[Federal Register Volume 91, Number 159 (Wednesday, August 19, 2026)]
[Notices]
[Pages 53669-53674]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2026-16864]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-255; NRC-2026-3796]


Palisades Energy, LLC; Palisades Nuclear Plant; Exemption

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued an 
exemption in response to a request dated July 10, 2026, as supplemented 
by letter dated July 30, 2026, from Palisades Energy, LLC. The 
exemption authorizes a one-time exemption to allow Operations personnel 
use of the less restrictive work hour limitations described in NRC 
regulations for a period of no more than 60 days commencing upon core 
reload, or until Palisades is connected to the electrical grid, 
whichever occurs first.

DATES: The exemption was issued on August 12, 2026.

ADDRESSES: Please refer to Docket ID NRC-2026-3796 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2026-3796. Address 
questions about Docket IDs in Regulations.gov to Bridget Curran; 
telephone: 301-415-1003; email: [email protected]. For technical 
questions, contact the individual(s) listed in the  For Further 
Information Contact section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin ADAMS Public Search.'' 
For problems with ADAMS, please contact the NRC's Public Document Room 
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email 
to [email protected]. The ADAMS accession number for each document 
referenced (if it is available in ADAMS) is provided the first time 
that it is mentioned in this document.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

FOR FURTHER INFORMATION CONTACT: Brent Ballard, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-0680; email: [email protected].

SUPPLEMENTARY INFORMATION: The text of the exemption is attached.
    Authority: 42 U.S.C. 2011 et seq.

    Dated: August 14, 2026.


[[Page 53670]]


    For the Nuclear Regulatory Commission.
Brent Ballard,
Project Manager, Operating Reactor Licensing Branch 3, Division of 
Licensing Projects 1, Office of Nuclear Reactor Regulation.

Attachment--Exemption

NUCLEAR REGULATORY COMMISSION

Docket No. 50-255

Palisades Energy, LLC; Palisades Nuclear Plant; Exemption

I. Background

    Palisades Energy, LLC (Palisades Energy, the licensee), is the 
holder of Renewed Facility Operating License No. DPR-20, which 
authorizes operation of the Palisades Nuclear Plant (Palisades). The 
license provides, among other things, that the facility is subject 
to all rules, regulations, and orders of the U.S. Nuclear Regulatory 
Commission (NRC, the Commission) now or hereafter in effect. The 
facility consists of one pressurized-water reactor located in Van 
Buren County, Michigan.
    Palisades Energy became subject to the work hour requirements in 
Title 10 of the Code of Federal Regulations (10 CFR) Part 26, 
``Fitness for Duty Programs,'' Section 26.205, ``Work hours,'' after 
Palisades entered an outage status on August 25, 2025. The 
regulatory history of the Palisades restart effort as it relates to 
the work hour requirements is presented in the third work hours 
exemption issued to Palisades Energy on March 18, 2026 (91 Federal 
Register [FR] 13073). However, in the fourth work hours exemption 
issued to Palisades Energy on June 18, 2026, (91 FR 38035), the NRC 
staff determined that a graded Fitness for Duty (FFD) approach for 
fatigue management could be applied to Palisades until nine days 
before initial fuel load due to a combination of factors that 
include the NRC staff's risk assessment, continued applicability of 
the remainder of Subpart I to 10 CFR part 26, and the unique 
circumstances of restarting a decommissioning power reactor. 
Therefore, the NRC staff issued an exemption for the Palisades 
Nuclear Plant to allow the use of the less restrictive outage work 
hour limitations until nine days before the start of the unit's 
initial fuel load into the reactor for various covered individuals 
as described in that exemption, which includes 10 CFR 26.4(a)(1) 
[Operations] personnel.

