BNUMBER: B-275855
DATE: April 4, 1997
TITLE: Matter of:Telestar Corp.
**********************************************************************
Matter of:Telestar Corp.
File: B-275855
Date:April 4, 1997
Frank Liu for the protester.
Donald F. Hassell, Esq., Brian T. Kildee, Esq., and Robin B. Teichman,
Esq., Nuclear Regulatory Commission, for the agency.
Jennifer D. Westfall-McGrail, Esq., and Christine S. Melody, Esq.,
Office of the General Counsel, GAO, participated in the preparation of
the decision.
DIGEST
1. Protest challenging agency's conclusion that protester's proposal
is technically unacceptable is denied where record demonstrates that
agency's evaluation of the proposal was reasonable.
2. Agency was not required to conduct discussions with offeror whose
proposal reasonably had been determined technically unacceptable and
excluded from the competitive range.
DECISION
Telestar Corp. protests the rejection of its proposal under request
for proposals (RFP) No. RS-IRM-96-177, issued by the Nuclear
Regulatory Commission (NRC) for the acquisition of microcomputer
hardware and software, laser printers, and microcomputer support
services. The protester takes issue with the technical evaluation of
its proposal and objects to the agency's failure to hold discussions
with it.
We deny the protest.
BACKGROUND
The RFP sought a contractor to furnish computer software and hardware
and laser printers and to provide computer support services, including
hardware moves, upgrades, and maintenance and software installation
and deinstallation.[1] Competition under the solicitation was limited
to socially and economically disadvantaged firms in the transitional
stage of the Small Business Administration's section 8(a) program.
The RFP provided for award to the offeror whose proposal represented
the most advantageous technical/cost relationship, with technical
merit a more significant factor than cost in the selection process.
The solicitation identified the technical evaluation factors (and
subfactors) and their corresponding weights as follows:
I. Technical Competence 45
A. Key Personnel 20
B. Technical Approach 20
C. Technical Documentation 5
II. Corporate Experience and Contractor Past Performance45
III. Program Management and Project Reporting 5
IV. Vendor Relationships 5
Offerors were advised that in addition to submitting a written
proposal, they would be required to make an oral technical
presentation and to participate in an interview conducted by
government representatives. The sole purpose of the oral presentation
and the interview, the RFP explained, was to permit the agency to test
and evaluate the offeror's knowledge and competence with regard to the
government's requirements and program objectives, the relevant
technology, and program challenges and risks. The solicitation
further advised that the oral presentation and interview answers were
not part of the offers and could not include changes to the offers;
that neither the presentation nor the interview would constitute
discussions within the meaning of Federal Acquisition Regulation (FAR) sec.
15.601 FAC (90-40) and 15.610 FAC (90-31), nor would they obligate the
government to entertain revisions to the offers or to solicit best and
final offers; and that the NRC intended to award without discussions.
Five offerors submitted timely written proposals. The proposals were
reviewed by members of the source evaluation panel (SEP), who noted
areas requiring clarification. Each of the offerors was then
scheduled for an oral presentation/ interview. After each oral
presentation, the SEP convened and decided on interview questions to
ask the presenters. The questions were intended to clarify written
materials, to amplify areas not adequately explained and to probe the
qualifications and abilities of the key personnel proposed. Upon
completion of each interview, the panel reconvened to score the
proposal in question.
The five proposals received scores ranging from 95.99 (Sylvest
Management Systems Corp.) to 16.99; Telestar's score of 27.65 was
second low.[2] The SEP concluded that Telestar's proposal was
technically unacceptable due to the deficiencies in the technical and
management proposals as well as its corporate experience. The SEP
determined that since Sylvest's score so far exceeded any of the
others, and since its evaluated costs were lower than those of the
only other proposal that could possibly have been made acceptable
through negotiations, it was the only firm that stood a reasonable
chance of receiving the award; accordingly, the SEP recommended a
competitive range of one, i.e., Sylvest. The contracting officer
accepted the panel's recommendation and notified the four firms other
than Sylvest that their proposals had not been included in the
competitive range. Telestar responded by protesting first to the
agency and then to our Office.
