[Federal Register Volume 91, Number 44 (Friday, March 6, 2026)]
[Notices]
[Pages 11092-11101]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2026-04474]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 70-7033; CLI-26-3]


Global Laser Enrichment, LLC; (Paducah Laser Enrichment 
Facility); Notice of Receipt of Application for License; Notice of 
Consideration of Issuance of License; Notice of Hearing and Commission 
Order; Opportunity To Request a [Contested] Hearing; and Order Imposing 
Procedures for Access to Sensitive Unclassified Non-Safeguards 
Information and Safeguards Information for Contention Preparation

    Commissioners: Ho. K. Nieh, Chairman; David A. Wright; Bradley R. 
Crowell; Matthew J. Marzano; Douglas W. Weaver.

(i) Receipt of Application and Availability of Documents

    The U.S. Nuclear Regulatory Commission (NRC) has received an 
application from Global Laser Enrichment, LLC (GLE) for a license to 
possess and use special nuclear material for the purpose of 
constructing and operating a uranium enrichment facility in McCracken 
County, Kentucky.\1\ GLE is a Delaware limited liability company that 
is indirectly owned, through subsidiaries, by parent companies Silex 
Systems Limited, an Australian company with a 51 percent ownership 
interest in GLE, and Cameco Corporation, a Canadian corporation with a 
49 percent ownership interest in GLE. The requested license would 
authorize GLE to possess equipment capable of enriching uranium, to 
construct and operate a uranium enrichment facility, and to receive 
title to, own, acquire, receive, possess, use, transfer, and/or deliver 
source material, special nuclear material, and byproduct material as 
specified in the license for a facility that uses laser-based isotope 
separation technology to enrich uranium. The facility would be known as 
the Paducah Laser Enrichment Facility (PLEF) and would be located 
adjacent to the former Paducah Gaseous Diffusion Plant.\2\ The 
requested license would authorize the PLEF to re-enrich depleted 
uranium hexafluoride (UF6) tails and enrich natural-grade 
UF6 to a maximum of 8-weight percent uranium-235.
---------------------------------------------------------------------------

    \1\ Letter from Tim Knowles, Global Laser Enrichment, LLC, to 
NRC Document Control Desk (June 27, 2025) (ML25179A001).
    \2\ Id. at 1.
---------------------------------------------------------------------------

    In July 2024, GLE requested that the NRC staff grant an exemption 
from timing requirements set forth in 10 CFR 51.60(a) to allow 
submittal of its environmental report in advance of the remainder of 
its application.\3\ The NRC staff granted GLE's requested exemption.\4\ 
Later that year, GLE submitted an initial version of its environmental 
report and thereafter submitted supplements to its environmental 
report.\5\ On June 27, 2025, GLE submitted its safety and safeguards 
analysis report, which it later supplemented by a revised affidavit.\6\ 
GLE requested an exemption from the requirements of 10 CFR 70.22(m), 
which requires that certain license applications submitted under Part 
70 include a description of the applicant's security program to protect 
classified matter and equipment.\7\ The NRC staff granted GLE a 
temporary exemption from the requirements of 10 CFR 70.22(m), allowing 
GLE until March 1, 2026, to submit the portions of the application 
required by section 70.22(m).\8\ On August 4, 2025, the NRC staff 
informed GLE of its determination that ``the application provides 
sufficient information to proceed with a detailed technical review'' 
and formally accepted the application for review.\9\
---------------------------------------------------------------------------

    \3\ Letter from Tim Knowles, Global Laser Enrichment, LLC, to 
NRC Document Control Desk (July 2, 2024) (ML24193A060).
    \4\ Letter from Samantha Lav, U.S. Nuclear Regulatory 
Commission, to Tim Knowles, Global Laser Enrichment, LLC (Aug. 19, 
2024) (ML24184B971), Encl., ``The Safety Evaluation Report for the 
Global Laser Enrichment Exemption to Bifurcate Submittal of the 
Environmental and Safety and Safeguards Portion of the License 
Application for the Paduch Laser Enrichment Facility,'' (undated) 
(ML24184B972).
    \5\ Letter from Tim Knowles, Global Laser Enrichment, LLC, to 
NRC Document Control Desk (Dec. 30, 2024) (ML24365A110), Encl. 1, 
``Environmental Report for the Paducah Laser Enrichment Facility,'' 
(Dec. 31, 2024) (ML24365A111); Letter from Tim Knowles, Global Laser 
Enrichment, LLC, to NRC Document Control Desk (Apr. 7, 2025) 
(ML25097A172 (package)); Letter from Tim Knowles, Global Laser 
Enrichment, LLC, to NRC Document Control Desk (June 13, 2025) 
(ML25164A077 (package)).
    \6\ Letter from Tim Knowles, Global Laser Enrichment, LLC, to 
NRC Document Control Desk (June 27, 2025) (ML25179A000 (package)); 
Letter from Tim Knowles, Global Laser Enrichment, LLC, to NRC 
Document Control Desk (July 14, 2025) (ML25195A093).
    \7\ Letter from Tim Knowles, Global Laser Enrichment, LLC, to 
NRC Document Control Desk (June 26, 2025) (ML25177D049).
    \8\ Letter from Samantha Lav, U.S. Nuclear Regulatory 
Commission, to Tim Knowles, Global Laser Enrichment, LLC (July 23, 
2025) (ML25182A184 (package)).
    \9\ Letter from Samantha Lav, U.S. Nuclear Regulatory 
Commission, to Timothy Knowles, Global Laser Enrichment, LLC (Aug. 
4, 2025), at 1 (ML25202A201).
---------------------------------------------------------------------------

    The NRC staff will perform a detailed technical review of the 
application and prepare a safety evaluation report (SER) that addresses 
the findings required by the Atomic Energy Act of 1954, as amended 
(AEA), and the NRC's regulations concerning the public health and 
safety and common defense and security. Additionally, in accordance 
with section 193 of the AEA, the National Environmental Policy Act of 
1969 (NEPA), and the NRC's regulations in 10 CFR part 51, the NRC staff 
will prepare an environmental impact statement (EIS) before the hearing 
on the issuance of the license is completed.\10\
---------------------------------------------------------------------------

    \10\ See Global Laser Enrichment, LLC; Paducah Laser Enrichment 
Facility; Notice of Intent to Conduct Scoping Process and Prepare 
Environmental Impact Statement, 90 FR 42988 (Sept. 5, 2025).
---------------------------------------------------------------------------

    Interested persons may obtain publicly available documents relating 
to this application online in the Agencywide Documents Access and 
Management System (ADAMS) Public Documents collection at https://www.nrc.gov/reading-rm/adams.html.

[[Page 11093]]

Interested persons may also examine and order copies of publicly 
available documents at the NRC's Public Document Room (PDR), which is 
open by appointment. To make an appointment to visit the PDR, please 
send an email to [email protected] or call 1-800-397-4209 or 301-
415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through 
Friday, except Federal holidays. When available, the NRC staff's SER 
and EIS, except for portions subject to withholding from public 
inspection in accordance with 10 CFR 2.390, will also be placed in the 
PDR and in ADAMS. Copies of correspondence between the NRC and GLE and 
transcripts of prehearing conferences and hearings, except for portions 
subject to withholding from public inspection in accordance with 10 CFR 
2.390, similarly will be made available to the public.