II. Request/Action

    By letter dated July 10, 2026 (ML26191A405), the licensee 
requested a one-time exemption from the Fitness for Duty (FFD) 
Program work hour requirements in 10 CFR 26.205(d), ``Work hour 
controls,'' pursuant to 10 CFR 26.9, ``Specific exemptions.'' 
Specifically, the licensee requested to use the outage work hour 
controls in 10 CFR 26.205(d)(4) in lieu of the non-outage work hour 
controls described in 10 CFR 26.205(d)(3) and (d)(7) for a period of 
no more than 60 days commencing with core reload, or until Palisades 
is connected to the electrical grid, whichever occurs first, for 
individuals specified in Paragraphs (a)(1) of 10 CFR 26.4, ``FFD 
program applicability to categories of individuals.''
    Section 26.205(d)(3) of 10 CFR requires licensees to comply with 
the requirements for individuals to have a minimum number of days 
off per week depending on the duration of shift schedules, averaged 
over the shift cycle, and the duties being performed. Individuals 
working 8-hour shift schedules shall have at least 1 day off per 
week, and individuals who are working 10-hour shift schedules shall 
have at least 2 days off per week. Individuals working 12-hour shift 
schedules while performing the duties described in 10 CFR 26.4(a)(1) 
through (a)(3) shall have at least 2.5 days off per week and 
individuals working 12-hour shift schedules while performing duties 
described in 10 CFR 26.4(a)(4) shall have at least 2 days off per 
week. Section 26.205(d)(7) of 10 CFR, requires licensees to comply 
with the requirements for maximum average work hours wherein 
individuals may not work more than a weekly average of 54 hours, 
calculated using an averaging period of up to 6 weeks, which 
advances by 7 consecutive calendar days at the finish of every 
averaging period. The licensee seeks a one-time exemption from the 
requirements of 10 CFR 26.205(d)(3) and (d)(7).
    The requirements in 10 CFR 26.205(d)(4) provide that during the 
first 60 days of a unit outage, licensees need not meet the 
requirements of 10 CFR 26.205(d)(3) or (d)(7) for individuals 
specified in 10 CFR 26.4(a)(1) through (a)(4), while those 
individuals are working on outage activities. However, 10 CFR 
26.205(d)(4) does require the licensee to ensure individuals 
specified in 10 CFR 26.4(a)(1) through (a)(3) have at least 3 days 
off in each successive (i.e., non-rolling) 15-day period, and that 
the individuals specified in 10 CFR 26.4(a)(4) have at least 1 day 
off in any 7-day period. This is collectively known as the outage 
minimum days off (MDO) requirement.
    In the exemption request, the licensee stated they re-evaluated 
the operational support necessary to safely conduct core reload, 
startup, and plant restoration activities through synchronization to 
the electrical grid. Pursuant to 10 CFR 26.5, for the purposes of 
Part 26, a unit outage means, for electricity-generation units, that 
the reactor unit is disconnected from the electrical grid. The 
licensee asserted that the outage work hour provisions of 10 CFR 
26.205(d)(4) are necessary for Operations personnel during the 
requested exemption period. Concurrently with this exemption 
request, the licensee requested that the portion of the previous 
exemption from 10 CFR 26.205(d)(3) and (d)(7) for 10 CFR 26.4(a)(1) 
[Operations] personnel currently in effect until nine days before 
core reload be rescinded and replaced by this exemption.

III. Discussion

    Pursuant to 10 CFR 26.9, the Commission may, upon application by 
any interested person or upon its own initiative, grant exemptions 
from the requirements of 10 CFR part 26 when the exemptions are 
authorized by law and will not endanger life or property or the 
common defense and security; and are otherwise in the public 
interest.

A. The Exemption Is Authorized by Law

    The exemption would authorize a one-time exemption from the 
requirements of 10 CFR 26.205(d)(3) and (d)(7) for personnel 
performing duties under 10 CFR 26.4(a)(1) to allow the use of the 
less restrictive work hour controls in 10 CFR 26.205(d)(4) for a 
period not to exceed 60 days commencing with core reload, or until 
Palisades is connected to the electrical grid. As stated, 10 CFR 
26.9 allows the NRC to grant exemptions from the requirements of 10 
CFR part 26. After reviewing the exemption, the NRC staff has 
determined that granting the proposed exemption will not result in a 
violation of the Atomic Energy Act of 1954, as amended, other laws, 
or the Commission's regulations. Therefore, the exemption is 
authorized by law.

B. The Exemption Will Not Endanger Life or Property

    The purpose of Subpart I, ``Managing Fatigue,'' of 10 CFR part 
26 is to ensure that worker fatigue does not compromise the 
abilities of individuals to perform their duties safely and 
competently. The purpose of 10 CFR 26.205(d)(4) is to provide 
licensees flexibility for a limited period in scheduling required 
days off while accommodating more intense work schedules associated 
with a unit outage.
    During the proposed exemption period, personnel performing 
duties in 10 CFR 26.4(a)(1) would be permitted to work in accordance 
with the outage MDO requirements for up to a 60-day period. In the 
July 10, 2026, submittal, the licensee asserted that the exemption 
and the use of the outage work hour controls are ``necessary for 
Operations personnel during this period to maintain continuity of 
experienced operators and supervisors, minimize personnel turnovers, 
preserve operational knowledge, and support effective decision-
making during safety-significant startup evolutions.'' In addition, 
the licensee asserted that the requested exemption provides 
``necessary flexibility to safely complete remaining restart 
activities while maintaining fatigue-management protections, 
enhancing human performance, and supporting safe, reliable startup 
execution.'' The licensee also requested that the previously issued 
exemption on June 18, 2026, (ML26156A018) be rescinded for 10 CFR 
26.4(a)(1) personnel and replaced with this exemption request dated 
July 10, 2026. The exemption issued on June 18, 2026, applied to 
personnel performing duties specified in 10 CFR 26.4(a)(1), (a)(2), 
(a)(3), (a)(4) and granted the licensee to utilize the outage work 
hour controls in 10 CFR 26.205(d)(4) until nine days before initial 
fuel load. The licensee seeks to rescind the portion of the fourth 
exemption specifically for 10 CFR 26.4(a)(1) personnel and instead 
utilize the flexibility provided by the MDO requirements under this 
fifth exemption for 10 CFR 26.4(a)(1) personnel.
    Palisades Energy provides several reasons for the proposed 
exemption. The licensee stated that the exemption period will 
encompass safety-significant activities that require heightened 
operational focus, close coordination across plant organizations, 
and

