[Federal Register Volume 91, Number 39 (Friday, February 27, 2026)]
[Notices]
[Pages 9888-9890]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2026-03957]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-010; NRC-2026-1090]


Constellation Energy Generation, LLC; Dresden Nuclear Power 
Station, Unit 1; Exemption

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC, or Commission) 
has issued an exemption in response to a request from Constellation 
Energy Generation, LLC, to allow the completion of decommissioning 
beyond 60 years of permanent cessation of operations for the Dresden 
Nuclear Power Station, Unit 1.

DATES: The exemption was issued on February 19, 2026.

ADDRESSES: Please refer to Docket ID NRC-2026-1090 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2026-1090. Address 
questions about Docket IDs in Regulations.gov to Bridget Curran; 
telephone: 301-415-1003; email: [email protected]. For technical 
questions, contact the individual(s) listed in the FOR FURTHER 
INFORMATION CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin ADAMS Public Search.'' 
For problems with ADAMS, please contact the NRC's Public Document Room 
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email 
to [email protected]. The ADAMS accession number for each document 
referenced (if it is available in ADAMS) is provided the first time 
that it is mentioned in this document.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

FOR FURTHER INFORMATION CONTACT: Tanya E. Hood, Office of Nuclear 
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission, 
Washington, DC 20555-0001; telephone: 301-415-1387; email: 
[email protected].

SUPPLEMENTARY INFORMATION: The text of the exemption is attached.

    Dated: February 25, 2026.

    For the Nuclear Regulatory Commission.
Tanya Hood,
Project Manager, Reactor Decommissioning Branch, Division of 
Decommissioning, Uranium Recovery and Waste Programs, Office of Nuclear 
Material Safety and Safeguards.

Attachment--Exemption

NUCLEAR REGULATORY COMMISSION

Docket No. 50-010; Constellation Energy Generation, LLC; Dresden 
Nuclear Power Station, Unit 1; Exemption

I. Background

    By letter dated March 14, 2024 (Agencywide Documents Access and 
Management System Accession No. ML24074A437), as supplemented by 
letters dated July 22, 2024, July 31, 2024, and December 5, 2024 
(ML24204A219, ML24213A313, and ML24340A271 respectively), 
Constellation Energy Generation, LLC (the licensee) submitted a 
request for an alternative decommissioning schedule for Dresden 
Nuclear Power Station, Unit 1 (Dresden Unit 1) that would allow the 
completion of decommissioning for Dresden Unit 1 in conjunction with 
the decommissioning of Dresden's operating units, Units 2 and 3, 
thereby extending decommissioning beyond 60 years of permanent 
cessation of operations.
    The Dresden Nuclear Power Station is in Grundy County, IL and is 
composed of three reactor licenses: Dresden Unit 1 (License No. DPR-
2), which is presently in a long-term storage condition for a 
permanently shut down nuclear power plant, referred to as SAFSTOR 
and is the subject of this request, along with Dresden Unit 2 (DPR-
19) and Dresden Unit 3 (DPR-25), which are actively operating. 
Dresden Unit 1 is licensed pursuant to Section 104(b) of the Atomic 
Energy Act of 1954, as amended, and Title 10 of the Code of Federal 
Regulations (10 CFR) Part 50, Paragraph 50.82(a)(2) to possess but 
not operate the facility.
    Dresden Unit 1 was a boiling water reactor that permanently 
ceased operations on October 31, 1978. In October 1984, a decision 
was made to decommission Dresden Unit 1 and a chemical 
decontamination of the primary system was completed. On July 23, 
1986, the U.S. Nuclear Regulatory Commission (NRC or Commission) 
issued a license amendment to alter the Dresden Unit 1 operating 
license to possession only status. Between 1986 and 2006, various 
decommissioning activities were performed at Dresden Unit 1, 
including the transfer of the spent fuel to the onsite independent 
spent fuel storage installation (ISFSI); the September 1993 approval 
of the decommissioning plan (ML20057A646); the

[[Page 9889]]

May 1998, submission by the Commonwealth Edison Company of the 
Dresden Post-Shutdown Decommissioning Activities Report (PSDAR) to 
the NRC (ML20248H086); and the revision of the Decommissioning 
Program Plan to the current Defueled Safety Analysis Report (DSAR) 
format. Since that time, Dresden Unit 1 has been monitored and 
controlled in SAFSTOR in accordance with the Facility Operating 
License, Technical Specifications as amended, and Decommissioning 
Plan.