II. Notice of Mandatory Hearing

    A. Pursuant to 10 CFR 70.23a and Section 193 of the AEA, as amended 
(42 U.S.C. 2243), an uncontested mandatory hearing will be conducted 
following completion of the NRC staff's safety evaluation and 
environmental review of the license application. The NRC staff 
currently anticipates completing the SER in January 2027 and finalizing 
the EIS in September 2026.\11\ This hearing will be held under the 
authority of sections 53, 63, 189, 191, and 193 of the AEA. The 
applicant and the NRC staff are parties to the hearing. This mandatory 
hearing is distinct from the contested hearing opportunity discussed 
below in Section III, ``Opportunity to Request a Hearing and Petition 
for Leave to Intervene.''
---------------------------------------------------------------------------

    \11\ See id. at 2.
---------------------------------------------------------------------------

    B. The mandatory hearing will be conducted by an Atomic Safety and 
Licensing Board (Licensing Board), designated by the Chief 
Administrative Judge of the Atomic Safety and Licensing Board Panel, 
under 10 CFR part 2, subparts A, C, G, and, to the extent that 
classified information becomes involved, Subpart I, subject to the 
following exceptions and supplemental procedures:
    1. Unless a party requests an oral evidentiary hearing, all 
evidence will be presented in written form only;
    2. Neither party will be required to file proposed findings of fact 
and conclusions of law, although the parties will have the option to do 
so;
    3. The NRC staff shall file initial written testimony on the docket 
for the proceeding within seven days after the NRC staff has issued 
both the final safety evaluation and final NEPA document.
    4. The NRC staff's initial written testimony should, at a minimum:
    a. Address each of the findings necessary for issuance of the 
license and provide an adequate basis for the Licensing Board to 
conclude whether each of these findings can be made. The testimony 
should not recap all matters in the safety or environmental review 
process, particularly routine aspects of the review where there was no 
actual complication or controversy. Rather, the testimony should be 
focused on non-routine matters. In focusing on non-routine matters, the 
areas of particular importance in supporting the safety and 
environmental findings include any unique features of the facility or 
novel issues that arose as part of the review process.
    b. Include other aspects of the staff's review that are important 
for the Licensing Board to make its initial decision but are not 
necessarily tied to specific findings. For instance, if any exemption 
requests or rulemakings, including revisions to guidance documents 
(e.g., regulatory guides or standard review plans), are ongoing, the 
staff's testimony should include a brief summary of any issues that may 
be relevant to the Licensing Board's decision.
    c. Reference the following documents and include them as enclosures 
to be entered into the record of the mandatory hearing as exhibits:
    i. The license application and all supplements;
    ii. The Final Safety Evaluation Report and all supplements;
    iii. The Final Environmental Impact Statement and all supplements; 
and
    iv. The proposed license or permit.
    5. Following receipt of the NRC staff's initial written testimony, 
the Licensing Board shall hold a prehearing conference that includes 
representatives of the NRC staff and the applicant to address the 
scheduling of subsequent mandatory hearing activities and any other 
administrative matters, including establishing timeframes for:
    a. the Licensing Board to pose written questions, if any, to the 
parties,
    b. the parties to provide written responses to any such questions,
    c. the applicant to file any separate written testimony of its own, 
should the applicant choose to do so,
    d. a party to request that the Licensing Board hold an oral 
evidentiary hearing,
    e. the parties to file proposed findings of fact and conclusions of 
law, if the parties choose to do so, and
    f. the parties, if they decide not to file proposed findings of 
fact and conclusions of law, to notify the Board of that decision.
    6. The resulting schedule of hearing activities will be publicly 
available in an Initial Scheduling Order issued by the Board and 
located in the Electronic Hearing Docket.
    7. Interested States, local governmental bodies, and Federally-
recognized Indian Tribes may file written statements within fourteen 
days after the NRC staff files its initial written testimony.
    a. Subject to the exception discussed in Subpart II.B.7.e, these 
written statements may address any issues or questions that the State, 
local governmental body, or Federally-recognized Indian Tribe wishes 
the Licensing Board to give particular attention to as part of the 
mandatory hearing process.
    b. The statements may be accompanied by supporting documentation.
    c. Any statements and supporting documentation, if received by the 
NRC using the agency's E-Filing system by the deadline indicated above, 
will be made part of the record of the proceeding.
    d. The Licensing Board will use such statements and documents as 
appropriate to inform its written questions to the NRC staff and the 
applicant and its decision following the hearing.
    e. States, local governmental bodies, and Federally-recognized 
Indian Tribes should be aware that this mandatory hearing is separate 
and distinct from the NRC's contested hearing process. Issues within 
the scope of contentions that have been admitted in a contested 
proceeding for the application are outside the scope of the mandatory 
hearing. In addition, while States, local governmental bodies, and 
Federally-recognized Indian Tribes participating as described above may 
take any position they wish, or no position at all, with respect to 
issues regarding the application or the NRC staff's associated 
environmental review that do fall within the scope of the mandatory 
hearing (i.e., issues that are not within the scope of admitted 
contentions), they should be aware that many of the procedures and 
rights applicable to the NRC's contested hearing process, due to the 
inherently adversarial nature of such proceedings, are not available 
with respect to this mandatory hearing. Participation in the NRC's 
contested hearing process is governed by 10 CFR 2.309 (for persons or 
entities, including States, local governmental bodies, and Federally-
recognized Indian Tribes, seeking to file contentions of their own)

[[Page 11094]]

and 10 CFR 2.315(c) (for interested States, local government bodies, 
and Federally-recognized Indian Tribes seeking to participate with 
respect to contentions filed by others).
    f. Participation in this mandatory hearing does not affect a 
State's, local governmental body's, or Federally-recognized Indian 
Tribe's right to participate in the separate contested hearing process. 
Similarly, if an interested State's, local governmental body's, or 
Federally-recognized Indian Tribe's request to participate in a 
contested hearing under 10 CFR 2.315(c) is denied or dismissed, that 
denial or dismissal does not affect the State's, local governmental 
body's, or Federally-recognized Indian Tribe's opportunity to 
participate in the mandatory hearing by filing written statements as 
described above.
    C. The matters of fact and law to be considered are whether the 
application satisfies the standards set forth in this Notice and 
Commission Order and the applicable standards in 10 CFR parts 30, 40, 
and 70, and whether the requirements of NEPA and the NRC's implementing 
regulations in 10 CFR part 51 have been met.
    D. The Licensing Board will determine the following without 
conducting a de novo evaluation of the application: (1) whether the 
application and record of the proceeding contain sufficient information 
to support license issuance and whether the NRC staff's review of the 
application has been adequate to support findings to be made by the 
Director of the Office of Nuclear Materials Safety and Safeguards with 
respect to the matters set forth in paragraph C of this section; and 
(2) whether the review conducted by the NRC staff pursuant to 10 CFR 
part 51 has been adequate.
    E. In the initial decision for the mandatory hearing the Licensing 
Board will, in accordance with Subpart A of 10 CFR part 51: determine 
whether the requirements of sections 102(2)(A), (C), and (E) of NEPA 
and Subpart A of 10 CFR part 51 have been complied with in the 
proceeding; independently consider the final balance among conflicting 
factors contained in the record of the proceeding with a view to 
determining the appropriate action to be taken; and determine, after 
weighing the environmental, economic, technical, and other benefits 
against the environmental and other costs, and considering reasonable 
alternatives, whether a license should be issued, denied, or 
appropriately conditioned to protect environmental values.
    F. If there is no contested portion of this licensing proceeding, 
the Board shall issue its initial decision in the mandatory hearing 
within three months after the date on which the staff filed its initial 
written testimony. If there is a contested portion of this licensing 
proceeding, the Board shall issue its initial decision within three 
months after the date on which the staff filed its initial written 
testimony in the mandatory hearing, or within one month after the 
completion of the contested portion of the proceeding, whichever is 
later.
    G. Pursuant to 10 CFR part 2, subparts C and G, a contested hearing 
shall be conducted by a Licensing Board appointed by the Chief 
Administrative Judge of the Atomic Safety and Licensing Board Panel. 
Notice as to the membership of the Licensing Board will be published in 
the Federal Register at a later date.
    H. If the proceeding becomes a contested proceeding, the Licensing 
Board shall make findings of fact and conclusions of law on admitted 
contentions. With respect to matters set forth in paragraph C of this 
section, but not covered by admitted contentions, the Licensing Board 
will make the determinations set forth in paragraph D without 
conducting a de novo evaluation of the application.
    I. Regardless of whether the proceeding is contested or 
uncontested, the Licensing Board will, in the initial decision, in 
accordance with Subpart A of 10 CFR part 51: determine whether the 
requirements of sections 102(2)(A), (C), and (E) of NEPA and Subpart A 
of 10 CFR part 51 have been complied with in the proceeding; 
independently consider the final balance among conflicting factors 
contained in the record of the proceeding with a view to determining 
the appropriate action to be taken; and determine, after weighing the 
environmental, economic, technical, and other benefits against the 
environmental and other costs, and considering reasonable alternatives, 
whether a license should be issued, denied, or appropriately 
conditioned to protect environmental values.

