BNUMBER: B-281948
DATE: May 10, 1999
TITLE: K.G., Inc., B-281948, May 10, 1999
**********************************************************************
Matter of:K.G., Inc.
File: B-281948
Date:May 10, 1999
Kevin P. Connelly, Esq., John C. Lavorato, Esq., and Michael D.
Garson, Esq., Seyfarth, Shaw, Fairweather & Geraldson, for the
protester.
Gena E. Cadieux, Esq., and Joseph Lenhard, Esq., Department of Energy,
for the agency.
Robert C. Arsenoff, Esq., and Paul I. Lieberman, Esq., Office of the
General Counsel, GAO, participated in the preparation of the decision.
DIGEST
Protest that awardee's bid should have been rejected as nonresponsive
for alleged failure to comply with a solicitation requirement that
bids for first 2 performance years be priced in accordance with an
applicable wage determination is denied where the bid satisfied the
requirement.
DECISION
K.G., Inc. (KGI) protests the award of a contract to Miracle Services,
Inc. under invitation for bids (IFB) No. DE-FB01-99AD66850, issued by
the Department of Energy (DOE) as a small business set-aside for
certain janitorial and maintenance services to be performed at the
agency's Forrestal Building headquarters in Washington, DC and at an
adjacent child development center. The protester principally alleges
that Miracle's bid should have been rejected as nonresponsive for
failure to comply with an IFB pricing requirement, and that the bid is
unbalanced.
We deny the protest.
The IFB was issued on November 10, 1998, and bids were opened on
December 10. Bidders were required to submit all-inclusive prices for
a base year (year 1) and four 1-year option periods (years 2 through
5). The bid schedule provided that, for each year, the bidder was to
submit separate pricing for: (1) a "DOE Unilateral Option for
Cleaning of Forrestal Cafeteria"; (2) a "DOE Unilateral Option for
Cleaning of the Forrestal Child Development Center," which is adjacent
to the Forrestal Building; and (3) "[a]ll remaining cleaning services
in accordance with the Statement of Work [SOW]." IFB amend. 3, sec. B.5;
IFB sec. B.6. The IFB notified bidders that the contract awarded would
be subject to the Service Contract Act (SCA). IFB sec. B.9(c). A
Collective Bargaining Agreement (CBA) between the Service Employees
International Union and the current contractor was to serve as the SCA
wage determination for the first 2 years of the contract. IFB attach.
3. The IFB further provided that price adjustments would be applied
to subsequent contract years once a new wage determination had been
incorporated into the contract. IFB sec. B.9(c). The CBA established
$13.74 per hour as the minimum labor rate for year 1 and $ 14.62 per
hour as the minimum labor rate for year 2. See CBA art. XVI and sec.
24.2, 25.1 and 26.3(a).
Bid prices were to include "all direct and indirect expenses
associated with the performance of the contract." IFB sec. E.1(i). The
IFB set forth an agency minimum estimate of 325 hours per work day for
SCA personnel to adequately perform the work set forth in the SOW.
Id. Contractors were required to perform approximately 251 days per
year (i.e., weekdays exclusive of 10 regular government holidays).
IFB sec. B.10.3.C.
In addition to providing personnel subject to the SCA wage rates,
bidders were responsible for providing supervisory personnel,
specified supplies, equipment and uniforms, as well as telephone
service for external calls. IFB sec. B.10.5.C, 6.B. The IFB did not
call for bidders to break down the labor costs to separately identify
profit and labor costs, or to specify associated overhead, materials,
administrative and other costs incorporated into their bid prices.[1]
Section E.1(i) of the IFB provided as follows:
This is an all or nothing solicitation, bidders will provide
prices
for all items in Clauses B.5 and Clause B.6. FAILURE TO
PROVIDE ALL PRICES WILL RENDER THE BID
NONRESPONSIVE AND IT WILL BE REJECTED.
Additionally, the bidder should provide total prices
by year and the total cumulative price in Clause B.7
"Summary." The evaluation of price will include all 60
months . . . . The bid prices are to include all direct and
indirect expenses associated with the performance of the
contract.
Bidders will price year one and two in accordance with the
[SOW] and Wage Determination. The Wage Determination is
applicable through January 31, 2001. Years Three, Four and Five will
be bid the same as year two. Afterward and once the new wage
determination is incorporated into the contract, the price(s) for the
remaining years will be adjusted in accordance with clause B.9.
