[Federal Register Volume 90, Number 247 (Wednesday, December 31, 2025)]
[Notices]
[Pages 61435-61438]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-24101]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-171; NRC-2025-1141]


Constellation Energy Generation, LLC; Peach Bottom Atomic Power 
Station, Unit 1; Exemption

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC, or Commission) 
has issued an exemption in response to a request from Constellation 
Energy Generation, LLC to allow the completion of decommissioning 
beyond 60 years of permanent cessation of operations for the Peach 
Bottom Atomic Power Station, Unit 1.

DATES: The exemption was issued on December 23, 2025.

ADDRESSES: Please refer to Docket ID NRC-2025-1141 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2025-1141. Address 
questions about Docket IDs in Regulations.gov to Bridget Curran; 
telephone: 301-415-10003; email: [email protected]. For technical 
questions, contact the individual(s) listed in the FOR FURTHER 
INFORMATION CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin ADAMS Public Search.'' 
For problems with ADAMS, please contact the NRC's Public Document Room 
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email 
to [email protected]. The ADAMS accession number for each document 
referenced (if it is available in ADAMS) is provided the first time 
that it is mentioned in this document.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

FOR FURTHER INFORMATION CONTACT: Tanya Hood, Office of Nuclear Material 
Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington 
DC 20555-0001; telephone: 301-415-1387; email: [email protected].

SUPPLEMENTARY INFORMATION: The text of the exemption is attached.

    Dated: December 29, 2025.

    For the Nuclear Regulatory Commission.
Tanya Hood,
Project Manager, Reactor Decommissioning Branch, Division of 
Decommissioning, Uranium Recovery and Waste Programs, Office of Nuclear 
Material Safety and Safeguards.

Attachment--Exemption.

NUCLEAR REGULATORY COMMISSION

Docket No. 50-171

Constellation Energy Generation, LLC

Peach Bottom Atomic Power Station, Unit 1 Exemption

I. Background

    By letter dated October 20, 2023 (Agencywide Documents Access and 
Management System Accession No. ML23293A305), as supplemented by 
letters dated May 13, 2024, and August 1, 2024 (ML24134A179 and 
ML24214A323, respectively), Constellation Energy Generation, LLC (the 
licensee), submitted a request for Peach Bottom Atomic Power Station 
Unit 1 (Peach Bottom Unit 1) that would allow the completion of 
decommissioning for Peach Bottom Unit 1 beyond 60 years of permanent 
cessation of operations.
    The Peach Bottom Atomic Power Station is in York County, PA and is 
composed of three reactor licenses: Peach Bottom Unit 1 (License No. 
DPR-12), which is presently in a long-term storage condition for a 
permanently shut down nuclear power plant, referred to as SAFSTOR and 
is the subject of this request, along with Peach Bottom Unit 2 (DPR-44) 
and Peach Bottom Unit 3 (DPR-56), which are actively operating. Peach 
Bottom Unit 1 is licensed pursuant to Section 104(b) of the Atomic 
Energy Act of 1954, as amended, and Title 10 of the Code of Federal 
Regulations (10 CFR) Part 50, Paragraph 50.82(a)(2) to possess but not 
operate the facility. Peach Bottom Unit 1 was a high-temperature gas-
cooled reactor (HTGR) that permanently ceased operations on October 31, 
1974. All Peach Bottom Unit 1 spent fuel containing special nuclear 
material was removed from the site and shipped to a U.S. Department of 
Energy facility in Idaho. Peach Bottom Unit 1 has been monitored and 
controlled in SAFSTOR in accordance with the Facility Operating 
License, Technical Specifications as amended, and Decommissioning Plan.