I. Opportunity To Request a Hearing and Petition for Leave To Intervene

    Within 60 days after the date of publication of this notice, any 
person (petitioner) whose interest may be affected by this action may 
file a request for a hearing and petition for leave to intervene 
(petition) with respect to the action. Petitions shall be filed in 
accordance with the Commission's ``Agency Rules of Practice and 
Procedure'' in 10 CFR part 2. Interested persons should consult 10 CFR 
2.309. If a petition is filed, the presiding officer will rule on the 
petition and, if appropriate, a notice of a hearing will be issued.
    Petitions must be filed no later than 60 days from the date of 
publication of this notice in accordance with the filing instructions 
in the ``Electronic Submissions (E-Filing)'' section of this document. 
Petitions and motions for leave to file new or amended contentions that 
are filed after the 60-day deadline will not be entertained absent a 
determination by the presiding officer that the filing demonstrates 
good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i) 
through (iii).
    A State, local governmental body, Federally-recognized Indian 
Tribe, or designated agency thereof, may submit a petition to the 
Commission to participate as a party under 10 CFR 2.309(h) no later 
than 60 days from the date of publication of this notice. 
Alternatively, a State, local governmental body, Federally-recognized 
Indian Tribe, or agency thereof may participate as a non-party under 10 
CFR 2.315(c).
    For information about filing a petition and about participation by 
a person not a party under 10 CFR 2.315, see ADAMS Accession No. 
ML20340A053 (https://adamswebsearch2.nrc.gov/webSearch2/main.jsp?AccessionNumber=ML20340A053) and the NRC's public website at 
https://www.nrc.gov/about-nrc/regulatory/adjudicatory/hearing.html#participate.

II. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings, including 
documents filed by an interested State, local governmental body, 
Federally-recognized Indian Tribe, or designated agency thereof that 
requests to participate under 10 CFR 2.315(c), must be filed in 
accordance with 10 CFR 2.302. The E-Filing process requires 
participants to submit and serve all adjudicatory documents over the 
internet, or in some cases, to mail copies on electronic storage media, 
unless an exemption permitting an alternative filing method, as further 
discussed, is granted. Detailed guidance on electronic submissions is 
located in the ``Guidance for Electronic Submissions to the NRC'' 
(ADAMS Accession No. ML13031A056) and on the NRC's public website at 
https://www.nrc.gov/site-help/e-submittals.html.
    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at [email protected], or by 
telephone at 301-415-1677, to: (1)

[[Page 11095]]

request a digital identification (ID) certificate, which allows the 
participant (or its counsel or representative) to digitally sign 
submissions and access the E-Filing system for any proceeding in which 
it is participating; and (2) advise the Secretary that the participant 
will be submitting a petition or other adjudicatory document (even in 
instances in which the participant, or its counsel or representative, 
already holds an NRC-issued digital ID certificate). Based upon this 
information, the Secretary will establish an electronic docket for the 
proceeding if the Secretary has not already established an electronic 
docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public website at https://www.nrc.gov/site-help/e-submittals/getting-started.html. After a digital ID certificate is 
obtained and a docket created, the participant must submit adjudicatory 
documents in Portable Document Format. Guidance on submissions is 
available on the NRC's public website at https://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is considered complete at the 
time the document is submitted through the NRC's E-Filing system. To be 
timely, an electronic filing must be submitted to the E-Filing system 
no later than 11:59 p.m. ET on the due date. Upon receipt of a 
transmission, the E-Filing system time-stamps the document and sends 
the submitter an email confirming receipt of the document. The E-Filing 
system also distributes an email that provides access to the document 
to the NRC's Office of the General Counsel and any others who have 
advised the Office of the Secretary that they wish to participate in 
the proceeding, so that the filer need not serve the document on those 
participants separately. Therefore, applicants and other participants 
(or their counsel or representative) must apply for and receive a 
digital ID certificate before adjudicatory documents are filed to 
obtain access to the documents via the E-Filing system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic 
Filing Help Desk through the ``Contact Us'' link located on the NRC's 
public website at https://www.nrc.gov/site-help/e-submittals.html, by 
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m. 
and 6 p.m., ET, Monday through Friday, excluding government holidays.
    Participants who believe that they have good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
stating why there is good cause for not filing electronically and 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted in accordance with 10 CFR 
2.302(b)-(d). Participants filing adjudicatory documents in this manner 
are responsible for serving their documents on all other participants. 
Participants granted an exemption under 10 CFR 2.302(g)(2) must still 
meet the electronic formatting requirement in 10 CFR 2.302(g)(1), 
unless the participant also seeks and is granted an exemption from 10 
CFR 2.302(g)(1).
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket, which is publicly available at https://adams.nrc.gov/ehd, unless excluded pursuant to an order of the 
presiding officer. If you do not have an NRC-issued digital ID 
certificate as described above, click ``cancel'' when the link requests 
certificates and you will be automatically directed to the NRC's 
electronic hearing dockets where you will be able to access any 
publicly available documents in a particular hearing docket. 
Participants are requested not to include personal privacy information 
such as social security numbers, home addresses, or personal phone 
numbers in their filings unless an NRC regulation or other law requires 
submission of such information. With respect to copyrighted works, 
except for limited excerpts that serve the purpose of the adjudicatory 
filings and would constitute a Fair Use application, participants 
should not include copyrighted materials in their submission.

III. Commission Guidance

a. Licensing Board Determination of Contentions

    The Licensing Board shall issue a decision on the admissibility of 
contentions no later than [150 days from the date of publication of 
this Federal Register notice].

b. Novel Legal Issues

    If rulings on petitions, contention admissibility, or admitted 
contentions, raise novel legal or policy questions, the Commission will 
provide early guidance and direction on the treatment and resolution of 
such issues. Accordingly, the Commission directs the Licensing Board to 
promptly certify to the Commission in accordance with 10 CFR 2.319(l) 
and 2.323(f) all novel legal or policy issues that would benefit from 
early Commission consideration should such issues arise in this 
proceeding.

c. Discovery Management

    (1) All parties, except the NRC staff, shall make the mandatory 
disclosures required by 10 CFR 2.704(a) and (b) within 45 days of the 
issuance of the Licensing Board order admitting contentions.
    (2) The Licensing Board, consistent with fairness to all parties, 
should narrow the issues requiring discovery and limit discovery to no 
more than one round for admitted contentions.
    (3) All discovery against the NRC staff shall be governed by 10 CFR 
2.336(b) and 2.709. The NRC staff shall comply with 10 CFR 2.336(b) no 
later than 30 days after the Licensing Board order admitting 
contentions and shall update the information at the same time as the 
issuance of the SER or the Final Environmental Impact Statement (FEIS), 
and, subsequent to the publication of the SER and FEIS, as otherwise 
required by the Commission's regulations. Discovery under 10 CFR 2.709 
shall not commence until the issuance of the particular document, i.e., 
SER or EIS, unless the Licensing Board, in its discretion, finds that 
commencing discovery against the NRC staff on safety issues before the 
SER is issued, or on environmental issues before the FEIS is issued 
will expedite the hearing without adversely affecting the staff's 
ability to complete its evaluation in a timely manner.
    (4) No later than 30 days before the commencement of the hearing at 
which an issue is to be presented, all parties other than the NRC staff 
shall make the pretrial disclosures required by 10 CFR 2.704(c).