II. Request/Action

    The regulation at 10 CFR 50.82(a)(3) requires power reactor 
licensees to complete decommissioning within 60 years of permanent 
cessation of operations. The regulation provides that completion of 
decommissioning beyond 60 years will be considered by the Commission 
only when necessary to protect public health and safety, with site-
specific factors considered when reviewing such requests, including 
the presence of other nuclear facilities at the site.
    The licensee requested an alternative to the 60 year 
decommissioning schedule requirements in 10 CFR 50.82(a)(3) to 
decommission Dresden Unit 1 to coincide with the eventual 
decommissioning of Dresden Units 2 and 3. The licensee stated its 
alternative request ``meets the evaluation factors in 10 CFR 
50.82(a)(3) due to the potential impact on public health and safety 
with other nuclear facilities present at the site'' and that 
``[t]here are site-specific factors, supporting the operation of 
Dresden Units, 2 and 3, that necessitate decommissioning of Dresden, 
Unit 1, beyond 60 years of permanent cessation of operations to best 
protect public health and safety.''
    On September 30, 2025, the NRC issued subsequent renewed 
facility operating licenses for Dresden Units 2 and 3 (ML25233A275), 
which included the expiration dates of December 22, 2049, and 
January 12, 2051, respectively. The licensee is requesting extension 
of Dresden Unit 1 decommissioning completion and license termination 
to be concurrent with that of Dresden Units 2 and 3.

III. Discussion

    Under 10 CFR 50.82(a)(3), the Commission will approve an 
alternative that provides for completion of decommissioning beyond 
60 years of permanent cessation of operations only when necessary to 
protect public health and safety. In evaluating whether an 
alternative is necessary, the regulations provide that the 
Commission will consider factors such as unavailability of waste 
disposal capacity; or other site-specific factors affecting the 
licensee's capability to carry out decommissioning, including 
presence of other nuclear facilities at the site. Prior to this 
request for an alternative decommissioning schedule, Dresden Unit 1, 
was required to complete decommissioning by October 31, 2038.
    The NRC staff's approach in evaluating the 10 CFR 50.82(a)(3) 
criteria is documented, in part, in SECY-24-0073, ``Site-Specific 
Considerations for Review of Requests to Complete Power Reactor 
Decommissioning Beyond 60 Years from Permanent Cessation of 
Operations,'' dated September 3, 2024 (ML24100A760). As explained in 
more detail below, the NRC has determined that the licensee has met 
the ``only when necessary to protect public health and safety'' 
criterion because the licensee demonstrated that Dresden Unit 1 
decommissioning activities could result in site-specific impacts on 
public health and safety due to the increased risk to structures, 
systems, and components (SSCs) supporting the adjacent operating 
Dresden Units 2 and 3 and the associated security measures.