II. Request/Action

    The regulation at 10 CFR 50.82(a)(3) requires power reactor 
licensees to complete decommissioning within 60 years of permanent 
cessation of operations. The regulation provides that completion of 
decommissioning beyond 60 years will be considered by the U.S. Nuclear 
Regulatory Commission (NRC or Commission) only when necessary to 
protect public health and safety, with site-specific factors considered 
when reviewing such requests, including the presence of other nuclear 
facilities at the site.
    The licensee requested an alternative to the 60 year 
decommissioning schedule requirements in 10 CFR 50.82(a)(3) to 
decommission Peach Bottom Unit 1 to coincide with the eventual 
decommissioning of Peach Bottom Units 2 and 3. The licensee stated its 
alternative request ``meets the evaluation factors in 10 CFR 
50.82(a)(3) due to the potential impact on public health and safety 
with other nuclear facilities present at the site'' and that ``[t]his 
request is to allow [the licensee] to complete the decommissioning of 
[Peach Bottom], Unit 1, in a time frame more suitable with the 
decommissioning of [Peach Bottom], Units 2 and 3, in order to reduce 
the overall risk and increase the margin to public health and safety.''
    The licensee is requesting that the decommissioning schedule for 
Peach

[[Page 61436]]

Bottom Unit 1 be completed no later than 20 years following the 
permanent shutdown of Peach Bottom Units 2 and 3, pending a decision to 
modify the expiration dates for Peach Bottom's subsequent renewed 
facility operating licenses DPR-44 and DPR-56 for Peach Bottom Units 2 
and 3, per an application dated July 10, 2018 (ML18193A689). On March 
5, 2020, the NRC issued subsequent renewed facility operating licenses 
for Peach Bottom (ML20010F285), which included the expiration dates of 
August 8, 2053, for Peach Bottom Unit 2 and July 2, 2054, for Peach 
Bottom Unit 3. On February 2022, in CLI-22-04 (ML22055A557), the 
Commission determined that the environmental review associated with 
that licensing action was incomplete and therefore directed the NRC 
staff to complete this environmental review and to change the licenses' 
expiration dates to match the expiration dates of the previous licenses 
until the completion of the environmental review. Therefore, on March 
25, 2022 (ML22073A193), in accordance with the Commission's direction, 
the NRC staff modified the expiration dates of these subsequent renewed 
licenses to reflect the end dates of the previous renewed licenses. On 
September 30, 2025 (ML25209A020), the NRC staff issued its decision to 
restore the end dates of the subsequent renewed licenses for Peach 
Bottom Atomic Power Station, Units 2 and 3 to August 8, 2053, and to 
July 2, 2054, respectively.
    To support its review of the request for an alternative 
decommissioning schedule, the NRC staff conducted a regulatory audit of 
the application onsite at the Peach Bottom Atomic Power Station. The 
NRC staff issued an audit plan to the licensee on March 28, 2024 
(ML24088A318), which provided the scope of the audit.

III. Discussion

    Under 10 CFR 50.82(a)(3), the Commission will approve an 
alternative that provides for completion of decommissioning beyond 60 
years of permanent cessation of operations only when necessary to 
protect public health and safety. In evaluating whether an alternative 
is necessary, the regulations provide that the NRC will consider 
factors such as unavailability of waste disposal capacity; or other 
site-specific factors affecting the licensee's capability to carry out 
decommissioning, including presence of other nuclear facilities at the 
site. Prior to this request for an alternative decommissioning 
schedule, Peach Bottom, Unit 1, was required to complete 
decommissioning by October 31, 2034.
    The NRC staff's approach in evaluating the 10 CFR 50.82(a)(3) 
criteria is documented, in part, in SECY-24-0073, ``Site-Specific 
Considerations for Review of Requests to Complete Power Reactor 
Decommissioning Beyond 60 Years from Permanent Cessation of 
Operations,'' dated September 3, 2024 (ML24100A760). In conducting the 
Peach Bottom review, which was the first time the NRC staff applied the 
approach outlined in the SECY, the NRC staff remained mindful of the 
approach outlined, and also applied additional risk insights and site-
specific considerations, as explained in SECY-25-0095, ``Staff's 
Planned Approval of Peach Bottom Atomic Power Station Unit 1 Exemption 
Request for Alternative Decommissioning Schedule,'' dated December 10, 
2025 (ML25150A317). The NRC has determined that the licensee has met 
the ``only when necessary to protect public health and safety'' 
criterion because the licensee showed that Peach Bottom Unit 1 
decommissioning activities could result in site-specific impacts on 
public health and safety due to the increased risk to systems and 
structures supporting the adjacent operating Peach Bottom Units 2 and 
3.