[[Page 53671]]

conservative decision-making by experienced licensed operators and 
supervisors. The licensee described reactor startup as a highly 
operationally intensive period requiring continuous oversight by 
Reactor Operators and Senior Reactor Operators to direct fuel load 
activities, authorize plant mode changes, ensure Technical 
Specification compliance, and manage plant evolutions. In addition, 
Operations personnel will perform system restorations, integrated 
testing, plant configuration changes, operator training, and 
emergent issue resolution, which the licensee stated significantly 
increases operational workload and the need for continuity of 
experienced staff.
    The licensee asserted that applying outage work-hour controls 
during the exemption period will support safer startup execution by 
reducing unnecessary turnovers, preserving operational knowledge, 
and ensuring critical operational decisions are made by personnel 
most familiar with current plant conditions. Palisades Energy stated 
that outage controls provide greater staffing stability, improve 
oversight and mentoring opportunities for less experienced 
operators, enhance troubleshooting and issue resolution, and support 
efficient completion of startup testing and system restoration while 
maintaining established fatigue-management protections.
    Palisades Energy noted that it maintains sufficient licensed 
operator staffing to meet the requirements of 10 CFR 50.54(m) and to 
safely conduct startup activities. However, the licensee stated that 
the exemption is necessary to maintain continuity of experienced 
Operations personnel during the startup period.
    The licensee asserted that the proposed exemption will not 
endanger life or property because the requested relief is limited to 
Operations personnel for up to 60 days under a highly controlled 
environment with extensive procedural guidance, management 
oversight, testing requirements, and operational reviews. The 
licensee stated that Operations personnel routinely work under 
outage work-hour controls during refueling outages, consistent with 
industry practice, and that applying these controls during the 
exemption period enhances nuclear safety by maintaining continuity, 
reducing turnovers, preserving plant status awareness, and 
supporting conservative decisions during safety-significant 
evolutions. The licensee added that using outage controls minimizes 
risks associated with personnel transitions, loss of operational 
context, and fragmented ownership of plant conditions.
    In the section of the submittal titled ``Mitigating Strategy'' 
the licensee proposed two commitments and several fatigue management 
actions for the duration of the exemption. The first commitment 
includes continued compliance with the work hour limitations in 10 
CFR 26.205(d)(1), the rest breaks in 10 CFR 26.205(d)(2), and 
compliance with the outage MDO requirements in 10 CFR 26.205(d)(4) 
in lieu of the requirements in 10 CFR 26.205(d)(3) and (d)(7). The 
second commitment is to ensure a portion of weekly supervisory 
observations are dedicated to fatigue awareness, fatigue indicators, 
fitness-for-duty behaviors, and worker readiness. The fatigue 
management actions include items such as providing reasonable 
opportunities for restorative sleep, monitoring work duration, 
schedules, and shift rotations, and evaluation of fatigue-related 
concerns into the corrective action program. In addition, the 
licensee proposed enhancements to their behavioral observation 
program including supervisory engagement in the field, individual 
responsibility to identify and report fatigue, and reinforcement of 
stop-work authority and conservative decision making. Further, the 
licensee stated that the personnel performing the duties specified 
in 10 CFR 26.4(a)(1) have not utilized previous work-hour exemptions 
and have complied with the work hour requirements of 10 CFR 
26.205(d)(7) since August 2025.
    The NRC reviewed the exemption request, justification, and 
mitigation strategy and determined that additional clarification and 
information was needed to evaluate if the exemption request will not 
endanger life and property. The NRC staff issued draft request for 
confirmatory information (RCI) and request for additional 
information (RAI) to the licensee on July 23, 2026, and held 
clarification calls with the licensee on July 28, 2026, and July 30, 
2026. By letter dated July 30, 2026, (ML26212A004), the NRC staff 
issued a final RCI and RAI to the licensee that requested additional 
details about the applicable personnel, the risk of cumulative 
fatigue, and the potential benefits or impacts to the schedule, 
fatigue limits, and continuity of operations. The licensee submitted 