d. Hearing Schedule

    In the interest of providing a fair hearing, avoiding unnecessary 
delays in NRC's review and hearing process, and producing an informed 
adjudicatory record that supports the licensing determination to be 
made in this proceeding, the Commission expects that both the Licensing 
Board and NRC staff, as well as the applicant and other parties to this 
proceeding, will follow the applicable requirements contained in 10 CFR 
part 2 and guidance in the Commission's Statement of Policy on Conduct 
of Adjudicatory Proceedings, CLI-98-12, 48 NRC 18 (1998) (63 Fed. Reg. 
41872 (August 5, 1998)) to the extent that such guidance is not 
inconsistent with specific guidance in this Order. The guidance in the 
Statement of Policy on Conduct of Adjudicatory Proceedings is intended 
to

[[Page 11096]]

improve the management and the timely completion of the proceeding and 
addresses hearing schedules, parties' obligations, contentions and 
discovery management. In addition, the Commission is providing the 
following direction for this proceeding:
    (1) The Commission directs the Licensing Board to set a schedule 
for the hearing in this proceeding consistent with this Order that 
provides for the issuance of a final Commission decision on the pending 
application within two-and-one-half years (30 months) from the date the 
staff formally accepted the application for review. Accordingly, the 
Licensing Board shall issue its decision on either the contested or 
mandatory hearing, or both, held in this matter no later than 28\1/2\ 
months (855 days) from the date the staff formally accepted the 
application for review. Formal discovery against the staff shall be 
suspended until after the staff completes its final SER and EIS in 
accordance with the direction provided in paragraph c.3) above.
    (2) The evidentiary hearing with respect to contested issues shall 
commence promptly after completion of the final staff documents (SER or 
EIS) unless the Licensing Board, in its discretion, finds that starting 
the hearing with respect to one or more safety issues prior to issuance 
of the final SER \12\ (or one or more environmental contentions 
directed to the applicant's Environmental Report) will expedite the 
proceeding without adversely impacting the staff's ability to complete 
its evaluations in a timely manner.
---------------------------------------------------------------------------

    \12\ The Commission believes that, in the appropriate 
circumstances, allowing discovery or an evidentiary hearing with 
respect to safety-related issues to proceed before the final SER is 
issued will serve to further the Commission's objective, as 
reflected in the Statement of Policy on Conduct of Adjudicatory 
Proceedings, CLI-98-12, supra, to ensure a fair, prompt, and 
efficient resolution of contested issues. For example, it may be 
appropriate for the Board to permit discovery against the staff and/
or the commencement of an evidentiary hearing with respect to safety 
issues prior to the issuance of the final SER in cases where the 
applicant has responded to the Staff's ``open items'' and there is 
an appreciable lag time until the issuance of the final SER, or in 
cases where the initial SER identifies only a few open items.
---------------------------------------------------------------------------

    (3) The Commission also believes that issuing a decision on the 
pending application within about two-and-one-half years may be 
reasonably achieved under the rules of practice contained in 10 CFR 
part 2 and the enhancements directed by this Order. We do not expect 
the Licensing Board to sacrifice fairness and sound decision-making to 
expedite any hearing granted on this application. We do expect the 
Licensing Board to use the applicable techniques specified in: this 
Order; 10 CFR 2.332, 2.333, and 2.334; and the Commission's policy 
statement on the conduct of adjudicatory proceedings (CLI-98-12, supra) 
to ensure prompt and efficient resolution of contested issues. See also 
Statement of Policy on Conduct of Licensing Proceedings, CLI-81-8, 13 
NRC 452 (1981).
    (4) If this is a contested proceeding, the Licensing Board shall 
adopt the following milestones, in developing a schedule, for 
conclusion of significant steps in the adjudicatory proceeding.\13\
---------------------------------------------------------------------------

    \13\ This schedule assumes that the SER and FEIS are issued 
essentially at the same time. If these documents are not to be 
issued very close in time, the Board should adopt separate schedules 
but concurrently running for the safety and environmental reviews 
consistent with the timeframes herein for each document.

------------------------------------------------------------------------
 
------------------------------------------------------------------------
Within [60 days from the date of         Deadline for Requests for
 publication of this Federal Register     Hearing; Petitions to
 notice].                                 Intervene and Contentions; and
                                          Requests for Limited
                                          Participation.
Within [90 days from the date of         Answers to Requests for
 publication of this Federal Register     Hearing; Petitions to
 Notice].                                 Intervene and Request for
                                          Limited Participation.
Within [100 days from the date of        Replies to Answers regarding
 publication of this Federal Register     Requests for Hearing;
 Notice].                                 Petitions to Intervene and
                                          Request for Limited
                                          Participation.
Within [120 days from the date of        Licensing Board holds Pre-
 publication of this Federal Register     hearing Conference to hear
 notice].                                 arguments on petitions to
                                          intervene and contention
                                          admissibility.
Within 30 days of pre-hearing            Licensing Board issues order
 conference.                              determining intervention.
                                         Discovery commences, except
                                          against the staff.
Within 10 days of the Licensing Board    Persons admitted or entities
 order determining intervention.          participating under 10 CFR
                                          2.315(c) may submit a motion
                                          for reconsideration (see
                                          below, at Section VI.B).*
Within 20 days of the Licensing Board    Persons admitted or entities
 order determining intervention.          participating under 10 CFR
                                          2.315(c) may respond to any
                                          motion for reconsideration.
Within 30 days of the Licensing Board    Staff prepares hearing file.
 decision determining intervention.
Date of issuance of final SER/EIS......  Staff updates hearing file.
                                         Discovery commences against the
                                          Staff.
Within 20 days of the issuance of the    Motions to amend contentions;
 final SER/EIS.                           motions for late-filed
                                          contentions.
Within 40 days of the issuance of final  Completion of answers and
 SER/EIS:.                                replies to motions for amended
                                          and late-filed contentions.
                                         Completion of discovery on
                                          original contentions.
                                         Deadline for summary
                                          disposition motions on
                                          original contentions.**
Within 50 days of the issuance of the    Licensing Board decision on
 final SER/EIS.                           admissibility of late-filed
                                          contentions.**
Within 55 days of the issuance of the    Licensing Board determination
 final SER/EIS.                           as to whether resolution of
                                          any motion for summary
                                          disposition will serve to
                                          expedite the proceedings.
Within 65 days of the issuance of the    Answers to motions for summary
 final SER/EIS.                           disposition identified by
                                          Licensing Board.
Within 75 days of the issuance of the    Replies to answers to motions
 final SER/EIS.                           for summary disposition.
Within 80 days of the issuance of final  Completion of discovery on late-
 SER/EIS.                                 filed contentions.
Within 105 days of the issuance of the   Licensing Board decision on
 final SER/EIS.                           summary disposition motions on
                                          original contentions.
Within 115 days of the issuance of       Direct testimony filed on
 final SER/EIS.                           original contentions and any
                                          amended or admitted late-filed
                                          contentions.
Within 125 days of the issuance of       Cross-examination plans filed
 final SER/EIS.                           on original contentions and
                                          any amended or admitted late-
                                          filed contentions.
Within 135 days of the issuance of       Evidentiary hearing begins on
 final SER/EIS.                           original contentions and any
                                          amended or admitted late-filed
                                          contentions.
Within 160 days of the issuance of       Completion of evidentiary
 final SER/EIS.                           hearing on remaining
                                          contentions and any amended or
                                          admitted late-filed
                                          contentions.
Within 205 days of the issuance of       Completion of findings and
 final SER/EIS.                           replies.
Within 245 days of the issuance of       Licensing Board's initial
 final SER/EIS.                           decision.***
------------------------------------------------------------------------
* Motions for reconsideration do not stay this schedule.
** No summary disposition motions on late-filed contentions are
  contemplated.
*** The Licensing Board's initial decision with respect to either a
  contested adjudicatory hearing or an uncontested, mandatory hearing
  shall be issued no later than 28\1/2\ months from the date the staff
  formally accepted the application for review.


