[Federal Register Volume 91, Number 19 (Thursday, January 29, 2026)]
[Notices]
[Page 3970]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2026-01792]
=======================================================================
-----------------------------------------------------------------------
SUSQUEHANNA RIVER BASIN COMMISSION
Minor Modification Approval
AGENCY: Susquehanna River Basin Commission.
ACTION: Notice.
-----------------------------------------------------------------------
SUMMARY: This notice lists the minor modifications approved for
previously approved projects by the Susquehanna River Basin Commission
during the period set forth in DATES.
DATES: January 1-31, 2026.
ADDRESSES: Susquehanna River Basin Commission, 4423 North Front Street,
Harrisburg, PA 17110-1788.
FOR FURTHER INFORMATION CONTACT: Jason E. Oyler, General Counsel and
Secretary to the Commission, telephone: (717) 238-0423, ext. 1312; fax
(717) 238-2436; email: [email protected]. Regular mail inquiries may be
sent to the above address.
SUPPLEMENTARY INFORMATION: This notice lists previously approved
projects, receiving approval of minor modification or a corrective
modification, described below, pursuant to 18 CFR 806.18 or to
Commission Resolution Nos. 2013-11 and 2015-06, for the time period
specified above.
1. Repsol Oil & Gas USA, LLC--Seeley Creek, Docket No. 20251216,
Wells Township, Bradford County, Pa.; modification approval to change
the passby monitoring location; Approval Date: January 8, 2026.
2. Amazon Data Services, Inc.--PHL100 Data Center, Docket No.
20251217, Salem Township, Luzerne County, Pa.; modification approval to
add sources of water for consumptive use; Approval Date: January 26,
2026.
(Authority: Public Law 91-575, 84 Stat. 1509 et seq., 18 CFR parts
806 and 808.)
Dated: January 27, 2026.
Jason E. Oyler,
General Counsel and Secretary to the Commission.
[FR Doc. 2026-01792 Filed 1-28-26; 8:45 am]