[Federal Register Volume 91, Number 76 (Tuesday, April 21, 2026)]
[Notices]
[Pages 21283-21286]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2026-07713]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. RM21-14-000]


Participation of Aggregators of Retail Demand Response Customers 
in Markets Operated by Regional Transmission Organizations and 
Independent System Operators

AGENCY: Federal Energy Regulatory Commission.

ACTION: Withdrawal of notice of inquiry and termination of rulemaking 
proceeding.

-----------------------------------------------------------------------

SUMMARY: The Commission withdraws a notice of inquiry, which sought 
comment on whether to revise the Commission's regulations that require 
a Regional Transmission Organization or Independent System Operator not 
to accept bids from an aggregator of retail customers that aggregates 
the demand response of the customers of utilities that distributed more 
than 4 million megawatt-hours in the previous fiscal year, where the 
relevant electric retail regulatory authority prohibits such customers' 
demand response to be bid into organized markets by an aggregator of 
retail customers.

DATES: This withdrawal will become effective May 21, 2026.

FOR FURTHER INFORMATION CONTACT: Kaitlin Johnson, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 
502-8542, [email protected].

SUPPLEMENTARY INFORMATION: 
    1. On March 18, 2021, the Commission issued a notice of inquiry 
(NOI) in this proceeding. For the reasons that we set forth below, we 
exercise our discretion to withdraw the NOI and terminate this 
rulemaking proceeding.

I. Background

    2. In the NOI, as a preliminary step, the Commission sought comment 
on whether to revise its regulations that require a Regional 
Transmission Organization (RTO) or Independent System Operator (ISO) 
(RTO/ISO) not to accept bids from an aggregator of retail customers 
(ARC) that aggregates the demand response of the customers of utilities 
that distributed more than 4 million megawatt-hours (MWh) in the 
previous fiscal year, where the relevant electric retail regulatory 
authority (RERRA) prohibits such customers' demand response to be bid 
into organized markets by an ARC (Demand Response Opt-Out).\1\
---------------------------------------------------------------------------

    \1\ See 18 CFR 35.28(g)(1)(iii) (2025).
---------------------------------------------------------------------------

    3. In issuing the NOI, the Commission stated that it had been more 
than a decade since it had established the Demand Response Opt-Out in 
Order Nos. 719 and 719-A.\2\ It noted that, since that time, there have 
been significant legal, policy, and technological developments that may 
cause it to reconsider the Demand Response Opt-Out. The Commission 
therefore sought comment on whether to revise the Commission's 
regulations to remove the Demand Response Opt-Out from its regulations.
---------------------------------------------------------------------------

    \2\ Wholesale Competition in Regions with Organized Elec. Mkts., 
Order No. 719, 125 FERC ] 61,071 (2008), order on reh'g, Order No. 
719-A, 128 FERC ] 61,059, order on reh'g, Order No. 719-B, 129 FERC 
] 61,252 (2009).
---------------------------------------------------------------------------

II. Comments 3
---------------------------------------------------------------------------

    \3\ On March 28, 2022, the Mississippi Public Service Commission 
filed a motion to lodge their initial comments and reply comments 
submitted in Docket No. EL21-12-000 in the instant proceeding, which 
were joined by the Louisiana Public Service Commission. We dismiss 
the motion because, as discussed below, we are terminating this 
proceeding.
---------------------------------------------------------------------------

    4. Several commentators urged the Commission to eliminate the 
Demand

[[Page 21284]]

Response Opt-Out.\4\ Among other arguments, nearly all of these 
commenters state that the landscape for demand response and experience 
with demand response has changed significantly enough to warrant a 
reexamination of the Demand Response Opt-Out.\5\ However, other 
commenters opposed the removal of the Demand Response Opt-Out,\6\ and 
many argued that the demand response landscape has not changed 
significantly enough to warrant the Commission's reexamination of the 
opt-out, as the original reasoning of Order No. 719 is still valid 
today.\7\
---------------------------------------------------------------------------