[[Page 11097]]

    To avoid unnecessary delays in the proceeding, the Licensing Board 
shall not routinely grant requests for extensions of time and should 
manage the schedule such that the overall hearing process is completed 
within 28\1/2\ months. Although summary disposition motions are 
included in the schedule above, the Licensing Board shall not entertain 
motions for summary disposition under 10 CFR 2.710, unless the 
Licensing Board finds that such motions, if granted, are likely to 
expedite the proceeding. Unless otherwise justified, the Licensing 
Board shall provide for the simultaneous filing of answers to proposed 
contentions, responsive pleadings, proposed findings of fact, and other 
similar submittals.
    (5) Parties are obligated to comply with applicable requirements in 
10 CFR part 2, unless directed otherwise by this Order or the Licensing 
Board. They are also obligated in their filings before the Licensing 
Board and the Commission to ensure that their arguments and assertions 
are supported by appropriate and accurate references to legal authority 
and factual basis, including, as appropriate, citation to the record. 
Failure to do so may result in material being stricken from the record 
or, in extreme circumstances, a party being dismissed from the 
proceeding.
    (6) The Commission directs the Licensing Board to inform the 
Commission promptly, in writing, if the Licensing Board determines that 
any single milestone could be missed by more than 30 days. The 
Licensing Board must include an explanation of why the milestone cannot 
be met and the measures the Licensing Board will take to mitigate the 
failure to achieve the milestone and restore the proceeding to the 
overall schedule.

e. Commission Oversight

    As in any proceeding, the Commission retains its inherent 
supervisory authority over the proceeding to provide additional 
guidance to the Licensing Board and participants and to resolve any 
matter in controversy itself.

IV. Applicable Requirements

A. Licensing

    The Commission will license and regulate byproduct, source, and 
special nuclear material at the PLEF in accordance with the AEA. 
Section 274c.(1) of the AEA was amended by Public Law 102-486 (October 
24, 1992) to require the Commission to retain authority and 
responsibility for the regulation of uranium enrichment facilities. 
Therefore, in compliance with law, the Commission will be the sole 
licensing and regulatory authority with respect to possession of 
equipment capable of enriching uranium, operation of a uranium 
enrichment facility, and possession and use of byproduct, source, and 
special nuclear material for the PLEF in connection therewith.
    Many rules and regulations in 10 CFR Chapter I are applicable to 
the licensing of a person to receive, possess, use, transfer, deliver, 
or process byproduct, source or special nuclear material in the 
quantities that would be possessed at the PLEF. These include 10 CFR 
parts 19, 20, 21, 25, 30, 40, 51, 70, 71, 73, 74, 95, 140, 170, and 171 
for the licensing and regulation of byproduct, source, and special 
nuclear material, including requirements for notices to workers, 
reporting of defects, radiation protection, waste disposal, 
decommissioning funding, and insurance. With respect to these 
regulations, the Commission notes that this is the sixth proceeding 
involving the licensing of an enrichment facility.\14\
---------------------------------------------------------------------------

    \14\ The Commission issued a number of decisions in earlier 
proceedings regarding proposed sites in Homer, Louisiana (Claiborne 
Enrichment Center); Eunice, New Mexico (National Enrichment 
Facility); Piketon, Ohio (American Centrifuge Plant); Bonneville 
County, Idaho (Eagle Rock Enrichment Facility); and Wilmington, 
North Carolina (GLE Commercial Facility). These final decisions--
Louisiana Energy Services, L.P. (Claiborne Enrichment Center), CLI-
92-7, 35 NRC 93 (1992); Louisiana Energy Services, L.P. (Claiborne 
Enrichment Center), CLI-97-15, 46 NRC 294 (1997); Louisiana Energy 
Services, L.P. (Claiborne Enrichment Center), CLI-98-3, 47 NRC 77 
(1998); Louisiana Energy Services, L.P. (National Enrichment 
Facility), CLI-05-05, 61 NRC 22(2005); Louisiana Energy Services, 
L.P. (National Enrichment Facility), et. al., CLI-05-17, 62 NRC 5 
(2005); USEC, Inc. (American Centrifuge Plant), CLI-07-05, 65 NRC 
109 (2007); AREVA Enrichment Services, LLC (Eagle Rock Enrichment 
Facility), CLI-11-4, 74 NRC 1 (2011)--resolve a number of issues 
concerning uranium enrichment licensing and may be relied upon as 
precedent.
---------------------------------------------------------------------------

    Consistent with the AEA, and the Commission's regulations, the 
Commission is providing the following direction for licensing uranium 
enrichment facilities:
1. Environmental Issues
    a. General: 10 CFR part 51 governs the preparation of an 
environmental report and an EIS for a materials license. GLE's 
environmental report and the NRC staff's associated EIS shall include a 
statement on the alternatives to the proposed action, including a 
discussion of the no-action alternative.
    b. Treatment of depleted UF6 tails: As to the treatment 
of the disposition of depleted UF6 tails (depleted tails) in 
these environmental documents, unless GLE demonstrates a use for 
uranium in the depleted tails as a potential resource, the depleted 
tails will be considered waste. The Commission has previously concluded 
that depleted uranium from an enrichment facility is appropriately 
classified as low-level radioactive waste.\15\ An approach for 
disposition of tails that is consistent with the USEC Privatization 
Act, such as transfer to the Department of Energy (DOE) for disposal, 
constitutes a ``plausible strategy'' for disposition of the GLE 
depleted tails.\16\ The NRC staff may consider DOE's Final Programmatic 
Environmental Impact Statement for Alternative Strategies for the Long-
Term Management and Use of Depleted Uranium Hexafluoride in preparing 
the staff's EIS.\17\ GLE and the Staff shall address alternatives for 
the disposition of depleted uranium tails in these documents. As part 
of the licensing process, GLE must also address the health, safety, and 
security issues associated with the onsite storage of depleted uranium 
tails pending removal of the tails from the site for disposal or DOE 
disposition.
---------------------------------------------------------------------------

    \15\ See Louisiana Energy Services, CLI-05-05, 61 NRC at 36.
    \16\ Id.
    \17\ See Department of Energy, Final Programmatic Environmental 
Impact Statement for Alternative Strategies for the Long-Term 
Management and Use of Depleted Uranium Hexafluoride (DOE/EIS-0269), 
64 FR 43358 (Aug. 10, 1999).
---------------------------------------------------------------------------

2. Financial Qualifications
    Review of financial qualifications for enrichment facility license 
applications is governed by 10 CFR part 70. In CLI-97-15, the 
Commission held that the 10 CFR part 70 financial criteria, 10 CFR 
70.22(a)(8) and 70.23(a)(5), could be met by conditioning the license 
to require funding commitments to be in place prior to construction and 
operation.\18\ The specific license condition imposed--providing one 
way to satisfy the requirements of 10 CFR part 70--required the 
licensee to have in place prior to commencement of construction or 
operation: a minimum equity contribution of 30% of project costs from 
the parents and affiliates of partners prior to construction of the 
associated capacity; firm funding commitments for the remaining project 
costs; and long term enrichment contracts with prices sufficient to 
cover both construction and operating costs, including a return on 
investment, for the entire term of the contracts.
---------------------------------------------------------------------------

    \18\ Louisiana Energy Services, CLI-97-15, 46 NRC at 309.
---------------------------------------------------------------------------

3. Foreign Ownership
    The GLE application is governed by sections 53 and 63 of the AEA, 
and, consequently, issues of foreign