a response to the RCI and RAIs on July 30, 2026 (ML26211A374) which 
is discussed below.
    The NRC staff evaluated the licensee's proposed mitigating 
actions and commitments to manage fatigue for individuals performing 
duties specified in 10 CFR 26.4(a)(1) during the requested 
exemption. Palisades Energy requested authorization to implement the 
outage work-hour controls in 10 CFR 26.205(d)(4), in lieu of the 
online work-hour requirements in 10 CFR 26.205(d)(3) and (d)(7), for 
a 60-day period supporting fuel load and startup activities starting 
with commencement of fuel load. The staff noted that Operations 
personnel were included in the previous exemption. However, the 
licensee has demonstrated compliance with the applicable maximum 
average work hour controls in 26.205(d)(7) and confirmed in the RCIs 
that Operations personnel have not worked more than 54 hours since 
at least the end of the first exemption period and will not work 
more than 54 hours prior to implementation of core load. 
Additionally, the licensee committed that Operations personnel will 
not exceed 54 hours per week averaged over a 6-week cycle prior to 
core-load activities, and will receive at least a 34-hour break in 
the nine days preceding implementation of outage controls. In 
support of its request, the licensee requested recession of the 
previous exemption portion that is applicable individuals performing 
duties in 10 CFR 26.4(a)(1) [Operations]. These factors provided 
assurance that cumulative fatigue has been and will be adequately 
managed prior to the exemption.
    The licensee stated that Operations personnel normally work 
under outage work-hour provisions during refueling outages while 
performing shutdown, maintenance, testing, restoration, and startup 
preparations. The staff notes that during the proposed exemption 
period, Palisades will continue to be in outage period as defined by 
10 CFR 26.5 until connected to the electrical grid. While the staff 
acknowledges that using outage controls is standard industry 
practice during refueling outages, the overall scope and complexity 
of Palisades Energy's activities differ from a typical outage 
because the plant is concurrently restoring a number of safety-
significant systems, structures, and components (SSC) to operability 
in addition to startup activities. These additional activities could 
increase the amount and intensity of operator tasks or the number 
and complexity of operational decisions which can contribute to an 
increased risk of human error and cumulative fatigue.
    In response to RAI 1a, the licensee clarified that most safety-
related systems required for startup will be restored and have 
completed Technical Specification surveillance requirements and 
procedural testing before entering the applicable modes for power 
ascension. As Operations personnel transition from overseeing large-
scale equipment restoration to directing integrated startup 
evolutions, the licensee expects operator workload to shift toward 
plant operations, situational awareness, and decision-making. 
Contracted Operations personnel will supplement licensed operators 
by performing functions traditionally performed by licensed staff, 
thereby reducing administrative burden and operator cognitive load.
    The licensee made the following assertions regarding staffing 
and its implications for Operations personnel considering compliance 
with either the outage or online work hour controls. First, using 
outage work-hour controls minimizes fatigue risk by continuing to 
limit maximum hours and continuing to provide minimum break 
requirements while maintaining stable crew schedules to maintain 
continuity among experienced operators thereby reducing cognitive 
burden. Second, compliance with online work-hour provisions would 
require a five-on/three-off rotation, increasing personnel 
transitions and reducing continuity. Third, operators returning from 
their scheduled time off must regain familiarity with evolving plant 
conditions, ongoing activities, increasing reliance on personnel 
transitions, shift turnovers, and the transfer of detailed 
operational knowledge. As a result, Operators may not complete the 
full transfer of information and context during turnover during a 
period of rapidly changing plant conditions and decision-making. 
Finally, the licensee asserts that reducing the frequency of 
personnel transitions while continuing to manage fatigue through the 
utilization of outage work hour controls will allow Operators to 
maintain continuity of plant knowledge, oversight, and decision-
making.
    Startup activities are highly operationally intensive, requiring 
licensed operators to direct fuel load, authorize mode changes,

