BNUMBER: B-261506.2
DATE: November 7, 1995
TITLE: Adler Construction, Inc.
**********************************************************************
Matter of:Adler Construction, Inc.
File: B-261506.2
Date: November 7, 1995
Rosemary Hanna Hayes, Esq., and Paul W. Moses II, Esq., Maguire,
Voorhis & Wells, for the protester.
Christopher P. Kneib, Esq., Cynthia S. Guill, Esq., and Diane D.
Hayden, Esq., Department of the Navy, for the agency.
C. Douglas McArthur, Esq., and Christine S. Melody, Esq., Office of
the General Counsel, GAO, participated in the preparation of the
decision.
DIGEST
Contracting officer properly rejected bid containing language that
made it uncertain, absent post-bid opening explanation, whether bidder
intended to provide ozone treatment system in accordance with
specifications.
DECISION
Adler Construction, Inc. protests the award of a contract to Heard
Construction, Inc. under invitation for bids (IFB) No.
N62467-94-B-2690, issued by the Naval Facilities Engineering Command
for installation of an ozone water treatment system. Adler contends
that the Navy erroneously determined its bid to be nonresponsive.
We deny the protest.
On April 4, 1995, the agency issued the solicitation for a fixed-price
contract to install a new ozone water treatment system and ancillary
mechanical and electrical systems for cooling towers at the Naval Air
Warfare Center in Orlando, Florida.
Adler submitted the lowest of 11 bids received on May 18. Item 17 of
the bid form, standard form (SF) 1442, where Adler entered its bid
price, contained the following notation: "Price based on alternate
ozone equipment than shown on drawings." On May 19, in response to an
inquiry by a contract specialist, Adler provided an explanation of its
bid, in which it denied taking exception to any of the solicitation
requirements.
The Navy concluded, however, that it could not determine that the bid
was responsive without consideration of the post-bid opening
explanation. Accordingly, by letter of July 12, the Navy rejected
Adler's bid, and this protest followed.
Adler explains that the statement in item 17 of the SF1442 merely
repeated what the solicitation provided. The solicitation contained
six drawings. The fifth of these drawings, No. 5241588, the piping
and equipment layout and flow diagram, used a Reztek model 2L-1050
ozone generator to depict the process water ozonation flow. The
drawing contained a legend, specifically stating that the listing of a
manufacturer was "intended only to convey the basis of design" and was
not intended as a limitation on competition. Further, amendment No.
0003 to the IFB, dated May 4, elaborated on this guidance as follows:
"The number of injectors and hand valves shown [on drawing No.
5241588] is intended to be conceptual only. The number of
injectors and valves, and their arrangement, shall be as
necessary to meet the requirements of the specification."
Thus, Adler explains, it only inserted the language in item 17 of the
SF 1442 to advise the agency that as permitted by drawing No. 5241588,
the protester intended to provide another brand of ozone generator
than the Reztek model shown on that drawing. Adler concedes that it
provided this information "unartfully" but argues that the agency is
simply overanalyzing the bid.
To be responsive, a bid must unequivocally offer to provide the exact
item or service called for in the IFB so that acceptance of the bid
will bind the contractor to perform strictly in accordance with the
IFB's material terms and conditions. Astro-Valcour, Inc., B-253253,
Aug. 30, 1993, 93-2 CPD 128. An agency must reject any bid where
the bidder attempts to impose conditions that would modify such
material terms and conditions. Federal Acquisition Regulation
14.404-2(d); New Dimension Masonry, Inc., B-258876, Feb. 21, 1995,
95-1 CPD 102. Where a bid is ambiguous with respect to a material
requirement, the bid must be rejected as nonresponsive. Northwestern
Motor Co., Inc., B-244334, Sept. 16, 1991, 91-2 CPD 249.
Here, drawing No. 5241588 depicted not only an ozone generator but
pumps and an air compressor, with specific requirements for each.
Absent any description of the equipment or any explanation as to which
equipment the note at item 17 of the SF 1442 referred, the bid was
ambiguous as to whether Adler intended to furnish equipment meeting
the specifications. This ambiguity rendered the bid nonresponsive.
Id. Adler's intention of providing a system meeting specifications
becomes clear only when one considers the explanation provided in
Adler's May 19 letter. A bid which is nonresponsive on its face may
not, however, be converted into a responsive bid by post-bid opening
clarifications or corrections. Plateau Elec. Constructors, Inc.,
B-256495, June 27, 1994, 94-1 CPD 384.
The record therefore supports the Navy's determination that Adler's
bid was nonresponsive, since the bid was ambiguous and it would have
been improper to consider Adler's explanation to establish the
responsiveness of the bid.
The protest is denied.
Comptroller General
of the United States