Presence of Other Nuclear Facilities

    The licensee's request for an alternative decommissioning 
schedule was based on the potential impacts to public health and 
safety from decommissioning Dresden Unit 1, while there are two 
other operating nuclear facilities at the site. Specifically, the 
licensee noted that the proximity and interconnectivity of Dresden 
Unit 1 to the operating Units, Dresden Units 2 and 3, pose unique 
challenges to decommissioning Unit 1 while the remaining units 
continue to operate.
    In support of its exemption request, the licensee noted that 
Dresden Unit 1 is structurally connected to Dresden Units 2 and 3. 
To complete decommissioning of Dresden Unit 1, several large 
components of Dresden Unit 1, including the reactor vessel, 
supporting reactor coolant systems, and steam supply systems, must 
be removed and shipped for disposal. Removal of these large 
components from Dresden Unit 1 while Dresden Units 2 and 3 continue 
to operate would be particularly challenging given the proximity and 
shared structures between Dresden Unit 1 and the operating units, 
Dresden Units 2 and 3. In support of its exemption request, the 
licensee noted that removal of the remaining large components and 
conducting other decommissioning activities at Dresden Unit 1 while 
Units 2 and 3 continue to operate would require the structural 
separation of the Main Control Room and Turbine Building to permit 
demolition of the Dresden Unit 1 Turbine Building structure. The 
licensee's assessment determined that attempting to separate the 
structures was prohibitive as the Main Control Room resides in both 
Dresden Unit 1 and Dresden Unit 2 Turbine Buildings, rendering the 
Dresden Unit 1 Turbine Building necessary to support safe operation 
of Units 2 and 3.
    The licensee also indicated that the operating Dresden Units 2 
and 3, have underground cable tunnels that are in close proximity to 
the Dresden Unit 1 containment structure. These various buried power 
and mechanical systems within the previous operating area of Dresden 
Unit 1, create site characteristics not normally encountered during 
decommissioning activities. In this instance, the close proximity of 
the underground cable tunnels to the Dresden Unit 1 buildings that 
would be decommissioned would require relocation. Physical 
relocation of these systems would require new robust structures, 
installation of redundant equipment, and space outside of Dresden 
Unit 1 operating areas being decommissioned.
    Additionally, the licensee notes that the entire site containing 
Dresden Units 1, 2, and 3, along with the associated ISFSI, are 
within a common site Protected Area under the site Physical Security 
Plan, which meets the physical protection requirements of 10 CFR 
part 73 for operating power reactors. Generally, as power reactors 
begin decommissioning, the sites transition to security plans 
meeting 10 CFR part 72 for ISFSIs and 10 CFR part 37 for security of 
radioactive materials. However, the licensee states that under both 
SAFSTOR and during dismantlement of Dresden Unit 1, due to the 
physical site characteristics, implementation of 10 CFR part 37 and 
72 security plans for Dresden Unit 1 would not be feasible given the 
proximity and interconnectivity of Dresden Unit 1 to Dresden Units 2 
and 3. These unique physical site characteristics make isolating 
areas of Dresden Unit 1 for decommissioning, and for implementation 
of a 10 CFR part 72 and Part 37 security plan for Dresden Unit 1, 
impractical. Therefore, according to the licensee, and consistent 
with the licensee's current decommissioning strategy as stated in 
the Dresden Unit 1 PSDAR, delaying the decommissioning of Dresden 
Unit 1 to coincide with shutdown of Dresden Units 2 and 3 would 
permit the implementation of a 10 CFR part 72 and Part 37 site-wide 
Physical Security Plan during decommissioning where common 
decommissioning techniques would be utilized across all units to 
provide for safe and efficient conduct of decommissioning 
operations.
    In evaluating this information, the NRC staff has determined 
that the interconnectivity and proximity of Dresden Unit 1 to the 
operating Dresden Units 2 and 3, as well as the need to maintain a 
combined site Physical Security Plan that encompasses all the Units, 
are site specific factors that affect the licensee's capability to 
safely carry out decommissioning of Dresden Unit 1 while Dresden 
Units 2 and 3 continue to operate. Therefore, the presence of the 
operating Dresden Units 2 and 3 at the site, supports an alternative 
decommissioning schedule for Dresden Unit 1, pursuant to 
50.82(a)(3).

Capacity and Capability of the Power Systems

    The licensee raised concerns with potential impacts to the 
electric power systems and the mechanical systems if Dresden Unit 1 
were required to be decommissioned on the original 60-year schedule. 
According to the licensee, the potential damage to a station 
blackout (SBO) cable tunnel could result in loss of the SBO function 
to one or both of the operating Units for an extended duration. The 
licensee explained that, although probability can be reduced through 
mitigation, the consequence of this risk represents an increased 
risk to protect public health and safety. The licensee stated that 
loss of the Dresden Units 2 and 3 SBO function would result in 
reduced defense-in-depth for the mitigation capability of the site 
during a loss of offsite power transient. Given the location of the 
SBO cable tunnel to Dresden Unit 1, common decommissioning 
techniques such as structure/site wide

[[Page 9890]]

electrical isolation, structure/site wide support system isolation 
(e.g., air, water, fire suppression), heavy equipment demolition and 
heavy equipment excavation, could not be executed due to the risk of 
damaging the SBO cable tunnel during decommissioning of Dresden Unit 
1, which could negatively impact the operation of Dresden Units 2 
and 3.
    According to the licensee, decommissioning of Dresden Unit 1 
would also require relocation of 4 kilovolt and 480 volt buses and 
distribution lines throughout the Dresden Unit 1 Turbine Building 
because this distribution system supports Dresden Units 2 and 3 SBO 
equipment and provides industrial power to a large portion of the 
site. Physical relocation would require new robust structures, 
installation of redundant equipment, and space outside of Dresden 
Unit 1 operating areas being decommissioned. To mitigate potential 
effects of demolition activities such as impacting sensitive 
equipment within proximity of, and inadvertent damage to electric 
power or mechanical systems not isolated, detailed isolation and 
demolition plans would be required. The licensee indicated that this 
would involve assessing the status of each mechanical and electrical 
component by area to ensure decommissioning activities do not 
adversely affect operation of Dresden Units 2 and 3, or personal 
safety of individuals executing decommissioning activities.
    Based on this information, the NRC staff has determined that 
decommissioning Dresden Unit 1 would impact the capacity and 
capability of the electric power or mechanical systems of the 
operating Dresden Units 2 and 3. Therefore, the NRC staff finds that 
the capacity and capability of the power systems at the Dresden 
Nuclear Power Station is a factor that, in combination with other 
factors discussed above, supports an alternative decommissioning 
schedule pursuant to 50.82(a)(3).