[[Page 53672]]

determine operability, maintain Technical Specification compliance, 
and manage plant evolutions. During this exemption period, 
Operations personnel will conduct startup activities in parallel 
with system restoration and operability determinations. The staff 
previously described that outages ``increase the risk of human error 
as a result of higher workload, the performance of more complex and 
infrequent tasks, and the pressure to meet schedular goals.'' (73 FR 
16966). However, the licensee asserted that online work hour 
controls would require more days off to maintain compliance, 
resulting in additional crew rotations and decreasing staffing 
flexibility, independent oversight opportunities, and team cohesion.
    If granted, the licensee states that the outage work hour 
controls provide scheduling flexibility, so that it could increase 
shift staffing from four senior reactor operators (SROs) and three 
reactor operators (ROs) to six SROs and five ROs. The staff 
determined that this additional qualified staffing will enhance 
supervision, oversight, peer checking, and independent verification 
of startup work activities, thereby reducing the potential for human 
error during a complex restart evolution. Contracted Operations 
personnel further support licensed operators by alleviating some 
traditionally performed licensed operator duties.
    The staff also considered the benefits of reduced call-ins and 
fewer on-the-go scheduling changes. Stable outage schedules minimize 
circadian disruptions and allow personnel to plan rest periods, 
although night-shift personnel may still experience circadian 
challenges. Overall, maintaining consistent startup crews reduces 
information transfers and reacquisitions that could contribute to 
communication errors and increased cognitive workload.
    The NRC evaluated the responses to the RAIs. The Palisades 
restart project is a first-of-a-kind unique activity where a nuclear 
power plant in decommissioning status is being returned to 
operational status. Furthermore, Palisades Energy, LLC is the first 
NRC licensee to engage in a complex startup evolution of a 
previously decommissioning nuclear power reactor, which required 
major restoration of safety-significant systems. In addition, this 
may be the first time the licensed operators have worked together in 
operating crews, compromised of a mix of experienced and less 
experienced operators, who will need to perform many startup 
activities such as core load, testing, inspections, surveillances, 
plant configuration changes, operator training, procedural 
execution, operational readiness verification, and grid 
synchronization. The staff acknowledge the particular importance of 
maintaining continuity of operation and crew cohesion throughout 
these complex and intense activities and the impact of continuity 
and cohesion on crew dynamics. Continuity and cohesion can lead to 
crew dynamics demonstrating positive effects such as resilience, 
adaptability, robust decision-making, shared mental models, 
questioning attitudes, and coordination. In addition, by reducing 
information transfers and reacquisitions between licensed operators, 
the licensee can reduce the potential risk for human error which 
could occur due to information gaps, communication errors, and 
increased cognitive workload during the complex startup evolutions.
    The NRC staff considered the overall risk profile of the plant 
during the proposed exemption period. In the fourth exemption, the 
NRC staff found that the risk profile of Palisades prior to fuel 
load was substantially different than that of an operating reactor. 
However, given that Palisades Energy plans to load fuel during this 
proposed exemption period, the risk profile will now increase to 
that of an operating reactor. The nuclear safety risk to the public 
health and safety also increases to that of an operating reactor at 
the point that fuel is placed in a configuration and environment 
that enables reactor operation coinciding with licensed operators 
initiating power ascension activities. The increased risk profile 
within this exemption is compounded by the restoration of a number 
of safety-significant systems for safe operations and the first-of-
a-kind restart evolution. Specifically in relation to this 
exemption, this increases the potential number of tasks and 
decisions, in addition to the need to meet schedule pressure, which 
increases the potential risk of human error and fatigue.
    The NRC staff determined that the mitigating strategy and 
commitments provided by the licensee during the 60-day exemption 
period for individuals performing duties specified in 10 CFR 
26.4(a)(1) provide assurance that licensee will adequately manage 
acute and cumulative fatigue. Acute fatigue will be mitigated 
through ensuring Operations personnel work no more than the maximum 
work hour limitations specified in 10 CFR 26.205(d)(1) and receive 
rest breaks between successive work periods specified in 10 CFR 
26.205(d)(2)(i). Cumulative fatigue will be mitigated through the 
34-hour break in any 9-day period specified in 10 CFR 
26.205(d)(2)(ii) and the three days off in each successive (i.e., 
non-rolling) 15-day period specified in 10 CFR 26.205(d)(4). The 
staff determined that there is reasonable assurance that fatigue 
will be adequately managed for Operations personnel because the 
individuals will not have worked more than 54 hours per week in the 
6-week period prior to commencement of core load and will receive a 
34-hour break before the utilization of outage work hour controls. 
Further, the NRC staff has additional assurance that cumulative 
fatigue will have been managed prior to core load because Operations 
personnel have not worked more than 54 hours since the first 
exemption and the licensee has requested recession of the portion of 
the previous applicable exemption that covers individuals performing 
duties in 10 CFR 26.4(a)(1). Therefore, the NRC determined that the 
requested one-time exemption will not endanger life and property.

C. The Exemption Will Not Endanger the Common Defense and Security

    The exemption would authorize a one-time exemption from the 
requirements of 10 CFR 26.205(d)(3) and (d)(7) to allow the use of 
the less restrictive work hour controls specified in 10 CFR 
26.205(d)(4) for personnel performing duties in 26.4(a)(1) for up to 
60-days. The proposed exemption is not applicable to security 
personnel, nor does it have any relation to or impact on security 
issues. Therefore, the exemption will not endanger the common 
defense and security.