[[Page 11098]]

involvement shall be determined pursuant to sections 57 and 69, not 
sections 103, 104, or 193(f). Sections 57 and 69 of the AEA require, 
among other things, an affirmative finding by the Commission that 
issuance of a license for the PLEF facility will not be ``inimical to 
the common defense and security.'' The requirements of sections 57 and 
69 are incorporated in 10 CFR 70.31 and 10 CFR 40.32, respectively.
4. Creditor Requirements
    Pursuant to section 184 of the AEA, the creditor regulations in 10 
CFR 50.81 shall apply to the creation of creditor interests in 
equipment, devices, or important parts thereof, capable of separating 
the isotopes of uranium or enriching uranium in the isotope U-235. In 
addition, the creditor regulations in 10 CFR 70.44 shall apply to the 
creation of creditor interests in special nuclear material. These 
creditor regulations may be augmented by license conditions as 
necessary to allow ownership arrangements (such as sale and leaseback) 
not covered by 10 CFR 50.81, provided it can be found that such 
arrangements are not inimical to the common defense and security of the 
United States.
5. Classified Information
    All matters of classification of information related to the design, 
construction, operation, and safeguarding of the GLE-PLEF shall be 
governed by classification guidance in ``Joint DOE/NRC Classification 
Guide for Enrichment of Uranium by the SILEX Process in the United 
States,'' Secret Restricted Data (RD), Change 1 (November 2016) (CG-US-
SILEX-2) and ``Classification Guide for Safeguards and Security 
Information Associated with Uranium Enrichment by the SILEX Process,'' 
OUO, Change 1 (January 2024) (CG-NRC-SILEX-2A). All decisions on 
questions of classification or declassification of information shall be 
made by appropriate classification officials in the NRC and/or DOE and 
are not subject to de novo review in this proceeding.
6. Access to Classified Information
    Portions of GLE's application for a license are classified RD or 
National Security Information. Persons needing access to those portions 
of the application will be required to have the appropriate security 
clearance for the level of classified information to which access is 
required. Access requirements apply equally to intervenors, their 
witnesses and counsel, employees of the applicant, its witnesses and 
counsel, NRC personnel, and others. Any person who believes that he or 
she will have a need for access to classified information for the 
purpose of this licensing proceeding, including the hearing, should 
immediately contact the NRC, Division of Fuel Management, Washington, 
DC 20555, for information on the clearance process. Telephone calls may 
be made to Matthew Bartlett, Senior Project Manager, Fuel Facility 
Licensing Branch, Division of Fuel Management, Office of Nuclear 
Material Safety and Safeguards. Telephone: (301) 415-7154.
7. Obtaining NRC Security Facility Approval for Safeguarding Classified 
Information Received or Developed Pursuant to 10 CFR Part 95
    Any entity requiring access to or possession of classified 
information in connection with the licensing proceeding must process, 
store, reproduce, transmit, or handle such information exclusively at a 
location that has received facility security clearance approval from 
the NRC's Division of Security Operations, Washington, DC 20555. 
Telephone calls may be made to Mark MacDonald, Chief, Information 
Security Branch, Division of Security Operations, Office of Nuclear 
Security and Incident Response. Telephone: (301) 415-7751.

B. Reconsideration

    The above guidance does not foreclose the applicant, any person 
admitted as a party to the hearing, or an entity participating under 10 
CFR 2.315(c) from litigating material factual issues necessary for 
resolution of contentions in this proceeding. Persons permitted to 
intervene and entities participating under 10 CFR 2.315(c) as of the 
date of the order on intervention may also move the Commission to 
reconsider any portion of section VI of this Notice and Commission 
Order where there is no clear Commission precedent or unambiguously 
governing statutes or regulations. Any motion to reconsider must be 
filed within 10 days after the order on intervention. The motion must 
contain all technical or other arguments to support the motion. Other 
persons granted intervention and entities participating under 10 CFR 
2.315(c), including the applicant and the NRC staff, may respond to 
motions for reconsideration within 20 days of the order on 
intervention. Motions will be ruled upon by the Commission. A motion 
for reconsideration does not stay the schedule set out above in section 
V.d.4). However, if the Commission grants a motion for reconsideration, 
it will, as necessary, provide direction on adjusting the hearing 
schedule.

V. Notice of Intent Regarding Classified Information

    As noted above, a hearing on this application will be governed by 
10 CFR part 2, subparts A, C, G, and to the extent classified material 
becomes involved, Subpart I. Subpart I requires in accordance with 10 
CFR 2.907 that the NRC staff file a notice of intent if, at the time of 
publication of Notice of Hearing, it appears that it will be 
impracticable for the staff to avoid the introduction of Restricted 
Data or National Security Information into a proceeding. The applicant 
has submitted portions of its application that are classified and 
intends to submit additional portions of its application that will also 
be classified. The Commission notes that, since the entire application 
may become part of the record of the proceeding, the NRC staff has 
found it impracticable for it to avoid the introduction of RD or 
National Security Information into the proceeding.

VI. Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information and Safeguards Information for Contention 
Preparation

    A. This Order contains instructions regarding how potential parties 
to this proceeding may request access to documents containing sensitive 
unclassified information (including Sensitive Unclassified Non-
Safeguards Information (SUNSI) and Safeguards Information (SGI)). 
Requirements for access to SGI are primarily set forth in 10 CFR parts 
2 and 73. Nothing in this Order is intended to conflict with the SGI 
regulations.
    B. Within 10 days after publication of this notice of hearing or 
opportunity for hearing, any potential party who believes access to 
SUNSI or SGI is necessary to respond to this notice may request access 
to SUNSI or SGI. A ``potential party'' is any person who intends to 
participate as a party by demonstrating standing and filing an 
admissible contention under 10 CFR 2.309. Requests for access to SUNSI 
or SGI submitted later than 10 days after publication of this notice 
will not be considered absent a showing of good cause for the late 
filing, addressing why the request could not have been filed earlier.
    C. The requestor shall submit a letter requesting permission to 
access SUNSI, SGI, or both to the Office of the Secretary, U.S. Nuclear 
Regulatory Commission, Washington, DC 20555-0001, Attention: 
Rulemakings and Adjudications Staff, and provide a copy to the Deputy 
General Counsel for

[[Page 11099]]

Licensing, Hearings, and Enforcement, Office of the General Counsel, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. The 
expedited delivery or courier mail address for both offices is: U.S. 
Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, 
Maryland 20852. The email addresses for the Office of the Secretary and 
the Office of the General Counsel are [email protected] and 
[email protected], respectively.\19\ The request must 
include the following information:
---------------------------------------------------------------------------

    \19\ While a request for hearing or petition to intervene in 
this proceeding must comply with the filing requirements of the 
NRC's ``E-Filing Rule,'' the initial request to access SUNSI and/or 
SGI under these procedures should be submitted as described in this 
paragraph.
---------------------------------------------------------------------------

    (1) A description of the licensing action with a citation to this 
Federal Register notice;
    (2) The name and address of the potential party and a description 
of the potential party's particularized interest that could be harmed 
by the action identified in C.(1); and
    (3) If the request is for SUNSI, the identity of the individual or 
entity requesting access to SUNSI and the requestor's basis for the 
need for the information in order to meaningfully participate in this 
adjudicatory proceeding. In particular, the request must explain why 
publicly available versions of the information requested would not be 
sufficient to provide the basis and specificity for a proffered 
contention.
    (4) If the request is for SGI, the identity of each individual who 
would have access to SGI if the request is granted, including the 
identity of any expert, consultant, or assistant who will aid the 
requestor in evaluating the SGI. In addition, the request must contain 
the following information:
    (a) A statement that explains each individual's ``need to know'' 
the SGI, as required by 10 CFR 73.2 and 10 CFR 73.22(b)(1). Consistent 
with the definition of ``need to know'' as stated in 10 CFR 73.2, the 
statement must explain:
    (i) Specifically, why the requestor believes that the information 
is necessary to enable the requestor to proffer and/or adjudicate a 
specific contention in this proceeding; \20\ and
---------------------------------------------------------------------------