Presence of Other Nuclear Facilities

    The licensee's request for an alternative decommissioning schedule 
was based on the potential impacts to public health and safety from 
decommissioning Peach Bottom Unit 1 while there are two other operating 
nuclear facilities at the site. In support of its exemption request, 
the licensee noted that many portions of the original Peach Bottom Unit 
1 facilities have been refurbished to support ongoing power operations 
support functions at Peach Bottom Units 2 and 3. Specifically, the 
Peach Bottom Technical Support Center (TSC) and Control Room Simulator 
support regulatory required functions for the operating units at the 
site for Emergency Planning and Operations Training, respectively. The 
licensee also indicated that there are interconnectivity issues between 
the operational support facilities (i.e., the TSC, Control Room 
Simulator, and administration building) and portions of Peach Bottom 
Unit 1 site. The buildings housing these functions are not within 
radiological areas of Peach Bottom Unit 1, and thus, are not within the 
scope of decommissioning for license termination. However, the licensee 
stated that portions of the facilities are physically attached to the 
Peach Bottom Unit 1 containment structure, which is within a 
radiologically controlled area boundary and which the licensee 
indicates would need to be decommissioned to terminate the Peach Bottom 
Unit 1 license. Therefore, the licensee states that decommissioning the 
attached containment structure could impact the TSC and Control Room 
Simulator, and their use by Peach Bottom Units 2 and 3, due to their 
current location on the Peach Bottom Unit 1 footprint near the Peach 
Bottom Unit 1 reactor.
    Additionally, the licensee notes other connectivity impacts of 
decommissioning Peach Bottom Unit 1 while Peach Bottom Units 2 and 3 
continue to operate. The Peach Bottom Unit 1 footprint that must be 
decommissioned does not have any systems, structures, or components 
(SSCs) important to safety that are shared between Peach Bottom Unit 1 
and Peach Bottom Units 2 and 3. However, the licensee's audit response 
explains that accessing the systems for removal in the containment 
structure at Peach Bottom Unit 1 would pose challenges due to the 
proximity and location of the administration building. In its audit 
response and with regard to impacts, the licensee explained that, 
``while the adjacent administrative/training buildings to the east and 
south are not radiologically controlled or within the scope of 
decommissioning for license termination, elimination of these 
interfacing interferences following [Peach Bottom Units 2 and 3] 
operations would improve the access and ability to perform safe 
decommissioning of the containment building and internal SSCs. Physical 
space for an adequate confinement structure and associated engineered 
controls, including ventilation and radiological monitoring, are 
critical aspects of performing decommissioning activities related to 
the graphite components within the reactor vessel of this HTGR.''
    Also, the containment building at the Peach Bottom Unit 1 facility 
contains the radioactive reactor vessel, reactor internals, and 
graphite, and consists of a 100-foot diameter steel containment vessel 
reinforced by stiffening rings with a concrete floor. The steel 
containment vessel is on an approximately 3-foot-thick concrete 
foundation constructed on bedrock. The containment building is an 
important component because the containment building performs a safety 
function in confining radioactive material so that there is no 
exceedance of the radiation protection requirements outlined in 10 CFR 
part 20. The licensee's SAFSTOR program will continue for the extended 
period of decommissioning and the licensee should update its program

[[Page 61437]]

accordingly. For the period beyond 60 years, the NRC will continue its 
inspection of the SAFSTOR program as outlined in the Updated Final 
Safety Analysis Report, technical specifications, and licensee 
procedures, including the material condition of the Peach Bottom Unit 1 
buildings, such as the Unit 1 containment.
    In evaluating this information, the NRC staff determined that the 
licensee presented a reasonable argument that the proximity of Peach 
Bottom Units 2 and 3, and specifically, the support facilities 
associated with them in relation to the decommissioning facility, is a 
site-specific factor that affects the licensee's capability to safely 
carry out decommissioning. The NRC staff agrees that the proximity of 
the support facilities to Peach Bottom Unit 1 is likely to impact the 
manner in which the licensee would decommission Peach Bottom Unit 1 
such that the overall risk to the public health and safety due to 
decommissioning would likely be decreased if the decommissioning of 
Peach Bottom Unit 1 occurred after Peach Bottom Units 2 and 3 were no 
longer operating. Because of this, the NRC staff concludes that the 
presence of these other nuclear facilities impacts the method in which 
the licensee could reduce risk during decommissioning. Therefore, 
pursuant to 10 CFR 50.82(a)(3), the NRC staff agrees that the 
interconnectivity of the support structures at the Peach Bottom Atomic 
Power Station supports an alternative decommissioning schedule.