D. The Exemption Is Otherwise in the Public Interest

    The proposed exemption would authorize a one-time exemption from 
the requirements of 10 CFR 26.205(d)(3) and (d)(7) for personnel 
performing duties under 10 CFR 26.4(a)(1) to utilize the less 
restrictive work hour controls specified in 10 CFR 26.205(d)(4) for 
up to 60-days. In considering whether the requested exemption would 
be in the public interest, the NRC considered several factors 
including:
     the nature of the licensee's unique situation 
transitioning from decommissioning back to a power operations 
licensing basis, which requires restoration of safety-related 
equipment, core reload, and plant startup activities; and
     the public health and safety interests of the 
communities that are impacted by the safe restart of the plant.
    The NRC staff considered the unique nature of the Palisades 
Energy restart project, which was in a decommissioning status before 
transitioning to a power operations licensing basis and is currently 
working towards restoration of safety-significant SSCs, core load, 
and initial startup activities to ensure the plant will be safe 
prior to restart. The licensee asserted that ``granting the proposed 
exemption is in the public interest because it supports the safe and 
orderly completion of core reload, startup, and restoration 
activities leading to synchronization of the unit to the electrical 
grid while maintaining the fatigue-management protections 
established under the outage work-hour controls of 10 CFR 
26.205(d)(4).''
    In addition, Palisades asserted that the ``scheduling 
flexibility'' enables the continuity of Operations personnel, 
reduces unnecessary turnovers, preserves operational knowledge, and 
supports effective coordination across plant organizations. The 
licensee further asserted that the proposed exemption enhances human 
performance, strengthens conservative decision-making and 
configuration control, and promotes the safe, reliable, and 
efficient return to service by allowing operators and supervisors 
that have firsthand knowledge of the plant to remain engaged 
throughout startup activities. The NRC reviewed the licensee's 
justification and reasoning to support the proposed exemption. 
However, the staff could not determine how the exemption would be in 
the public interest. In the July 30, 2026, RAI letter, the NRC staff 
requested additional details, the benefits to the public, adverse 
impacts to the public, and the benefits to the Operations personnel, 
plant operation, and continuity of Operations.
    In the licensee's July 30, 2026, letter, Palisades Energy, LLC 
asserted in response to RAI 2a that the exemption is in the public 
interest because it provides a net operational safety benefit during 
the period of core load,

[[Page 53673]]