    \20\ Broad SGI requests under these procedures are unlikely to 
meet the standard for need to know; furthermore, NRC staff redaction 
of information from requested documents before their release may be 
appropriate to comport with this requirement. These procedures do 
not authorize unrestricted disclosure or less scrutiny of a 
requestor's need to know than ordinarily would be applied in 
connection with an already-admitted contention or non-adjudicatory 
access to SGI.
---------------------------------------------------------------------------

    (ii) The technical competence (demonstrable knowledge, skill, 
training or education) of the requestor to effectively utilize the 
requested SGI to provide the basis and specificity for a proffered 
contention. The technical competence of a potential party or its 
counsel may be shown by reliance on a qualified expert, consultant, or 
assistant who satisfies these criteria.
    (b) A completed Form SF-85, ``Questionnaire for Non-Sensitive 
Positions,'' for each individual who would have access to SGI. The 
completed Form SF-85 will be used by the Office of Administration to 
conduct the background check required for access to SGI, as required by 
10 CFR part 2, subpart C, and 10 CFR 73.22(b)(2), to determine the 
requestor's trustworthiness and reliability. For security reasons, Form 
SF-85 can only be submitted electronically through the National 
Background Investigation Services e-App system, a secure website that 
is owned and operated by the Defense Counterintelligence and Security 
Agency (DCSA). To obtain online access to the form, the requestor 
should contact the NRC's Office of Administration at 301-415-3710.\21\
---------------------------------------------------------------------------

    \21\ The requestor will be asked to provide the requestor's full 
name, social security number, date and place of birth, telephone 
number, and email address. After providing this information, the 
requestor usually should be able to obtain access to the online form 
within one business day.
---------------------------------------------------------------------------

    (c) A completed Form FD-258 (fingerprint card), signed in original 
ink, and submitted in accordance with 10 CFR 73.57(d). Copies of Form 
FD-258 will be provided in the background check request package 
supplied by the Office of Administration for each individual for whom a 
background check is being requested. The fingerprint card will be used 
to satisfy the requirements of 10 CFR part 2, subpart C, 10 CFR 
73.22(b)(1), and Section 149 of the Atomic Energy Act of 1954, as 
amended, which mandates that all persons with access to SGI must be 
fingerprinted for a Federal Bureau of Investigation identification and 
criminal history records check.
    (d) A check or money order payable in the amount of $369.00 \22\ to 
the U.S. Nuclear Regulatory Commission for each individual for whom the 
request for access has been submitted.
---------------------------------------------------------------------------

    \22\ This fee is subject to change pursuant to DCSA's adjustable 
billing rates.
---------------------------------------------------------------------------

    (e) If the requestor or any individual(s) who will have access to 
SGI believes they belong to one or more of the categories of 
individuals that are exempt from the criminal history records check and 
background check requirements in 10 CFR 73.59, the requestor should 
also provide a statement identifying which exemption the requestor is 
invoking and explaining the requestor's basis for believing that the 
exemption applies. While processing the request, the Office of 
Administration, Personnel Security Branch, will make a final 
determination whether the claimed exemption applies. Alternatively, the 
requestor may contact the Office of Administration for an evaluation of 
their exemption status prior to submitting their request. Persons who 
are exempt from the background check are not required to complete the 
SF-85 or Form FD-258; however, all other requirements for access to 
SGI, including the need to know, are still applicable.

    Note:  Copies of documents and materials required by paragraphs 
C.(4)(b), (c), and (d) of this Order must be sent to the following 
address: U.S. Nuclear Regulatory Commission, Office of 
Administration, ATTN: Personnel Security Branch, Mail Stop: TWFN-
07D04M, 11555 Rockville Pike, Rockville, MD 20852.

    These documents and materials should not be included with the 
request letter to the Office of the Secretary, but the request letter 
should state that the forms and fees have been submitted as required.
    D. To avoid delays in processing requests for access to SGI, the 
requestor should review all submitted materials for completeness and 
accuracy (including legibility) before submitting them to the NRC. The 
NRC will return incomplete packages to the sender without processing.
    E. Based on an evaluation of the information submitted under 
paragraphs C.(3) or C.(4), the NRC staff will determine within 10 days 
of receipt of the request whether:
    (1) There is a reasonable basis to believe the petitioner is likely 
to establish standing to participate in this NRC proceeding; and
    (2) The requestor has established a legitimate need for access to 
SUNSI or need to know the SGI requested.
    F. For requests for access to SUNSI, if the NRC staff determines 
that the requestor satisfies both E.(1) and E.(2), the NRC staff will 
notify the requestor in writing that access to SUNSI has been granted. 
The written notification will contain instructions on how the requestor 
may obtain copies of the requested documents, and any other conditions 
that may apply to access to those documents. These conditions may 
include, but are not limited to, the signing of a Non-Disclosure 
Agreement

[[Page 11100]]

or Affidavit, or Protective Order \23\ setting forth terms and 
conditions to prevent the unauthorized or inadvertent disclosure of 
SUNSI by each individual who will be granted access to SUNSI.
---------------------------------------------------------------------------

    \23\ Any motion for Protective Order or draft Non-Disclosure 
Affidavit or Agreement for SUNSI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 30 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    G. For requests for access to SGI, if the NRC staff determines that 
the requestor has satisfied both E.(1) and E.(2), the Office of 
Administration will then determine, based upon completion of the 
background check, whether the proposed recipient is trustworthy and 
reliable, as required for access to SGI by 10 CFR 73.22(b). If the 
Office of Administration determines that the individual or individuals 
are trustworthy and reliable, the NRC will promptly notify the 
requestor in writing. The notification will provide the names of 
approved individuals as well as the conditions under which the SGI will 
be provided. Those conditions may include, but are not limited to, the 
signing of a draft Non-Disclosure Agreement or Affidavit, or Protective 
Order \24\ by each individual who will be granted access to SGI.
---------------------------------------------------------------------------

    \24\ Any motion for Protective Order or draft Non-Disclosure 
Agreement or Affidavit for SGI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 180 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    H. Release and Storage of SGI. Prior to providing SGI to the 
requestor, the NRC staff will conduct (as necessary) an inspection to 
confirm that the recipient's information protection system is 
sufficient to satisfy the requirements of 10 CFR 73.22. Alternatively, 
recipients may opt to view SGI at an approved SGI storage location 
rather than establish their own SGI protection program to meet SGI 
protection requirements.
    I. Filing of Contentions. Any contentions in these proceedings that 
are based upon the information received as a result of the request made 
for SUNSI must be filed by the requestor no later than 25 days after 
receipt of (or access to) that information. However, if more than 25 
days remain between the petitioner's receipt of (or access to) the 
information and the deadline for filing all other contentions (as 
established in the notice of hearing or opportunity for hearing), the 
petitioner may file its SUNSI contentions by that later deadline.
    J. Review of Denials of Access.
    (1) If the request for access to SUNSI or SGI is denied by the NRC 
staff after a determination on standing and requisite need, or after a 
determination on trustworthiness and reliability, the NRC staff shall 
immediately notify the requestor in writing, briefly stating the reason 
or reasons for the denial.
    (2) Before the Office of Administration makes a final adverse 
determination regarding the trustworthiness and reliability of the 
proposed recipient(s) for access to SGI, the Office of Administration, 
in accordance with 10 CFR 2.336(f)(1)(iii), must provide the proposed 
recipient(s) any records that were considered in the trustworthiness 
and reliability determination, including those required to be provided 
under 10 CFR 73.57(e)(1), so that the proposed recipient(s) have an 
opportunity to correct or explain the record.
    (3) The requestor may challenge the NRC staff's adverse 
determination with respect to access to SUNSI or with respect to 
standing or need to know for SGI by filing a challenge within five days 
of receipt of that determination with: (a) the presiding officer 
designated in this proceeding; (b) if no presiding officer has been 
appointed, the Chief Administrative Judge, or if this individual is 
unavailable, another administrative judge, or an Administrative Law 
Judge with jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another 
officer has been designated to rule on information access issues, with 
that officer.
    (4) The requestor may challenge the Office of Administration's 
final adverse determination with respect to trustworthiness and 
reliability for access to SGI by filing a request for review in 
accordance with 10 CFR 2.336(f)(1)(iv).
    (5) Further appeals of decisions under this paragraph must be made 
pursuant to 10 CFR 2.311.
    K. Review of Grants of Access. A party other than the requestor may 
challenge an NRC staff determination granting access to SUNSI whose 
release would harm that party's interest independent of the proceeding. 
Such a challenge must be filed within five days of the notification by 
the NRC staff of its grant of access and must be filed with: (a) the 
presiding officer designated in this proceeding; (b) if no presiding 
officer has been appointed, the Chief Administrative Judge, or if this 
individual is unavailable, another administrative judge, or an 
Administrative Law Judge with jurisdiction pursuant to 10 CFR 2.318(a); 
or (c) if another officer has been designated to rule on information 
access issues, with that officer.
    If challenges to the NRC staff determinations are filed, these 
procedures give way to the normal process for litigating disputes 
concerning access to information. The availability of interlocutory 
review by the Commission of orders ruling on such NRC staff 
determinations (whether granting or denying access) is governed by 10 
CFR 2.311.\25\
---------------------------------------------------------------------------