    \4\ Such commenters include: Association of Businesses 
Advocating Tariff Equity; Advance Energy Economy; Armada Power, LLC; 
Advanced Energy Management Alliance; Electricity Consumers Resource 
Council; Voltus, Inc.; Google; Industrial Energy Consumers of 
America; Illinois Commerce Commission; American Forest & Paper 
Association, PJM Industrial Customer Coalition, and Coalition of 
MISO Transmission Customers; Midwest Energy Consumers Group; 
Environmental Law and Policy Center, Natural Resources Defense 
Council, Sierra Club, and Sustainable FERC Project; R Street 
Institute; California Air Resources Board, the Maine Office of 
Public Advocate, and the Attorneys General of Maryland, 
Massachusetts, and Rhode Island; Ted Thomas, Chairman of the 
Arkansas Public Service Commission.
    \5\ See Advance Energy Economy Initial Comments at 1-3; 
Environmental Law and Policy Center, Natural Resources Defense 
Council, Sierra Club, and Sustainable FERC Project Initial Comments 
at 1-4; R Street Institute Initial Comments at 1, 3.
    \6\ Such commenters include: American Electric Power Service 
Corporation; American Public Power Association and the National 
Rural Electric Cooperative Association; DTE Electric Company and 
Consumers Energy Company; Edison Electric Institute; Entergy 
Services, LLC; Indiana Utility Regulatory Commission; Kansas 
Corporation Commission; Louisiana Public Service Commission and the 
Mississippi Public Service Commission; MISO; MISO Transmission 
Owners; Public Service Commission of the State of Missouri; National 
Association of Regulatory Utility Commissioners; North Carolina 
Utilities Commission; Organization of MISO States; and Southern 
Pioneer Electric Company.
    \7\ See Entergy Services, LLC Initial Comments at 1-3; Louisiana 
Public Service Commission and the Mississippi Public Service 
Commission Initial Comments at 1-3; Public Service Commission of the 
State of Missouri Initial Comments at 3-4, 12-21.
---------------------------------------------------------------------------

III. Discussion

    5. Upon further consideration and after review of the comments that 
the Commission received in response to the NOI, we withdraw the NOI and 
terminate this rulemaking proceeding. We appreciate the feedback that 
the Commission received in response to the NOI. After careful 
consideration of the record, we agree with commenters that raised 
concerns regarding the removal of the Demand Response Opt-Out, stating 
that the demand response landscape has not changed significantly enough 
to warrant such action by the Commission at this time. We also note the 
strong opposition to removing the state opt-out expressed by state 
organizations such as the National Association of Regulatory Utility 
Commissioners (NARUC) and regional state regulatory associations. For 
these reasons, and to eliminate any uncertainty as to whether the 
Commission still intends to move forward with this proposal, the 
Commission exercises its discretion to withdraw the NOI and terminate 
this rulemaking proceeding. While withdrawing the NOI, we recognize the 
value that demand response can bring to the markets and encourage the 
development of demand response programs within the relevant regulatory 
structures. Further, in response to the dissent, we do not believe that 
terminating the instant proceeding eliminates options for 
interconnecting flexible large loads quickly and cost-effectively, and 
we clarify that our action today in no way prejudges the outcome of the 
pending proceeding on the Interconnection of Large Loads to the 
Interstate Transmission System.\8\
---------------------------------------------------------------------------

    \8\ Interconnection of Large Loads to the Interstate 
Transmission System, Advance Notice of Proposed Rulemaking (Oct. 23, 
2025) (Docket No. RM26-4-000).
---------------------------------------------------------------------------

    The Commission orders:
    The notice of inquiry is hereby withdrawn and Docket No. RM21-14-
000 is hereby terminated. By direction of the Commission. Commissioner 
Rosner is dissenting with a separate statement attached. Commissioner 
Chang is concurring with a separate statement attached.

    Issued: April 16, 2026.
Carlos D. Clay,
Deputy Secretary.

United States of America

Federal Energy Regulatory Commission

Participation of Aggregators of Retail Demand Response Customers in 
Markets Operated by Regional Transmission Organizations and Independent 
System Operators

Docket No. RM21-14-000
(Issued April 16, 2026)

ROSNER, Commissioner, dissenting:

