarding
the contract. [8] 31 U.S.C. sect. 3554(b)(2) (Supp. IV 1998); 4 C.F.R. sect. 21.8(c)
(2001). The legislative history for this statute shows that Congress
designed this provision of CICA to ensure that an agency's incurrence of
costs in administering a contract after a stay is overridden on a "best
interests" basis would not limit the range of relief measures that our
Office could recommend after sustaining a protest. Department of the
Navy--Modification of Remedy, supra, at 3. Specifically, the legislative
history states:

Before notifying the Comptroller General that continued performance of a
disputed contract is in the government's best interest, however, the head of
the procuring activity should consider potential costs to the government
from carrying out relief measures as may be recommended by the Comptroller
General if the protest is subsequently sustained.

H.R. Conf. Rep. No. 98-861, at 1436 (1984), reprinted in 1984 U.S.C.C.A.N.
697, 2124.

Here, the start-up costs of MCI's contract in excess of $[DELETED] million
were known to the agency at the time it made the "best interests" override
determination. See Agency Report at 28; Agency Report on Initial Protest,
Tab 115, MCI's Final Proposal, July 31, 2000, Pricing Tables, Table G.
Although we are mindful of the considerable cost to the government resulting
from SSA's action, we cannot, consistent with the requirements of CICA,
consider this cost in making our recommendation.

The protest is sustained.

We recommend that the agency reopen discussions with all offerors in the
competitive range at the time of the initial award decision, amend the RFP
as may be appropriate, [9] for example, instructing offerors as to the
levels of administrative call traffic the agency anticipates, request
revised proposals in a manner that does not restrict offerors from applying
this information in revising their price and technical proposals, reevaluate
revised proposals, make a new source selection decision and, if a proposal
other than MCI's is selected for award, terminate the contract previously
awarded to that firm. In addition, we recommend that Rockwell be reimbursed
the costs of filing and pursuing this protest, including reasonable
attorneys' fees. 4 C.F.R. sect. 21.8(d)(1). The protester should submit its
certified claim for such costs, detailing the time expended and the costs
incurred, directly to the contracting agency within 60 days of receiving
this decision.

Anthony H. Gamboa
General Counsel

Notes

1. SSA selected MCI as its FTS 2001 contractor from the General Services
Administration's available contractors.

2. The agency's price evaluation reduced this amount slightly "to reflect a
50%/50% contract overlap by year consistent with [SSA's] prior evaluation
(initial award)." Agency Report, Tab 6, Price Evaluation of Revised
Proposal, at 1.

3. The agency now concedes that this was an error.

4. In any case, there is no basis for concern that enough of MCI's
information has been disclosed to justify the extraordinary measure of
limiting discussions. For example, much of the information in the record was
subject to a protective order and there is no suggestion that any
information was improperly released outside the protective order.

5. SSA states that if the FTS costs in question are significant, then the
RFP is not misleading and Rockwell had a fair opportunity to compete. Agency
Report at 26. That observation does not support the reasonableness of the
agency's corrective action, since the agency itself has established that the
FTS costs are, in fact, insignificant.

6. The present situation is different from that in Rel-Tek Sys. & Design,
Inc.--Modification of Remedy, supra (cited by the agency in support of its
limitation of the discussions in taking corrective action after disclosure
of prices), where we found a limitation on discussions and proposal
revisions to particular areas of the proposal proper where the particular
procurement impropriety could be corrected with the limited revised
proposals and where the remedial discussions and opportunity to revise
proposals applied to all of the competitive range offerors.

7. We note that the contract at issue is a service contract that is still in
its base period, and there are still 6 option years left to be performed.
Also, Rockwell asserts that MCI's prices were front-loaded and Rockwell's
first year price was substantially less, so that this problem was caused by
MCI and SSA.

8. When an agency overrides the CICA stay based upon a written finding of
urgent and compelling circumstances, CICA permits our Office to consider all
circumstances--including cost and disruption to the government--in
fashioning the appropriate remedy under a sustained protest. See Department
of the Navy--Modification of Remedy, B-274944.4, July 15, 1997, 97-2 CPD
para. 16 at 3 n.2; 31 U.S.C. sect. 3554(b)(1) (1994).

9. In our first decision, we stated the single point of failure requirement
for call representatives that was stated in the RFP did not appear to
represent the agency's actual needs. Testimony indicated that the RFP was
never amended to reflect changes in the agency's requirements and that the
agency evaluators understood that the agency's requirement was actually
greater than that which was stated in the RFP. Although we found that MCI's
proposal was compliant with the RFP, and therefore the agency's
determination that the proposal was technically acceptable was not
unreasonable, we did not find that MCI's proposal met the more restrictive
terms that the evaluators believed represented the agency's actual
requirements. We stated that the agency should review this and other
questioned specifications, and amend the RFP, if appropriate, before it
requests revised proposals. Rockwell Elec. Commerce Corp., supra, at 11 n.8.
The agency incorrectly and unreasonably interpreted our decision as
endorsing the agency's evaluation, and therefore the agency states that it
did not reexamine this (or any other) technical requirement. Agency Report
at 11 n.6. We restate our prior recommendation that the agency review the
RFP requirements to determine whether they fairly state the agency's actual
requirements, and amend the RFP accordingly.