Eleven bids were received. The apparent low bidder was permitted to
withdraw its bid for reasons not pertinent to this protest. The next
two low bidders were the eventual awardee and the protester. Their
bids were as follows:
Miracle KGI
Year 1 $1,630,086.00 $1,594,104.34
Year 2 $1,633,013.88 $1,668,574.17
Year 3 $1,636,050.24 $1,668,574.17
Year 4 $1,639,154.28 $1,668,574.17
Year 5 $1,642,353.36 $1,668,574.17
TOTAL $8,180,657.76 $8,268,401.02
Agency Report at 3. The agency made award to Miracle on January 20,
1999, and KGI filed this protest on January 28.
Stating that the $74,469.83 increase in its own bid price from year 1
to year 2 solely reflected the $0.88 per hour increase in the wage
determination from year 1 to year 2, KGI asserts that the minimal
$2,927.88 increase in Miracle's bid price for the same time frame
shows that Miracle did not price year 1 and year 2 "in accordance with
the [SOW] and Wage Determination," as required by section E.1(i), and
concludes that the agency was required to reject the bid as
nonresponsive.
As a general matter, even where an offeror bases its price on rates
below those specified in a wage determination, that firm is eligible
for award if the offeror does not take exception to the SCA wage
determination requirements. McDonald-Bradley, B-270126, Feb. 8, 1996,
96-1 CPD para. 54 at 2. Here, nothing in its bid indicates that Miracle
took exception to the wage determination requirements. Further, there
is no indication that Miracle somehow failed to price the first 2
years "in accordance with" the SOW and the applicable wage
determination. As indicated above, bidders were required to provide a
minimum of 325 SCA labor hours per day for 251 days per year for a
total of 81,575 SCA labor hours per year; when the specified wage rate
for year 1 ($13.74 per hour) is multiplied by the minimum number of
SCA hours required by the IFB per year, the required yearly SCA wages
add up to $1,120,840.50; using the specified wage rate for year 2, the
amount is
$1,192,626.50. In each case, Miracle's all-inclusive price
substantially exceeds the relevant minimum yearly total. Thus, as the
agency points out, since Miracle's total bid for each year is more
than sufficient to pay the applicable SCA rates for each year, there
is no basis to conclude that Miracle did not bid "in accordance with"
the SOW and the CBA.
Other non-wage rate elements required to be included by the IFB into
the all-inclusive bid prices (e.g., profit, overhead, supervisory
costs, supply and equipment costs, uniform costs and the cost of
telephones for external calls) may have caused the structure of
Miracle's bid for the first 2 years to differ from that of KGI's bid.
However, even if this were not the case, and it appeared that Miracle
had bid below its cost, there is simply no prohibition on such
below-cost bidding. Bollinger Mach. Shop & Shipyard, Inc.,
B-261135.2, Sept. 1, 1995, 96-1 CPD para. 123 at 3. Accordingly, this
aspect of the protest is denied.
Noting that Miracle's bid prices for years 3, 4 and 5 contain
progressive (although minimal) increases through time, KGI further
alleges that Miracle failed to comply with the requirement in section
E.1(i) that "Years Three, Four and Five will be bid the same as year
two." However, the section pertains only to the SCA-derived wages for
which there is a uniform escalation, and does not, as the protester
suggests, prohibit any increases in prices throughout the remainder of
the contract for non-SCA-wage items.
KGI also maintains that Miracle's bid was materially unbalanced. KGI
asserts that Miracle's bid does not become low until year 3 at the
earliest, noting that if the government does not exercise at least two
options, or if the next CBA results in wage reductions, KGI's price
would be low. KGI argues, therefore, that Miracle's bid should have
been rejected as unbalanced since the agency is not reasonably assured
that an award to Miracle will result in the lowest price to the
government.
Federal Acquisition Regulation (FAR) sec. 14.404-2(g) provides that
materially unbalanced bids may be rejected and references FAR sec.
15.404-1(g), which provides that unbalanced pricing arises where the
prices of one or more contract line items are significantly over- or
understated. KGI's unbalancing allegation is entirely premised on the
assertion that Miracle's year 2 prices fail to rise enough to reflect
the CBA wage increase between years 1 and 2; KGI has not provided any
other support for the proposition that Miracle's year 1 prices are
overstated and its year 2 prices are understated. Since we reject,
for the reasons explained above, KGI's argument that Miracle's prices
fail to conform to the required year 2 CBA wage increase, we similarly
find without merit KGI's assertion that Miracle's prices are
understated or overstated. Accordingly, the factual predicate for a
finding of unbalanced pricing does not exist.
The protest is denied.
Comptroller General
of the United States
1. Section E.1(o) of the IFB required the contractor to submit a
certified list of personnel who would be staffing the contract within
5 working days after award. It further provided that all proposed
rates of pay must, at a minimum, conform to the CBA; failure to so
conform would result in the contractor being ineligible for an
adjustment in contract price following the adoption of a new wage
determination after the expiration of the current CBA.