    1. I dissent from today's order because it limits consideration of 
options at a time when I believe we need every tool in the toolbox to 
meet the electricity demand growth our country is experiencing. My 
primary motivation for writing separately is not to say whether my 
colleagues are right or wrong to close this dormant proceeding, but 
instead to elevate the issue of demand response and the important 
optionality it offers for quickly connecting new customers to the grid 
and balancing the affordability issues that are front of mind.
    2. The electricity system is at a turning point. New electric 
customers can individually use as much energy as a city. There are two 
primary ways to meet this growth and power these new, large customers. 
One path is to enable faster and cheaper grid integration by offering 
the option to use load flexibility or behind the meter generation, 
which can reduce impacts on the transmission system, require 
significantly less infrastructure, and lower costs. The other path is 
to rely on only the status quo, which can be time-intensive, require 
significant new infrastructure, and increase costs. While I believe 
strongly in building out needed energy infrastructure, we must also 
ensure that all options, including demand response, are available.
    3. I believe the Commission should consider whether demand response 
\9\ provided by customers that individually consume hundreds of 
megawatts or more is best enabled through a patchwork of programs or by 
a single RTO/ISO-wide program. With the benefit of hindsight, it is 
obvious that the Commission was not envisioning large retail customers 
like data centers when it first established the demand response opt-out 
in 2008.\10\ Nor could the Commission have been aware of how 
technologies that allow large loads to deliver meaningful grid 
flexibility with minimal impacts on the end-use customer would 
proliferate.\11\ Moreover, in the intervening years, courts have 
affirmed the Commission's exclusive

[[Page 21285]]

authority to determine who may participate in wholesale markets.\12\
---------------------------------------------------------------------------

    \9\ I note that the Commission considers both load flexibility 
and behind-the-meter resources that do not inject to be demand 
response, so maintaining the current opt-out presents a barrier to 
both approaches. See Elec. Storage Participation in Mkts. Operated 
by Reg'l Transmission Orgs. & Indep. Sys. Operators, Order No. 841, 
162 FERC ] 61,127, at P 32 (2018), order on reh'g, Order No. 841-A, 
167 FERC ] 61,154 (2019), aff'd sub nom. Nat'l Ass'n of Regul. Util. 
Comm'rs v. FERC, 964 F.3d 1177 (D.C. Cir. 2020) (NARUC v. FERC) 
(``[W]e have previously found that behind-the-meter resources that 
do not inject electric energy onto the grid are considered demand 
response.'').
    \10\ See Order No. 719, 125 FERC ] 61,071, at PP 154-56 (2008).
    \11\ See, e.g., Philip Colangelo et al., Turning AI Data Centers 
into Grid-Interactive Assets: Results from a Field Demonstration in 
Phoenix, Arizona (2025), https://arxiv.org/abs/2507.00909 
(``Conducted at a 256-GPU cluster running representative AI 
workloads within a commercial, hyperscale cloud data center in 
Phoenix, Arizona, the trial achieved a 25% reduction in cluster 
power usage for three hours during peak grid events while 
maintaining AI quality of service (QoS) guarantees.'').
    \12\ See NARUC v. FERC, 964 F.3d at 1187 (``[B]ecause FERC has 
the exclusive authority to determine who may participate in the 
wholesale markets, the Supremacy Clause . . . requires that States 
not interfere.''); see also FERC v. Elec. Power Supply Ass'n, 577 
U.S. 260, 278 (2016) (``[W]e now approve, a common-sense 
construction of the FPA's language, limiting FERC's `affecting' 
jurisdiction to rules or practices that `directly affect the 
[wholesale] rate.' . . . [T]he rules governing wholesale demand 
response programs meet that standard with room to spare.'' 
(footnotes omitted)).
---------------------------------------------------------------------------

    4. Every day, we see more evidence that both load flexibility and 
bring your own generation are essential to efficiently integrating new 
large loads like data centers.\13\ I would have preferred to probe 
whether it would be appropriate to revive this proceeding in a way that 
is forward-looking and tailored to the needs of the grid in 2026. 
Similarly, I would like to gather further record on how the 
perspectives of our state regulator colleagues may have evolved since 
2021. I have extraordinary respect for their perspectives, in 
particular, given that they regulate the retail rates ultimately 
charged to large load customers and have significant experience 
integrating large loads.\14\
---------------------------------------------------------------------------