Capacity and Capability of the Power Systems

    The licensee also raised concerns with potential impacts to the 
electric systems if Peach Bottom Unit 1 were required to decommission 
on the original 60-year schedule. According to the licensee, the Peach 
Bottom Unit 1 electrical distribution system, as originally designed, 
has mostly been abandoned during initial decommissioning activities, 
including all generation-related and reactor-related SSCs, or has been 
modified to support current functions. The 220-08 Line was originally 
the grid connection for Peach Bottom Unit 1 commercial operation. The 
configuration was an assortment of electromechanical protective relays 
and a transfer trip system linked to the nearest switchyards on PECO's 
220-08 230kV Line. When Peach Bottom Unit 1 ceased operation in 1974, 
the 220-08 Line remained and became an offsite source for Peach Bottom 
Units 2 and 3.
    The licensee's letter dated October 20, 2023, stated that Peach 
Bottom Unit 1 houses the North American Electric Reliability 
Corporation (NERC) required protective relay scheme SSCs for one of the 
credited offsite power sources necessary for Peach Bottom Units 2 and 
3. The licensee indicated that decommissioning Peach Bottom Unit 1 
challenges the 220-08 Line offsite power source that is credited for an 
offsite power source for Peach Bottom Units 2 and 3, which potentially 
increases the risk to public health and safety. Additionally, the 
licensee further stated in its letter dated May 13, 2024, that the 220-
08 Line protective scheme affects the reliability of Bulk Electric 
System, known as the grid. The 220-08 Line protective scheme detects 
faults on grid components such as lines, buses, transformers, etc., 
and, therefore, is within the scope of NERC Standard PRC-005-6, 
``Protection System, Automatic Reclosing, and Sudden Pressure Relaying 
Maintenance.''
    The NRC staff evaluated the applicable NERC standards that pertain 
to the electrical power system. The NRC staff determined that the 
applicable 220-08 Protection System components such as the protective 
relays, communication systems, sensing devices, DC supply and control 
circuitry are required to meet the maintenance activities required by 
NERC Standard PRC-005-6. Moreover, the NRC staff identified additional 
support for the licensee's claim that Peach Bottom Units 2 and 3 rely 
upon the 220-08 Protective System components, which are located at Unit 
1, for an offsite power source in the Peach Bottom Units 2 and 3 
Updated Final Safety Analysis Report (UFSAR) (ML23110A266). The UFSAR 
states: ``Each offsite source can be used to supply the unit auxiliary 
buses for plant startup and shutdown and the cooling tower equipment. . 
. . Every 4 kV emergency switchgear bus is energized from one of these 
two sources at all times during normal operation. . . .''
    Because power to Peach Bottom Unit 1 electrical systems and 
components is provided by onsite standby power supplies as well, the 
NRC staff evaluated the onsite power systems. The licensee explained, 
in its letter dated May 13, 2024, that for onsite power, Peach Bottom 
Unit 1 is currently equipped with a 125V direct current (DC) battery, 
10D465, which is the former Peach Bottom Unit 1 station battery, and 
the licensee performs maintenance and testing in accordance with 
station procedures and in compliance with NERC Standard PRC-005-6.
    Based on this information, the NRC staff agrees that 
decommissioning of Peach Bottom Unit 1 would impact the capacity and 
capability of the power systems (offsite and onsite power). Therefore, 
pursuant to 50.82(a)(3), the capacity and capability of the power 
systems at the Peach Bottom Atomic Power Station is a factor that, in 
combination with other factors discussed above, supports an alternative 
decommissioning schedule.

