BNUMBER: B-259274
DATE: May 22, 1996
TITLE: Funding of Maintenance Contract Extending Beyond Fiscal
Year
**********************************************************************
Matter of:Funding of Maintenance Contract Extending Beyond Fiscal Year
File: B-259274
Date: May 22, 1996
DIGEST
1. Section 2410a of title 10, U.S. Code, provides that funds
appropriated to Department of Defense for a fiscal year are available
for payments under maintenance contracts for 12 months beginning at
any time during the fiscal year. Kelly Air Force Base may award two
vehicle maintenance contracts charging fiscal year 1994 money for each
contract so long as each contract is properly awarded in fiscal year
1994 and each contract does not exceed 12 months in duration.
2. Section 2410a of title 10, U.S. Code, is a statutory exception to
the bona fide needs rule. The statute authorizes the Department of
Defense to use current fiscal year budget authority to finance a
severable service contract for equipment maintenance that continues
into the next fiscal year.
3. Air Force decision to leave 8 months of a 12-month severable
service contract unfunded at the time of award does not violate the
Antideficiency Act because of Availability of Funds clause in the
contract. Nor did the Air Force decision violate the bona fide needs
rule, because severable services contracts are funded out of funds
current at the time services are provided unless otherwise authorized
by law.
DECISION
During the third option year of a fixed price contract for vehicle
maintenance services, Kelly Air Force Base modified the contract
period so that the contract would expire on August 31, 1994. Kelly
Air Force Base exercised a fourth option to extend performance from
September 1, 1994 to August 31, 1995. Because fiscal year 1994 budget
authority was only available to finance performance through the first
4 months, that is, until December 31, 1995, the Air Force modified the
contract to provide that after that date, the government's obligation
under the contract was contingent upon the contracting officer
notifying the contractor in writing that funds were available for
continued performance and that the contractor continue work.
A certifying officer at the Kelly Air Force Base asks whether the use
of fiscal year 1994 budget authority to finance both the initial 11
months of orders covered by the third option period and the 4 months
of orders covered by the fourth option period violates 10 U.S.C. sec.
2410a and the bona fide needs rule. There is also implicit in the
facts and circumstances of this case a second question, namely, did
the Air Force's failure to fund at the time of award the remaining 8
months of the contract violate the Antideficiency Act, 31 U.S.C. sec.
1341(a)(1)(B). For the reasons discussed below, we have no objection
to the Air Force's financing of the contracts.
Background
According to the Air Force, in an effort to minimize the surge in
workload at the end of the fiscal year, it has staggered contract
periods for certain support service contracts, including this one, so
that the contracts do not all expire simultaneously. The Air Force
awarded the vehicle maintenance contract here, a fixed price contract
with K&M Maintenance Services, Inc., in 1990 for fiscal year 1991,
with four 1-year option periods. During the third option year, the
Air Force modified the contract period, cutting it short by 1 month
for that year, so that the contract would expire on August 31 instead
of September 30. The Air Force correspondingly changed the fourth
option period to run from September 1, 1994 to August 31, 1995.
At the time of exercise of the fourth 1-year option, the Air Force
only had fiscal year 1994 budget authority available to finance the
first 4 months of the new contract (September through December 1994).
Accordingly, the Air Force modified the contract by adding a clause
stating that the government's obligation beyond December 31, 1994, was
contingent upon the availability of appropriations. The clause
further provided that no legal liability on the part of the government
would arise for contract performance beyond December 31, 1994, unless
and until the contractor received notice in writing from the Air Force
contracting officer that sufficient funds were available and that the
contractor could continue work.
The Air Force cited section 2410a of title 10, U.S. Code, as authority
for its action. Memorandum for SA-ALC/FM10 from SA-ALC/JAN, Sept. 22,
1994. Section 2410a authorizes the Air Force to use funds
appropriated for a fiscal year for payments under contracts for the
maintenance of tools, equipment, and facilities for 12 months
beginning at any time during the fiscal year.
The certifying officer has questioned the legality of the Air Force's
action. The certifying officer asserts that the Air Force used fiscal
year 1994 funds to finance, effectively, a 15-month contract, i.e.,
the 11-month third option period (October 1, 1993 through August 31,
1994) and the first 4 months of the fourth option period (September 1,
1994 through December 31, 1994). The certifying officer believes that
while section 2410(a) permits the Department of Defense (DOD) to
convert an in-house function to a 12-month contract at any time during
a fiscal year, it does not permit DOD to order more than 12 months
worth of services using fiscal-year funds. The certifying officer
reads section 2410a to permit the acquisition of only 12-month
contract services using fiscal year funds, because the law refers to
"payments under contracts . . . for 12 months beginning at any time
during the fiscal year." Our review of the facts and circumstances
identified a second issue concerning the Anti-Deficiency Act
prohibition, 31 U.S.C. sec. 1341(a)(1)(B), against involving the
government in a contract or an obligation in advance of the
appropriation properly chargeable therefor.