Telestar's proposal received a score of 9.66 (of a possible 45) under
the technical competence evaluation factor; a score of 11.66 (of 45)
under the corporate experience and past performance evaluation factor;
a score of 3 (of 5) under the program management and project reporting
factor; and a score of 3.33 (of 5) under vendor relationships.
Proposal weaknesses identified by the evaluators included:
--emphasis on network installation and support services, an area
of work not required under the solicitation, in combination with lack
of information pertaining to the installation or maintenance of
workstation platforms, an area that was required, indicated that
Telestar did not understand the nature of the work to be performed;
--failure to adequately address maintenance support and services;
--failure to adequately address integration with existing NRC
project management and tracking systems;
--lack of experience on the part of proposed personnel in work
related to the work to be performed under the solicitation;
--lack of corporate experience in work of a similar size, scope,
or nature to that required here.
DISCUSSION
The protester takes issue with the agency's evaluation of its
proposal, arguing that it is technically qualified to perform the work
required and that the evaluators wrongly concluded that it
misunderstood the nature of the work to be performed. The protester
further argues that to the extent that there were deficiencies in its
technical approach, the contracting officer should have pointed them
out during discussions and given it an opportunity to correct them.
The evaluation of technical proposals is primarily the responsibility
of the contracting agency since the agency is responsible for defining
its needs and the best method of accommodating them and must bear the
burden of any difficulties resulting from a defective evaluation.
Young Enters., Inc., B-256851.2, Aug. 11, 1994, 94-2 CPD para. 159 at 3.
In reviewing protests challenging an agency's evaluation of proposals,
we will not substitute our judgment for that of the agency regarding
the merits of proposals; rather, we will examine the agency's
evaluation to ensure that it was reasonable and consistent with the
stated evaluation criteria and applicable statutes and regulations.
Federal Envtl. Servs., Inc., B-250135.4, May 24, 1993, 93-1 CPD para. 398
at 9. The fact that a protester does not agree with the evaluation
does not render the evaluation unreasonable. Newport News
Shipbuilding and Dry Dock Co. et al., B-261244.2 et al., Sept. 11,
1995, 95-2 CPD para. 192 at 8.
Here, the protester has failed to demonstrate that the agency's
evaluation of its proposal was unreasonable. The protester's argument
that it should not have been found "technically unqualified" is
misdirected--Telestar itself was not found to be technically
unqualified, its proposal was determined to be technically
unacceptable. Even the most well-qualified firm may be rejected as
technically unacceptable if it fails to contain information
demonstrating compliance with the solicitation requirements. See
Sunbelt Properties, Inc., B-245729.3, Mar. 12, 1992, 92-1 CPD para. 278 at
2.
Further, there is no evidence in the record to show that it was
unreasonable for the evaluators to conclude that the emphasis in
Telestar's proposal on network installation and support, in
combination with its failure to discuss other required areas of work,
indicated a lack of understanding of the solicitation's requirements.
The protester contends that its emphasis on network installation and
support was not misplaced since the RFP stated that 3 years of
experience in "network connectivity" was desirable for the senior
microcomputer technicians and that 2 years "exposure" to such was
desirable for the microcomputer technicians. As the agency points
out, however, "network connectivity" (i.e., assuring that computers
function properly when connected to a network) is not the same thing
as installing and maintaining a network; the former was encompassed
within the work to be performed under this solicitation, while the
latter was not. Also, it was apparent from the solicitation that
experience in network connectivity was far less significant than
experience in other areas relating to the integration and installation
of computer systems hardware and software; for the senior computer
technicians, for example, 7 years of experience with the latter was
required, while only 3 years of experience with the former was
"desired."