    \13\ See, e.g., PJM Interconnection, L.L.C., 193 FERC ] 61,217, 
at P 77 (2025) (``[O]ffering non-capacity backed transmission 
service on a permanent basis would allow PJM to capture the benefits 
of co-located facilities, serving the same amount of total load at 
lower cost, with less transmission infrastructure and fewer capacity 
resources.''); Carlo Brancucci et al., Flexible Data Centers: A 
Faster, More Affordable Path to Power (2025), https://www.camus.energy/flexible-data-center-report (finding that flexible 
data centers can connect 3-5 years faster, mitigate new system 
buildout, and shift remaining costs onto the data center); Ryan 
Hledik et al., The Untapped Grid: How Better Utilization of the 
Power System Can Improve Energy Affordability, Brattle (2026), 
https://www.brattle.com/wp-content/uploads/2026/03/The-Untapped-Grid-Mar-2026.pdf (finding that improving system utilization 
accelerates speed to market for new loads, avoids shifting costs to 
other consumers, and mitigates stranded asset risks).
    \14\ As of March 2026, 20 states had approved at least one large 
load tariff, and another nine states had pending large load tariffs. 
See Edison Electric Institute, Comments, Docket No. RM26-4-000, at 2 
(filed Mar. 12, 2026).
---------------------------------------------------------------------------

    5. All of this said, I want to emphasize that I share my fellow 
Commissioners' desire to close dormant proceedings. Leaving dormant 
regulatory proceedings open for years increases regulatory uncertainty 
and makes investing in new energy resources riskier and more expensive. 
That is a real cost that I agree this Commission must consider. But 
meeting the current moment also demands that we give full consideration 
to load flexibility, and I look forward to working with my colleagues 
on this topic as the Commission embarks upon the reforms needed to 
ensure the timely and orderly interconnection of large loads to the 
transmission system.\15\
---------------------------------------------------------------------------

    \15\ See Interconnection of Large Loads to the Interstate 
Transmission Sys., 195 FERC ] 61,045 (2026) (Order Regarding Intent 
to Act).
---------------------------------------------------------------------------

    For these reasons, I respectfully dissent.


David Rosner,
Commissioner.

United States of America

Federal Energy Regulatory Commission

Participation of Aggregators of Retail Demand Response Customers in 
Markets Operated by Regional Transmission Organizations and Independent 
System Operators

Docket No. RM21-14-000
(Issued April 16, 2026)

CHANG, Commissioner, concurring:

    1. The Commission's order today closes a Notice of Inquiry (NOI) on 
removing the so-called ``Demand Response Opt-Out,'' which allows state 
regulators to place limitations on the participation of third-party 
demand response aggregators in wholesale markets. The Demand Response 
Opt-Out was included in Order No. 719 to balance the competing 
interests of opening wholesale markets to demand response and 
respecting state and local regulatory concerns relating to the 
operation of existing retail demand response programs, regulatory 
burdens, and jurisdictional challenges.\1\ While the Demand-Response 
Opt-Out may need to be re-examined in the future, maintaining the 
status quo strikes the right balance today.\2\ Thus, I am persuaded 
that the Commission should close this NOI.
---------------------------------------------------------------------------

    \1\ Wholesale Competition in Regions with Organized Elec. Mkts., 
Order No. 719, 125 FERC ] 61,071, at PP 154-56 (2008), order on 
reh'g, Order No. 719-A, 128 FERC ] 61,059, order on reh'g, Order No. 
719-B, 129 FERC ] 61,252 (2009).
    \2\ While referred to as an ``opt out,'' Order No. 719 does not 
create a binary choice for state regulators with regard to the 
participation of third-party demand response aggregators in 
wholesale markets. Instead, Order No. 719 allows states to place 
conditions on participation of third-party aggregators, which may 
extend to disallowing participation for some or all customer 
classes. Some states that have chosen to ``opt out'' in fact do 
allow third-party demand response aggregation, but subject those 
programs to state regulations; or they may specify the customer 
classes that may take part in third-party aggregation programs. See, 
e.g., In the Matter of the Establishment of a Working Case Re: FERC 
Order No. 2222 Re: Participation of Distributed Energy Resource 
Aggregators in Markets Operated by Regional Trans. Organizations and 
Indep. Sys. Operators, Docket No. EW-2021-0267 (Missouri Pub. Serv. 
Comm'n Oct. 12, 2023) (allowing third-party aggregators to bid 
demand response into wholesale markets for commercial and industrial 
customers with demand of at least 100 kW); Indiana Util, Reg. Comm' 
Initial Comments at 9 (describing the ability of third party 
aggregators to participate in wholesale market through a retail 
tariff).
---------------------------------------------------------------------------

