NUCLEAR REGULATORY COMMISSION

[Docket No. 50-261; NRC-2025-0076]


Duke Energy Progress, LLC; H.B. Robinson Steam Electric Plant, 
Unit 2; Subsequent License Renewal and Record of Decision

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued 
Subsequent Renewed Facility Operating License No. DPR-23 to Duke Energy 
Progress, LLC (Duke) for H.B. Robinson Steam Electric Plant, Unit 2 
(Robinson). In addition, the NRC has prepared a record of decision 
(ROD) that supports the agency's decision to issue Subsequent Renewed 
Facility Operating License No. DPR-23.

DATES: The NRC issued Subsequent Renewed Facility Operating License No. 
DPR-23 on April 23, 2026.

ADDRESSES: Please refer to Docket ID NRC-2025-0076 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2025-0076. Address 
questions about Docket IDs in Regulations.gov to Bridget Curran; 
telephone: 301-415-1003; email: [email protected]. For technical 
questions, contact the individual listed in the For Further Information 
Contact section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin ADAMS Public Search.'' 
For problems with ADAMS, please contact the NRC's Public Document Room 
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email 
to [email protected]. For the convenience of the reader, 
instructions about obtaining materials referenced in this document are 
provided in the ``Availability of Documents'' section.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

FOR FURTHER INFORMATION CONTACT: Mark Yoo, Office of Nuclear Reactor 
Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-8583; email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Discussion

    Notice is hereby given that the NRC has issued Subsequent Renewed 
Facility Operating License No. DPR-23 to Duke for Robinson. Duke is the 
operator of the facility. Subsequent Renewed Facility Operating License 
No. DPR-23 authorizes Duke to operate Robinson at a reactor core power 
level not in excess of 2,339 megawatts thermal, in accordance with the 
provisions of the Robinson license and technical specifications. Notice 
is also given that the ROD that supports the NRC's decision to issue 
Subsequent Renewed Facility Operating License No. DPR-23 is available, 
and its location is listed in the ``Availability of Documents'' section 
of this document.
    As discussed in the ROD and the final supplemental environmental 
impact statement (SEIS), published as NUREG-1437, Supplement 13, Second 
Renewal, ``Generic Environmental Impact Statement for License Renewal 
of Nuclear Plants Regarding Subsequent License Renewal for H.B. 
Robinson Steam Electric Plant, Unit No. 2, Final Report,'' dated March 
2026, the final SEIS documents the NRC staff's environmental review, 
including the recommendation that the adverse environmental impacts of 
subsequent license renewal (SLR) for Robinson are not so great that 
preserving the option of SLR for energy-planning decision-makers would 
be unreasonable. This recommendation is based on (1) the analysis and 
findings in the NRC's Generic Environmental Impact Statement for 
License Renewal of Nuclear Plants, (2) information provided in the 
environmental report submitted by Duke, (3) the NRC staff's 
consultation with Federal, State, and local governmental agencies and 
Indian Tribes, (4) the NRC staff's independent environmental review, 
and (5) the NRC staff's consideration of public comments received 
during the scoping process and on the draft SEIS.
    Robinson consists of one Westinghouse three-loop pressurized-water 
reactor located near Hartsville, South Carolina. Duke submitted its SLR 
application for Robinson on April 1, 2025, which it supplemented by 
letters through October 1, 2025 (see the ``Availability of Documents'' 
section of this document). The NRC staff has determined that Duke's SLR 
application complies with the standards and requirements of the Atomic 
Energy Act of 1954, as amended (the Act), and the NRC's regulations. As 
required by the Act and NRC regulations in title 10 of the Code of 
Federal Regulations (10 CFR), Chapter I, ``Nuclear Regulatory 
Commission,'' the NRC has made appropriate findings, which are set 
forth in the subsequent renewed license.
    Notice of the NRC's acceptance for docketing of the SLR application 
and an opportunity to request a hearing was published in the Federal 
Register on May 8, 2025 (90 FR 19535). A notice of intent to conduct 
environmental scoping was published on May 22, 2025 (90 FR 21952). In 
April 2026, the NRC staff issued its safety evaluation concerning the 
Robinson SLR application. In December 2025, the NRC staff published a 
draft SEIS for public comment, providing the preliminary results of the 
staff's environmental review of the Robinson SLR application. A notice 
of availability of the draft SEIS was published in the Federal Register 
on January 9, 2026 (91 FR 1007). In March 2026, the NRC staff published 
the final SEIS; a notice of issuance was published in the Federal 
Register on March 20, 2026 (91 FR 13644).
    For further details with respect to this action, see (1) Duke's SLR 
application for Robinson, dated April 1, 2025, as supplemented by 
letters dated through October 1, 2025, (2) the NRC's safety

[[Page 22875]]

evaluation, dated April 2026, (3) the NRC's final SEIS, dated March 
2026, and (4) the NRC's ROD, dated April 23, 2026.

II. Availability of Documents

    The documents identified in the following table are available to 
interested persons through ADAMS, as indicated.

------------------------------------------------------------------------
              Document description                  ADAMS accession No.
------------------------------------------------------------------------
H.B. Robinson Steam Electric Plant, Unit 2,       ML25091A290 (Package).
 Application for Subsequent Renewed Operating
 Licenses, dated April 1, 2025.
NUREG-1437, Revision 2, ``Generic Environmental   ML24087A133 (Package).
 Impact Statement for License Renewal of Nuclear
 Plants,'' Volumes 1-3, dated August 2024.
Supplement No. 1--Changes to the Robinson Unit 2  ML25240B656.
 Subsequent License Renewal Application, dated
 August 28, 2025.
Supplement No. 2--Changes to the Robinson Unit 2  ML25274A131.
 Subsequent License Renewal Application, dated
 October 1, 2025.
``Generic Environmental Impact Statement for      ML25344A144.
 License Renewal of Nuclear Plants, Supplement
 13, Second Renewal, Regarding Subsequent
 License Renewal for H.B. Robinson Steam
 Electric Plant, Unit No. 2, Draft Report for
 Comment,'' dated December 2025.
Safety Evaluation Related to the Subsequent       ML26089A378 (Package).
 License Renewal of H.B. Robinson Steam Electric
 Plant, Unit 2, dated April 2026.
``Generic Environmental Impact Statement for      ML26062A118.
 License Renewal of Nuclear Plants, Supplement
 13, Second Renewal, Regarding Subsequent
 License Renewal for H.B. Robinson Steam
 Electric Plant, Unit No. 2, Final Report,''
 dated March 2026.
Record of Decision, Subsequent License Renewal    ML26044A014.
 Application for H.B. Robinson Steam Electric
 Plant, Unit 2, dated April 23, 2026.
------------------------------------------------------------------------

    Authority: 42 U.S.C. 2011 et seq.

    Dated: April 23, 2026.

    For the Nuclear Regulatory Commission.
Michele Sampson,
Director, Division of New and Renewed Licenses, Office of Nuclear 
Reactor Regulation.