[Federal Register Volume 90, Number 241 (Thursday, December 18, 2025)]
[Notices]
[Pages 59108-59110]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-23224]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP26-17-000]


Leaf River Energy Center LLC; Notice of Scoping Period Requesting 
Comments on Environmental Issues for the Proposed Leaf River Capacity 
Expansion Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental document that will discuss 
the environmental impacts of the Leaf River Capacity Expansion Project 
(Project) involving construction and operation of facilities by Leaf 
River Energy Center LLC (LREC) in Smith, Jasper, and Clarke counties, 
Mississippi. The Commission will use this environmental document in its 
decision-making process to determine whether the project is in the 
public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies regarding the project. As part of the National Environmental 
Policy Act (NEPA) review process, the Commission takes into account 
concerns the public may have about proposals and the environmental 
impacts that could result from its action whenever it considers the 
issuance of a Certificate of Public Convenience and Necessity. This 
gathering of public input is referred to as ``scoping.'' The main goal 
of the scoping process is to focus the analysis in the environmental 
document on the important environmental issues. Additional information 
about the Commission's NEPA process is described below in the NEPA 
Process and Environmental Document section of this notice.
    By this notice, the Commission requests public comments on the 
scope of issues to address in the environmental document. To ensure 
that your comments are timely and properly recorded, please submit your 
comments so that the Commission receives them in Washington, DC on or 
before 5:00 p.m. Eastern Time on January 12, 2026. Comments may be 
submitted in written form. Further details on how to submit comments 
are provided in the Public Participation section of this notice.
    Your comments should focus on the potential environmental effects, 
reasonable alternatives, and measures to avoid or lessen environmental 
impacts. Your input will help the Commission staff determine what 
issues they need to evaluate in the environmental document. Commission 
staff will consider all written comments during the preparation of the 
environmental document.
    If you submitted comments on this project to the Commission before 
the opening of this docket on October 31, 2025, you will need to file 
those comments in Docket No. CP26-17-000 to ensure they are considered 
as part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable easement agreement. You 
are not required to enter into an agreement.

[[Page 59109]]

However, if the Commission approves the project, the Natural Gas Act 
conveys the right of eminent domain to the company. Therefore, if you 
and the company do not reach an easement agreement, the pipeline 
company could initiate condemnation proceedings in court. In such 
instances, compensation would be determined by a judge in accordance 
with state law. The Commission does not subsequently grant, exercise, 
or oversee the exercise of that eminent domain authority. The courts 
have exclusive authority to handle eminent domain cases; the Commission 
has no jurisdiction over these matters.
    LREC provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?'' which addresses typically asked questions, including 
the use of eminent domain and how to participate in the Commission's 
proceedings. This fact sheet along with other landowner topics of 
interest are available for viewing on the FERC website (www.ferc.gov) 
under the Natural Gas, Landowner Topics link.

Public Participation

    There are three methods you can use to submit your comments to the 
Commission. Please carefully follow these instructions so that your 
comments are properly recorded. The Commission encourages electronic 
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. Using eComment is an easy method for 
submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the project docket number (CP26-
17-000) on your letter. Submissions sent via the U.S. Postal Service 
must be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, MD 20852.
    Additionally, the Commission offers a free service called 
eSubscription which makes it easy to stay informed of all issuances and 
submittals regarding the dockets/projects to which you subscribe. These 
instant email notifications are the fastest way to receive notification 
and provide a link to the document files which can reduce the amount of 
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    For public inquiries and assistance with making filings such as 
interventions, comments, or requests for rehearing, contact the Office 
of Public Participation at (202) 502-6595 or [email protected].

Summary of the Proposed Project

    LREC proposes to expand existing natural gas storage caverns and 
create a new natural gas storage cavern. The Leaf River Capacity 
Expansion Project would allow LREC to increase the certificated natural 
gas storage capacity at its existing New Home Salt Dome storage 
facility by 17.62 billion cubic feet (``Bcf''). According to LREC, the 
project would help satisfy market demand for incremental natural gas 
storage and is needed to provide critical natural gas grid reliability, 
and to help reduce price volatility and physical supply and demand 
imbalances in the Gulf Coast natural gas market.
    The Leaf River Capacity Expansion Project would consist of the 
following facilities:
     one new salt dome cavern with 12.52 billion cubic feet of 
working gas capacity, a well pad site, wellhead equipment, and other 
pipeline appurtenances;
     a new service corridor that includes 16-inch- and 24-inch-
diameter gas headers, 16-inch-diameter raw water and brine lines, and 
appurtenant facilities connecting to the new cavern well;
     two new gas-powered centrifugal compressors with a total 
of 27,010 horsepower (hp) at an existing compression facility; and
     installation of a 6,130 hp gas-powered centrifugal 
compressor within the existing fence line of a booster station.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary.'' For instructions on 
connecting to eLibrary, refer to the last page of this notice. For 
assistance, contact FERC at [email protected] or call toll 
free, (886) 208-3676 or TTY (202) 502-8659.
---------------------------------------------------------------------------