10 U.S.C. sec. 2410a and the Bona Fide Needs Rule
The first issue is one of statutory construction. The statute at
issue, 10 U.S.C. sec. 2410a, reads as follows:
"Funds appropriated to the Department of Defense for a fiscal
year shall be available for payments under contracts for any
of the following purposes for 12 months beginning at any time
during the fiscal year:
"(1) The maintenance of tools, equipment, and facilities . . .
."[1]
The Air Force Staff Judge Advocate takes the position that the use of
fiscal year 1994 funds to support 15 months of services "is consistent
with both the letter and spirit of 10 U.S.C. sec. 2410a". He reasons
that when in October 1993, the Air Force awarded the contract for the
third option period, the Air Force properly charged fiscal year 1994
funds for the obligation incurred. By virtue of 10 U.S.C. sec. 2410a,
when the Air Force on September 1, 1994, entered into a contract for
the fourth option period, it necessarily charged fiscal year 1994
funds for the 4-month liability it incurred. The only limitation in
10 U.S.C. sec. 2410a is that the contract may not exceed 12 months in
duration. The fact that the Air Force could obligate fiscal year
funds to cover a period in excess of 12 months is without "any legal
significance."
We agree with the Air Force's reading of the statute. In our opinion,
the phrase "for 12 months" modifies "contracts" and not "payments."
Fiscal year appropriations have long been available to make payments
for more than 12 months to liquidate valid obligations. We know of no
reason for Congress to enact legislation to limit payments on valid
obligations only to 12 months. If Congress had intended such a
significant departure from settled law, we think it would have more
clearly so indicated.
The purpose of 10 U.S.C. sec. 2410a is to overcome the bona fide needs
rule of this Office. By making current fiscal year budget authority
available in the next fiscal year when it would otherwise not be
available, section 2410a is a statutory exception to the bona fide
needs rule. The bona fide needs rule provides that a fiscal year
appropriation may be obligated only to meet a legitimate, or bona
fide, need arising in the fiscal year for which the appropriation was
made.[2] For service contracts, whether an expense was properly
incurred or properly made during the period of availability depends
upon whether the services are severable or nonseverable. A
nonseverable contract is essentially a single undertaking that cannot
be feasibly subdivided. B-240264, Feb. 7, 1994. It is considered a
bona fide need of the fiscal year in which the agency entered into the
contract. Consequently, agencies should record nonseverable service
contracts as obligations at the time of award. Service contracts,
where the services are continuing and recurring in nature, such as the
vehicle maintenance contract here, are severable and are chargeable to
the appropriation current at the time services are rendered. See 60
Comp. Gen. 219, 221 (1981). By definition, severable services address
needs of the time the services are rendered. 71 Comp. Gen. 428, 430
(1992).
As a general rule, a severable service contract crossing fiscal years
and financed exclusively from annual appropriations in the year of
award requires specific statutory authority. 71 Comp. Gen. at 430.
Section 2410a provides the requisite statutory authorization for DOD
vehicle maintenance contracts. By making current year budget
authority available for such contracts for a 12-month period
"beginning at any time during a fiscal year," section 2410a clearly
exempts DOD from the bona fide needs rule as it ordinarily applies to
severable service contracts. It permits DOD to obligate budget
authority covering the entire, annual contract at the time it enters
into the contract, similar to nonseverable service contracts, rather
than budget authority available at the time the services are rendered.
The fact that fiscal year funds may be used to make payments for more
than 12 months of services is a consequence of the law that, in the
words of the Air Force Staff Judge Advocate, has "no legal
significance."
Antideficiency Act
The second issue in this case is application of the basic proscription
of the Antideficiency Act contained in 31 U.S.C. sec. 1341(a)(1)(B). The
Antideficiency Act prohibits an officer or employee of the United
States from "involving [the] government in a contract or obligation
for the payment of money before an appropriation is made unless
authorized by law." 31 U.S.C. sec. 1341(a)(1)(B). Here, the Air Force,
as a result of its actions during the period questioned by the
certifying officer, awarded two contracts: one covering the 11-month
third option period and the other covering the 12-month fourth option
period. With respect to the latter contract, the Air Force included
an Availability of Funds clause in an attempt to limit its liability
under the contract to the amount of fiscal year 1994 funds obligated
to cover performance in the first 4 months, that period beginning
September 1, 1994 and ending December 31, 1994, of the 12-month
contract:
"No legal liability on the part of the Government for any payment
may arise for performance under this contract beyond 31 December
1994, until funds are made available to the Contracting Officer
for performance and until the contractor receives notice of
availability to be confirmed in writing by the Contracting
Officer."