    2. However, demand-side resources are underrepresented in the 
wholesale markets, and I write separately to emphasize constructive 
steps that the Commission, states, market operators, and demand 
response providers can take to improve demand-side participation in 
wholesale markets.
    3. Additional demand response, including from grid-interactive 
buildings, flexible large loads, and industrial customers, has the 
potential to significantly help meet the country's load growth and 
resource adequacy challenges.\3\ But despite a clear reliability 
imperative and strong economic signals from high market prices, the 
amount of demand response participating in wholesale markets is limited 
today. In the PJM Interconnection, L.L.C. (PJM) market, the last 
capacity auction cleared half of the amount of demand response compared 
to the 2014/2015 delivery period.\4\ Even with the issuance of Order 
No. 745,\5\ Commission-jurisdictional markets reflect very little 
economic demand response participation in the energy and ancillary 
services markets.
---------------------------------------------------------------------------

    \3\ See U.S. Dept. of Energy, A National Roadmap for Grid-
Interactive Efficient Buildings (May 17, 2021), https://gebroadmap.lbl.gov/A%20National%20Roadmap%20for%20GEBs%20-%20Final.pdf; Nicholas Institute for Energy, Environment, & 
Sustainability, Rethinking Load Growth: Assessing the Potential for 
Integration of Large Flexible Loads in US Power Systems (Feb. 2025), 
https://nicholasinstitute.duke.edu/publications/rethinking-load-growth; U.S. Dept. of Energy, Demand Response in Industrial 
Facilities (2022), https://betterbuildingssolutioncenter.energy.gov/sites/default/files/attachments/Demand%20Response%20in%20Industrial%20Facilities_Final.pdf.
    \4\ Compare PJM, 2014/2015 RPM Base Residual Auction Results, 
https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/20110513-2014-15-base-residual-auction-report.pdf with PJM, 2027/
2028 Base Residual Auction Results, https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/2027-2028/2027-2028-bra-report.pdf.
    \5\ Order No. 745 established rules governing demand response 
participation in organized wholesale energy markets, including that 
demand response resources will be compensated at prevailing 
locational marginal prices, subject to certain conditions. Demand 
Response Compensation in Organized Wholesale Energy Mkts., Order No. 
745, 134 FERC ] 61,187, order on reh'g & clarification, Order No. 
745-A, 137 FERC ] 61,215 (2011), reh'g denied, Order No. 745-B, 138 
FERC ] 61,148 (2012), vacated sub nom. Elec. Power Supply Ass'n v. 
FERC, 753 F.3d 216 (D.C. Cir. 2014), rev'd & remanded sub nom. FERC 
v. Elec. Power Supply Ass'n, 136 S.Ct. 760 (2016).
---------------------------------------------------------------------------

    4. To increase demand response participation, the Commission, state 
regulators, and market operators need to collaborate on market designs 
and participation models that balance: (1) practical limitations on 
customers'

[[Page 21286]]

ability and willingness to curtail demand, and (2) confidence that 
system operators can rely on demand response resources to respond 
quickly and predictably when called. This means that state and federal 
regulators as well as market operators need to engage more to 
understand and resolve friction that might arise when demand-side 
resources are integrated into market structures. Such frictions may 
involve end users' metering requirements, parameters around billing 
periods, or frequency of calls on customers to curtail their load.
    5. I am heartened by the development of new retail demand response 
proposals and programs across various states,\6\ including in states 
that have placed limitations on the wholesale market participation of 
third-party aggregators.\7\ I look forward to seeing them integrated 
into the wholesale markets to maximize their value for the whole 
system. Further, I will continue to look for opportunities--whether in 
proceedings before the Commission or other forums--to better realize 
the potential contributions from demand-side resources, while working 
collaboratively with our state colleagues to support their deployment.
---------------------------------------------------------------------------

    \6\ For example, several states have announced virtual power 
plants, including a program in Virginia targeting a capacity of 450 
MW. See Utility Dive, Viginia utility-scale VPP pilot mandate is 
first amid national push (May 12, 2025), https://www.utilitydive.com/news/virginia-leads-with-utility-scale-vpp-pilot-amid-national-push/747770/.
    \7\ For example, Google has committed to utility-run demand 
response programs in Indiana, Arkansas and Minnesota, which place 
restrictions on the ability of third party aggregators to 
participate in wholesale markets. Google, A new milestone for smart, 
affordable electricity growth (Mar. 19, 2026), https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/demand-response-data-center-milestone/.
---------------------------------------------------------------------------

    For these reasons, I respectfully concur.

Judy W. Chang,
Commissioner.

[FR Doc. 2026-07713 Filed 4-20-26; 8:45 am]
BILLING CODE 6717-01-P