startup, and restoration activities while managing fatigue under 10 
CFR 26.205(d)(4). The licensee asserted that Operations personnel 
are not presently fatigued because they have not worked more than 54 
hours since entering the initial outage and Operations personnel 
will receive a 34-hour break immediately prior to startup 
activities. Palisades Energy added that increased operational safety 
is gained through improved continuity of licensed operating crews 
during complex and infrequently performed startup evolutions. The 
licensee asserted that by allowing startup crews to remain together 
for longer portions of the restart process, if the exemption is 
granted, will reduce ``turnover-related human performance 
challenges, preserves shared situational awareness, and supports 
continuity of oversight and operational decision-making during 
safety-significant evolutions.'' Palisades Energy asserted that by 
returning critical equipment to service efficiently will result in a 
reduction of overall plant risk and supports restoration of defense-
in-depth which provide a public benefit of enhanced nuclear safety.
    In response to RAI 2b, Palisades Energy asserted that, if the 
exemption is not granted, operations personnel will remain in 
compliance with the online work hour controls working a schedule 
consisting of five consecutive days followed by three days off 
resulting in additional crew rotations and personnel transitions 
during fuel loading, system restoration, testing, plant heat up, and 
power ascension. During these activities, crews may not remain 
intact due to the scheduled time off required under the online work 
hour controls. As stated in Section B, the licensee asserted that 
operators who have a three-day break from shift must return and 
regain familiarity with the plant conditions and ongoing activities 
before assuming the shift. Palisades Energy asserted that without 
the exemption, the licensee would rely on personnel turnovers and 
the transfer of operational knowledge, however, the frequency would 
create additional opportunities for incomplete information transfer, 
loss of operational context, and other turnover-related human 
performance challenges. The licensee asserted that the impact to the 
public is the loss of operational and human-performance benefits 
associated with maintaining dedicated startup crews and result in 
the reduction of continuity, situational awareness, and crew 
coordination during startup activities. Lastly, the licensee stated 
that startup activities could be prolonged, resulting in a delayed 
return to commercial operation and generation of energy.
    The licensee asserted in response to RAI 2c that the exemption 
would provide benefits to plant operation, operations personnel, and 
continuity of operations by increasing operational continuity, 
maintaining startup crews, and reducing turnover-related human 
performance challenges during startup evolutions. For Operations, 
the licensee asserted that the exemption would provide greater 
schedule stability and reduces the need for changes in crew 
composition and short notice call-ins. For plant operation, the 
licensee asserted that the exemption would support safe and 
efficient startup allowing licensed operators to maintain continuity 
of involvement in system restoration and startup activities. For 
continuity of operations, the licensee asserted that the exemption 
would allow startup crews to remain together through larger portions 
of the startup process which reduces the number of personnel 
transitions and reliance on repeated transfers of operational 
knowledge. As a result, Palisades Energy asserted that continuity 
preserves shared situational awareness, crew coordination, and 
reduces turnover-related human performance challenges with repeated 
transfers and reacquisition of plant conditions, equipment status, 
and ongoing activities. The licensee also asserted that the 
exemption provides management with greater flexibility to address 
fatigue concerns when identified in addition to additional staffing 
flexibility.
    The NRC evaluated the RAI responses for their public interest 
considerations. The staff considered that the exemption, if granted, 
may provide an increased safety benefit to the public because 
licensed operators will remain together during complex periods of 
the startup evolutions resulting in increased continuity of 
operational knowledge, crew cohesion, and crew coordination which 
could enhance independent oversight, peer verification, and 
situational awareness. Further, the staff noted that through the 
usage of outage work hour controls, during the first startup 
evolution of a reactor from decommissioning status, will provide 
increased staffing resources, with experienced operators, additional 
oversight through increased shift staffing, and allow for mentoring 
opportunities for less experienced operators. The NRC also 
considered that because crews would remain together longer and have 
less crew turnover, that it may reduce the frequency and quantity of 
information transfers and reacquisitions between individual 
operators and crews changing shifts. It is possible that without 
complete turnovers, operators may not receive the entire depth of 
information and context necessary to identify potential events and 
intervene during the rapidly changing startup evolutions that the 
licensee is completing for the first time since decommissioning.
    As discussed in Section B, the staff noted that the licensee and 
this complement of both experienced and less experienced licensed 
operators will be performing a novel and complex startup evolution 
for the first time together. This restart project is a unique first-
of-a-kind activity for the nuclear industry with unique regulatory 
considerations. The staff's consideration of the public interest 
takes into account the novel conditions presented by a restart and 
the increases in safety provided by increased staffing during the 
exemption period, with consideration of the mitigating factors to 
address the increased risk of fatigue.
    The NRC also considered the potential adverse impacts to the 
public if the exemption was not granted. For the public, the primary 
adverse impact would be the delayed return of Palisades to operation 
and the reliable generation of energy to support Michigan's 
electrical grid. The staff considered the potential adverse impact 
on operations and operations personnel if the exemption was not 
granted. Specifically, without the exemption, Operations personnel 
will have an increased frequency of crew turnovers because 
Operations personnel would continue to comply with the online work 
hour controls resulting in five consecutive days of work followed by 
three days off. This increase in turnover could increase 
opportunities for incomplete information transfers and loss of 
operational context. It may also reduce continuity, crew cohesion, 
crew coordination, and shared mental models due to the number of 
personnel and crew transitions over the duration of the complex 
startup evolutions. These potential impacts could reduce the overall 
safe and efficient return to service and startup of the plant to 
benefit the public interest.
    The NRC staff considered the potential benefits of the exemption 
to operations personnel, plant operation, and continuity of 
operations. For Operations personnel, the exemption would provide 
the benefit of an outage schedule where individuals receive more 
predictable and stable schedules ahead of time which provide 
certainty in planning daily living obligations outside work and 
reduces or eliminates the number of day-night transitions which 
could increase the fatigue risk over the proposed exemption period. 
In addition, an outage schedule could reduce the potential for 
sudden changes in crew composition and call-ins. For plant 
operation, the exemption provides the benefit of retaining startup 
crews together for longer periods of the startup evolutions where 
crews could maintain operational knowledge, oversight, situational 
awareness, and shared mental models without extensive.
    The factors discussed above benefit the public interest because 
they improve safety through maintaining continuity of operations and 
crew cohesion while reducing the potential number of and volume of 
information transfers and reacquisitions which could negatively 
impact the safe and efficient restoration of systems and startup 
activities. These factors can help support operations personnel 
remain engaged and situationally aware throughout the startup 
evolutions. In addition, these factors are known to enhance human 
performance and decision-making which are important for safe and 
efficient completion of complex and infrequently performed 
evolutions like startup and power ascension. Lastly, these factors 
are important at Palisades because Palisades Energy is performing 
this first-of-a-kind startup evolution with a complement of licensed 
operators with a range of experience levels and who may be working 
together for the first time especially in a unique restart project 
which is returning a decommissioning nuclear power reactor to 
operational status.
    The NRC staff considered reasons why the proposed exemption may 
not be in the public interest. For example, compared to the previous 
exemption before fuel load, the risk level during the proposed 
exemption will increase as the licensee begins to load fuel into a 
configuration that will allow manipulation of controls for 
reactivity.