    \25\ Requestors should note that the filing requirements of the 
NRC's E-Filing Rule (72 FR 49139; August 28, 2007, as amended at 77 
FR 46562; August 3, 2012, 78 FR 34247, June 7, 2013) apply to 
appeals of NRC staff determinations (because they must be served on 
a presiding officer or the Commission, as applicable), but not to 
the initial SUNSI request submitted to the NRC staff under these 
procedures.
---------------------------------------------------------------------------

    L. The Commission expects that the NRC staff and presiding officers 
(and any other reviewing officers) will consider and resolve requests 
for access to SUNSI or SGI, and motions for protective orders, in a 
timely fashion in order to minimize any unnecessary delays in 
identifying those petitioners who have standing and who have propounded 
contentions meeting the specificity and basis requirements in 10 CFR 
part 2. The attachment to this Order summarizes the general target 
schedule for processing and resolving requests under these procedures.
    It is so ordered.

    Dated at Rockville, Maryland, this 4th day of March 2026.

    For the Commission.
Carrie Safford,
Secretary of the Commission.

Attachment 1--General Target Schedule for Processing and Resolving 
Requests for Access to Sensitive Unclassified Non-Safeguards 
Information and Safeguards Information in This Proceeding

------------------------------------------------------------------------
           Day                             Event/activity
------------------------------------------------------------------------
0........................  Publication of Federal Register notice of
                            hearing or opportunity for hearing,
                            including order with instructions for access
                            requests.

[[Page 11101]]

 
10.......................  Deadline for submitting requests for access
                            to Sensitive Unclassified NonSafeguards
                            Information (SUNSI) and/or Safeguards
                            Information (SGI) which contains
                            information: supporting the standing of a
                            potential party identified by name and
                            address; describing the need for the
                            information in order for the potential party
                            to participate meaningfully in an
                            adjudicatory proceeding; demonstrating that
                            access should be granted (e.g., showing
                            technical competence for access to SGI);
                            and, for SGI, including application fee for
                            fingerprint/background check.
60.......................  Deadline for submitting petition for
                            intervention which contains: (i)
                            Demonstration of standing; (ii) all
                            contentions whose formulation does not
                            require access to SUNSI and/or SGI (+25
                            Answers to petition for intervention; +7
                            requestor/petitioner reply).
20.......................  U.S. Nuclear Regulatory Commission (NRC)
                            staff informs the requestor of the staff's
                            determination whether the request for access
                            provides a reasonable basis to believe
                            standing can be established and demonstrates
                            the (1) need for SUNSI or (2) need to know
                            for SGI. (For SUNSI, NRC staff also informs
                            any party to the proceeding whose interest
                            independent of the proceeding would be
                            harmed by the release of the information.)
                            If NRC staff makes the finding of need for
                            SUNSI and likelihood of standing, NRC staff
                            begins document processing (preparation of
                            redactions or review of redacted documents).
                            If NRC staff makes the finding of need to
                            know for SGI and likelihood of standing, NRC
                            staff begins background check (including
                            fingerprinting for a criminal history
                            records check), information processing
                            (i.e., preparation of redactions or review
                            of redacted documents), and readiness
                            inspections.
25.......................  If NRC staff finds no ``need,'' no ``need to
                            know,'' or no likelihood of standing, the
                            deadline for requestor/petitioner to file a
                            motion seeking a ruling to reverse the NRC
                            staff's denial of access; NRC staff files
                            copy of access determination with the
                            presiding officer (or Chief Administrative
                            Judge or other designated officer, as
                            appropriate). If NRC staff finds ``need''
                            for SUNSI, the deadline for any party to the
                            proceeding whose interest independent of the
                            proceeding would be harmed by the release of
                            the information to file a motion seeking a
                            ruling to reverse the NRC staff's grant of
                            access.
30.......................  Deadline for NRC staff's reply to motions to
                            reverse NRC staff determination(s).
40.......................  (Receipt +30) If NRC staff finds standing and
                            need for SUNSI, deadline for NRC staff to
                            complete information processing and file
                            motion for Protective Order and draft Non-
                            Disclosure Agreement or Affidavit. Deadline
                            for applicant/licensee to file draft Non-
                            Disclosure Agreement or Affidavit for SUNSI.
190......................  (Receipt +180) If NRC staff finds standing,
                            need to know for SGI, and trustworthiness
                            and reliability, deadline for NRC staff to
                            file motion for Protective Order and draft
                            Non-Disclosure Agreement or Affidavit (or to
                            make a determination that the proposed
                            recipient of SGI is not trustworthy or
                            reliable). Note: Before the Office of
                            Administration makes a final adverse
                            determination regarding access to SGI, the
                            proposed recipient must be provided an
                            opportunity to correct or explain
                            information.
205......................  Deadline for petitioner to seek reversal of a
                            final adverse NRC staff trustworthiness or
                            reliability determination under 10 CFR
                            2.336(f)(1)(iv).
A........................  If access is granted: Issuance of a decision
                            by a presiding officer or other designated
                            officer on motion for Protective Order for
                            access to sensitive information (including
                            schedule for providing access and submission
                            of contentions) or decision reversing a
                            final adverse determination by the NRC
                            staff.
A + 3....................  Deadline for filing executed draft Non-
                            Disclosure Agreements or Affidavits. Access
                            provided to SUNSI and/or SGI consistent with
                            decision issuing the Protective Order.
A + 28...................  Deadline for submission of contentions whose
                            development depends upon access to SUNSI and/
                            or SGI. However, if more than 25 days remain
                            between the petitioner's receipt of (or
                            access to) the information and the deadline
                            for filing all other contentions (as
                            established in the notice of opportunity to
                            request a hearing and petition for leave to
                            intervene), the petitioner may file its
                            SUNSI or SGI contentions by that later
                            deadline.
A + 53...................  (Contention receipt +25) Answers to
                            contentions whose development depends upon
                            access to SUNSI and/or SGI.
A + 60...................  (Answer receipt +7) Petitioner/Intervenor
                            reply to answers.
>A + 60..................  Decision on contention admission.
------------------------------------------------------------------------


[FR Doc. 2026-04474 Filed 3-5-26; 8:45 am]
BILLING CODE 7590-01-P