Regarding the protester's argument that its proposal should have
received a higher score under the corporate experience/past
performance criterion, the solicitation clearly provided that in
evaluating proposals under this factor, the evaluators would consider
the extent to which the offeror has successfully performed on past or
current contracts "of similar size and scope related to this effort."
The evaluators determined that only one of the protester's references
was for related work (i.e., both the acquisition and support of
computers); the others were limited to work in Telestar's factory
manufacturing, upgrading, and installing peripherals in microcomputers
and working with telecommunications network and other nonrelevant
equipment. The protester insists that all of these contracts did
involve support services since it furnishes warranties on all of its
delivered equipment. The agency points out in response, however, that
warranty work is only a limited part of the broad spectrum of support
services called for in this solicitation. Since the protester's
proposal did not demonstrate that it has experience performing the
type of support services required here, the record supports the
evaluators' scoring of the proposal under the corporate
experience/past performance criterion.
The protester has not attempted to rebut other aspects of the agency's
technical evaluation.[3] For example, it has not argued that the
resumes submitted for its key employees demonstrated compliance with
all of the solicitation's experience requirements, nor has it argued
that its proposal adequately addressed integration with existing NRC
project management and tracking systems or maintenance support and
services. Absent any attempt by the protester to rebut the agency's
findings, and given that the record supports the agency's findings, we
see no basis upon which to conclude that the agency's evaluation was
unreasonable. See Amcare Medical Servs., Inc., B-271595, July 11,
1996, 96-2 CPD para. 10 at 2.
The protester also argues that the agency improperly failed to conduct
discussions with it. The FAR requires agencies to conduct discussions
only with responsible offerors submitting proposals within the
competitive range, i.e., offerors whose proposals stand a reasonable
chance of being selected for award. FAR sec. 15.609(a),(b); 15.610(b).
Since the evaluators reasonably concluded that Telestar's proposal was
technically unacceptable and thus properly excluded it from the
competitive range, the agency was under no obligation to hold
discussions with Telestar.[4] Cobra Tech., Inc., B-272041;
B-272041.2, Aug. 20, 1996, 96-2 CPD para. 73 at 6.
Telestar also objects to the agency's failure to evaluate its price.
We fail to see any impropriety in this since Telestar's technical
proposal had been determined to be unacceptable, it would have been
ineligible for award, no matter what its price. Data Resources,
B-228494, Feb. 1, 1988, 88-1 CPD para. 94 at 5.
In its initial protest, Telestar also complained that a company
associated with Tri-Cor, the incumbent contractor for the services
sought here, had been accorded favored treatment by the agency in the
evaluation process. When it was revealed that Sylvest, and not the
company associated with Tri-Cor (which was never identified by name by
either the agency or the protester), had been selected for award, the
protester changed its argument to a complaint that Sylvest had
received favored treatment. The protester has offered no evidence to
substantiate its allegations, and we found none during our review of
the record. We will not attribute prejudicial motives to contracting
officials on the basis of unsupported allegations, inference or
supposition. McDonnell Douglas Corp., B-259694.2; B-259694.3, June
16, 1995, 95-2 CPD para. 51 at 28.
The protest is denied.
Comptroller General
of the United States
1. Network services were not included in the services sought since NRC
contracts for them separately.
2. The other two scores were 66.6 and 58.66.
3. In commenting on the agency report, the protester raised for the
first time the argument that the agency evaluators did not have the
technical qualifications to evaluate proposals. We will not review
allegations concerning the qualifications of evaluators absent a
showing of fraud, conflict of interest, or actual bias on the part of
the evaluators. American CASA/National Air, B-271274; B-271274.3, May
23, 1996, 96-1 CPD para. 251 at 4. No such showing has been made here; in
fact, the protester offers no evidence in support of its allegation.
4. To the extent that the protester may have misconstrued the
interview phase of the proposal process as oral discussions, the RFP
explicitly advised that the interviews were not intended to be
discussions and that offerors would not be entitled to submit revised
offers upon their conclusion.