[[Page 53674]]

However, as all operating reactors experience this evolution, this 
risk is balanced by ensuring that Operations personnel are fit for 
duty and have reliable human performance to perform the intensive 
and complex work necessary for startup activities and to mitigate 
the potential for an accident during startup. In order to ensure 
Operations personnel are fit for duty and have reliable human 
performance prior to the startup activities, the licensee confirmed 
in their RCI response that Operations personnel have not and will 
not work more than 54 hours per week and will receive a 34-hour 
break in the nine-day period before commencing core load activities.
    The NRC staff evaluated the unique nature of the Palisades 
restart project, the previous work hours and breaks for Operations 
personnel, the mitigating strategy and commitments, and RAI 
responses against the balance of public interest considerations. The 
NRC determined that providing an exemption to permit individuals 
performing duties in 26.4(a)(1) to use the outage work hour controls 
in 10 CFR 26.205(d)(4) for up to a 60 day period commencing with 
core load would be in the public interest. Therefore, the NRC staff 
finds that approval of the requested exemption is otherwise in the 
public interest.

E. Environmental Considerations

    This action relates to changes to scheduling requirements. The 
NRC staff has determined that any ground disturbance is limited to 
previously disturbed areas. Additionally, the NRC staff has 
determined that the action involves no significant change in the 
types or significant increase in the amounts of any effluents that 
may be released offsite, no significant increase in individual or 
cumulative public or occupational radiation exposure, and no 
significant increase in the potential for or consequences from 
radiological accidents. Finally, the NRC staff has determined that a 
categorical exclusion applies and that special circumstances under 
10 CFR 51.22, ``Categorical exclusions,'' are not present that would 
preclude reliance on the categorical exclusion. Accordingly, this 
action meets the eligibility criteria for categorical exclusion set 
forth in 10 CFR 51.22(d)(5). Pursuant to 10 CFR 51.22, no 
environmental impact statement or environmental assessment need be 
prepared in connection with the action.

IV. Conclusions

    Accordingly, the Commission has determined that, pursuant to 10 
CFR 26.9, the exemption is authorized by law, will not endanger life 
or property or the common defense and security, and is otherwise in 
the public interest. Therefore, the Commission hereby grants 
Palisades Energy, LLC a one-time exemption from 10 CFR 26.205(d)(3) 
and (d)(7) for individuals performing duties in 10 CFR 26.4(a)(1) to 
allow the use of the outage MDO requirements described in 10 CFR 
26.205(d)(4) starting on upon commencement of core load activities 
and terminating after 60 days or when Palisades is connected to the 
electrical grid, whichever occurs first. While the exemption is in 
effect, Palisades Energy will ensure that individuals performing 
duties in 10 CFR 26.4(a)(1) have at least 3 days off in each 
successive (i.e., non-rolling) 15-day period. During the exemption 
period, Palisades Energy will also ensure that individuals' work 
hours do not exceed the limits specified in 10 CFR 26.205(d)(1), 
individuals receive a 10-hour break between successive work periods 
specified in 10 CFR 26.205(d)(2)(i), and individuals receive a 34-
hour break in any 9-day period specified in 10 CFR 26.205(d)(2)(ii).
    Additionally, Palisades Energy will use the outage MDO 
requirements, rest break requirements, maximum work hour 
limitations, and the mitigating strategy and commitments described 
in the July 10, 2026, enclosure. These actions and commitments 
provide reasonable assurance that acute and cumulative fatigue are 
adequately managed for personnel performing duties in 10 CFR 
26.4(a)(1) for a 60-day period commencing on core load, or until 
connected to the electrical grid, whichever occurs first. 
Furthermore, the Commission hereby grants the licensee's request and 
rescinds the fourth exemption granted on June 18, 2026, for 
Operations personnel described in 26.4(a)(1) and as discussed in 
Section II of this exemption.

    Dated: August 12, 2026.

    For the Nuclear Regulatory Commission.

Mahmoud Jardaneh,

Acting Director, Division of Licensing Projects 1, Office of Nuclear 
Reactor Regulation.

[FR Doc. 2026-16864 Filed 8-18-26; 8:45 am]
BILLING CODE 7590-01-P