IV. Environmental Review Under the National Environmental Policy Act

    The NRC staff has determined that the proposed exemption can be 
categorically excluded under 10 CFR 51.22(c)(25) from NRC 
requirements under the National Environmental Policy Act to conduct 
an environmental assessment or an environmental impact statement. 
The categorical exclusion in 10 CFR 51.22(c)(25) states that the 
granting of an exemption from the requirements of any NRC regulation 
may be categorically excluded as long as the conditions of 10 CFR 
51.22(c)(25)(i)-(vi) are met.
    In this instance, the NRC staff determined all the conditions of 
10 CFR 51.22(c)(25)(i)-(v) have been satisfied. Approving this 
exemption would not: result in conditions that could significantly 
increase the probability or consequences of an accident previously 
evaluated or create the possibility of a new or different kind of 
accident; result in a significant change in the types or a 
significant increase in the amounts of any effluents that may be 
released offsite; result in increases to public and occupational 
radiation exposure; result in a significant construction impact; or 
result in a significant increase in the potential for or 
consequences from radiological accidents. Approval in this instance 
only continues the current status and activities at the facility. 
During the duration of the decommissioning delay, the licensee will 
maintain Dresden Unit 1 in SAFSTOR condition in accordance with the 
Updated Final Safety Analysis Report, technical specifications, and 
licensee procedures for Dresden Unit 1. The licensee will continue 
ongoing monitoring activities, such as capturing any identified 
degradations in structural inspection reports and the Corrective 
Action Program for resolution.
    Finally, the NRC staff has determined that the request satisfies 
10 CFR 51.22(c)(25)(vi) because the exemption applies to the 
following specific activities associated with Dresden Unit 1 that 
support the continued maintenance of Dresden Unit 1 in SAFSTOR into 
the period approved in the alternative decommissioning schedule: (A) 
recordkeeping requirements; (B) reporting requirements; (C) 
inspection and surveillance requirements; (D) equipment servicing or 
maintenance scheduling requirements; (F) safeguard plans, and 
materials control and accounting inventory scheduling requirements; 
and (G) scheduling requirements.
    Based on the above assessment, in accordance with 10 CFR 
51.22(b), no environmental impact statement or environmental 
assessment need be prepared in connection with the NRC's 
consideration of this exemption request.

VII. Conclusions

    For the reasons described above, the NRC concludes that, 
pursuant to 10 CFR 50.82(a)(3), there are site-specific factors 
affecting the licensee's capability to carry out decommissioning at 
Dresden Unit 1 because of the presence of the operating units at the 
site such that an alternative decommissioning schedule is necessary 
to protect public health and safety. The NRC's determination is 
based on the multiple connections that exist between Dresden Unit 1 
and the operating units, Dresden Units 2 and 3, and the associated 
site-wide security measures. Therefore, the NRC grants Constellation 
Energy Generation, LLC, a one-time exemption from 10 CFR 50.82(a)(3) 
to allow the licensee an alternative decommissioning schedule that 
requires the decommissioning of Dresden Unit 1, 20 years after the 
permanent cessation of operations of either Dresden Units 2 or 3, 
whichever is earlier, and in no case beyond 2071. With this 
approval, the licensee's SAFSTOR program will continue for the 
extended period of decommissioning and the licensee should update 
its program accordingly. For the period beyond 60 years, the NRC 
will continue its inspection of the SAFSTOR program as outlined in 
the Updated Final Safety Analysis Report, technical specifications, 
and licensee procedures.
    The exemption will be effective upon issuance.
    Dated: this 19th day of February 2026.
    For the Nuclear Regulatory Commission.
/RA/
Jane Marshall,
Director, Division of Decommissioning, Uranium Recovery, and Waste 
Programs, Office of Nuclear Material Safety and Safeguards.

[FR Doc. 2026-03957 Filed 2-26-26; 8:45 am]
BILLING CODE 7590-01-P