IV. Environmental Review Under the National Environmental Policy Act

    The NRC staff has determined that the proposed exemption can be 
categorically excluded under 10 CFR 51.22(c)(25) from NRC requirements 
to conduct an environmental assessment or an environmental impact 
statement. The categorical exclusion in 10 CFR 51.22(c)(25) states that 
the granting of an exemption from the requirements of any NRC 
regulation may be categorically excluded as long as the conditions of 
51.22(c)(25)(i)-(vi) are met.
    In this instance, the NRC staff determined all the conditions of 
51.22(c)(25)(i)-(v) have been satisfied. Approving this exemption would 
not: result in conditions that could significantly increase the 
probability or consequences of an accident previously evaluated or 
create the possibility of a new or different kind of accident; result 
in a significant change in the types or a significant increase in the 
amounts of any effluents that may be released offsite; result in 
increases to public and occupational radiation exposure; result in a 
significant construction impact; or result in a significant increase in 
the potential for or consequences from radiological accidents. Approval 
in this instance only continues the current status and activities at 
the facility. During the duration of the decommissioning delay, the 
licensee will maintain Peach Bottom Unit 1 in SAFSTOR condition in 
accordance with the technical specifications for Peach Bottom Unit 1, 
and the licensee will continue ongoing monitoring activities, such as 
regular radiological surveys, use of monitoring wells, inspections for 
(and any needed management of) groundwater intrusion into the 
containment, and inspections of facility conditions.
    Finally, the NRC staff has determined that the request satisfies 
51.22(c)(25)(vi) because the exemption applies to the following 
specific activities associated with Peach Bottom Unit 1 that support 
the continued maintenance of Peach Bottom Unit 1 in SAFSTOR into the 
period approved in the alternative decommissioning schedule: (A) 
recordkeeping requirements; (B) reporting requirements; (C) inspection

[[Page 61438]]

and surveillance requirements; (D) equipment servicing or maintenance 
scheduling requirements; (F) Safeguard plans, and materials control, 
and (G) scheduling requirements.
    Based on the above assessment, in accordance with 10 CFR 51.22(b), 
no environmental impact statement or environmental assessment need be 
prepared in connection with the NRC's consideration of this exemption 
request.

VII. Conclusions

    For the reasons described above, the NRC concludes that, pursuant 
to 10 CFR 50.82(a)(3), there are site-specific factors affecting the 
licensee's capability to carry out decommissioning at Peach Bottom Unit 
1 because of the presence of the operating units at the site such that 
an alternative decommissioning schedule is necessary to protect public 
health and safety. The NRC's determination is based on the multiple 
connections that exist between Peach Bottom Unit 1 and the operating 
Peach Bottom Units 2 and 3 at this site, including the presence of the 
nuclear facilities (Peach Bottom Units 2 and 3 support buildings) 
located on the Peach Bottom Unit 1 footprint and the need for its 
continued use by Peach Bottom Units 2 and 3, and the electric power 
connection at Peach Bottom Unit 1 that is utilized as one of the 
primary power sources of offsite power for Peach Bottom Units 2 and 3.
    Therefore, the NRC grants Constellation Energy Generation, Inc., a 
one-time exemption from 10 CFR 50.82(a)(3) to allow the licensee an 
alternative decommissioning schedule that requires the decommissioning 
of Peach Bottom Unit 1, 20 years after the permanent cessation of 
operations of either Peach Bottom Units 2 or 3, whichever is earlier, 
and in no case beyond 2074. With this approval, the licensee's SAFSTOR 
program will continue for the extended period of decommissioning and 
the licensee should update its program accordingly. For the period 
beyond 60 years, the NRC will continue its inspection of the SAFSTOR 
program as outlined in the Updated Final Safety Analysis Report, 
technical specifications, and licensee procedures, including the 
material condition of the Peach Bottom Unit 1 buildings, such as the 
Unit 1 containment.
    The exemption will be effective upon issuance.

    Dated: this 23rd day of December 2025.

    For the Nuclear Regulatory Commission.

/RA/

Jane Marshall,

Director, Division of Decommissioning, Uranium Recovery, and Waste 
Programs, Office of Nuclear Material Safety and Safeguards.

[FR Doc. 2025-24101 Filed 12-30-25; 8:45 am]
BILLING CODE 7590-01-P