Under these circumstances, the issue is whether the Air Force involved
the government in a contract for the payment of money in advance of
the appropriation available for the remaining 8-month period of the
contract without authority of law.
We think the resolution of this issue is controlled by our decision in
A-60589, July 12, 1935. In order to even out the workload, the
Procurement Division of the Treasury Department adopted the practice
of staggering the award of contracts. To this end, the Treasury
Department awarded a contract for gear oil, the contract term running
from January 1, 1935 to March 31, 1936 (the then fiscal year ran from
July 1 to June 30). The contract was for an indefinite quantity and
imposed no financial liability on the government until the government
placed an order; the only obligation under the contract was a
negative one--not to procure from someone else. Even though the
contract extended beyond the period of availability of the annual
appropriation involved, we did not object to the "contractual
obligation" as a violation of the Anti-Deficiency Act, 31 U.S.C. sec.
1341(a)(1)(B).[3]
We have had occasion to revisit our decision in A-60589, July 12,
1935, and expressly declined to overrule it. 48 Comp. Gen. 497, 500
(1969). In 48 Comp. Gen. 497, 500 (1969), we questioned whether the
decision was "technically correct" in light of 42 Comp. Gen. 272
(1962). However, since we had permitted 1-year requirements contracts
under fiscal year appropriations to extend beyond the end of the
fiscal year "for over 30 years apparently in reliance upon the July
12, 1935, decision [A-60589]," we did not object to the continuance of
this practice. Id. at 500.
Today, as in 1969, we see no reason to disturb the implicit holding of
A-60589, July 2, 1935, namely, that a naked contractual obligation
that carries with it no financial exposure to the government does not
violate the Antideficiency Act.[4] Indeed, the criticism of the logic
of A-60589 contained in 48 Comp. Gen. 497, 500, is arguably based on a
misreading of the facts and the rationale for our decision in 42 Comp.
Gen. 272 (1962). (See, in this regard, our discussion of the effect
of a Limitation of Funds clause in light of the Antideficiency Act in
71 Comp. Gen. at 431.) However, we need not resolve that matter here
since we are persuaded that the Availability of Funds clause included
in the contract converted the government's obligation for the
remaining 8 months of the fourth option period contract to no more
than a "negative" obligation not to procure maintenance services
elsewhere should such services be needed. Since section 2410a
extended the availability of Air Force's budget authority beyond the
end of the fiscal year, the critical point in time for Antideficiency
Act purposes was the date on which the Air Force was to exhaust the
amount of its fiscal year 1994 appropriations. At this point, the Air
Force had a choice: either fund the remaining term of the contract
with fiscal year 1995 funds or do without the maintenance services.
The effect of the Air Force's inclusion of the Availability of Funds
clause, for fiscal law purposes, was to convert the government's
financial obligation to only a contractual obligation not to procure
elsewhere.
Accordingly, we do not object to the Air Force's financing of its
fourth option period, beginning September 1, 1994.
/s/Robert P. Murphy
for Comptroller General
of the United States
1. Section 2410a is a codification of a freestanding, permanent
authority contained in a continuing defense appropriation for fiscal
year 1986. Pub. L. No. 99-190, sec. 8005(e), 99 Stat. 1202-1203 (1985).
The language of section 8005(e) of Public Law 99-190 is not materially
different from section 2410a and as relevant here simply made fiscal
year DOD appropriations available for "payments under contracts for
maintenance of tools and facilities for 12 months beginning at any
time during the fiscal year."
2. The rule has its statutory basis in section 1502(a) of title 31,
U.S. Code, which provides: "The balance of an appropriation or fund
limited for obligation to a definite period is available only for
payment of expenses properly incurred during the period of
availability or to complete contracts properly made within that period
of availability."
3. We did object in this case to the 15-month term of the contract.
Title 41 U.S.C., Section 13, then Revised Statutes sec. 3735, limits the
duration of contracts for stationery and other supplies to one year
from the date of contract award.
4. We do not view our conclusion here or our reliance on A-60589, July
12, 1935, as inconsistent with the Supreme Court's decision in Leiter
v. United States, 271 U.S. 204 (1925) or our decisions based thereon.
See 63 Comp. Gen. 129 (1983) (3-year Multiple Award Schedule
agreements do not violate Anti-Deficiency Act since there is no
binding obligation to expend funds until agencies issue purchase
orders against MAS agreements).