Land Requirements for Construction

    Constructing the proposed facilities would disturb about 32.0 acres 
of land. Following construction, LREC would maintain about 18.0 acres 
of land for permanent operation of the proposed facilities, and the 
remaining acreage would be restored and be allowed to revert to former 
uses.

NEPA Process and the Environmental Document

    Any environmental document issued by the Commission will discuss 
impacts that could occur as a result of the construction and operation 
of the proposed project under the relevant general resource areas:
     geology and soils;
     water resources and wetlands;
     vegetation and wildlife;
     threatened and endangered species;
     cultural resources;
     land use;
     air quality and noise; and
     reliability and safety.
    Commission staff will also evaluate reasonable alternatives to the 
proposed project or portions of the project and make recommendations on 
how to lessen or avoid impacts on the various resource areas. Your 
comments will help Commission staff identify and focus on the issues 
that might have an effect on the human environment and potentially 
eliminate others from further study and discussion in the environmental 
document.
    Following this scoping period, Commission staff will determine 
whether to prepare an Environmental Assessment (EA) or an Environmental 
Impact Statement (EIS). The EA or the EIS will present Commission 
staff's independent analysis of the issues. If Commission staff 
prepares an EA, a Notice of Schedule for the Preparation of an 
Environmental Assessment will be issued. The EA may be issued for an 
allotted public comment period. The Commission would consider timely 
comments on the EA before making its decision regarding the proposed 
project. If Commission staff prepares an EIS, a Notice of Intent to 
Prepare an EIS/Notice of Schedule will be issued, which will open up an 
additional comment period. Staff will then prepare

[[Page 59110]]

a draft EIS which will be issued for public comment. Commission staff 
will consider all timely comments received during the comment period on 
the draft EIS and revise the document, as necessary, before issuing a 
final EIS. Any EA or draft and final EIS will be available in 
electronic format in the public record through eLibrary \2\ and the 
Commission's natural gas environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If eSubscribed, you will receive instant email notification 
when the environmental document is issued.
---------------------------------------------------------------------------

    \2\ For instructions on connecting to eLibrary, refer to the 
last page of this notice.
---------------------------------------------------------------------------

    With this notice, the Commission is asking agencies with 
jurisdiction by law and/or special expertise with respect to the 
environmental issues of this project to formally cooperate in the 
preparation of the environmental document.\3\ Agencies that would like 
to request cooperating agency status should follow the instructions for 
filing comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ Cooperating agency responsibilities are addressed in Section 
107(a)(3) of NEPA (42 U.S.C. 4336(a)(3)).
---------------------------------------------------------------------------

Consultation Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, the Commission is using this notice to initiate 
consultation with the applicable State Historic Preservation Office(s), 
and to solicit their views and those of other government agencies, 
interested Indian tribes, and the public on the project's potential 
effects on historic properties.\4\ The environmental document for this 
project will document findings on the impacts on historic properties 
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project and includes a mailing address with their 
comments. Commission staff will update the environmental mailing list 
as the analysis proceeds to ensure that Commission notices related to 
this environmental review are sent to all individuals, organizations, 
and government entities interested in and/or potentially affected by 
the proposed project.
    If you need to make changes to your name/address, or if you would 
like to remove your name from the mailing list, please complete one of 
the following steps:
    (1) Send an email to [email protected] stating your 
request. You must include the docket number CP26-17-000 in your 
request. If you are requesting a change to your address, please be sure 
to include your name and the correct address. If you are requesting to 
delete your address from the mailing list, please include your name and 
address as it appeared on this notice. This email address is unable to 
accept comments.
    OR
    (2) Return the attached ``Mailing List Update Form'' (appendix 2).

Additional Information

    Additional information about the project is available from the FERC 
website at www.ferc.gov using the eLibrary link. Click on the eLibrary 
link, click on ``General Search'' and enter the docket number in the 
``Docket Number'' field. Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
[email protected] or (866) 208-3676, or for TTY, contact (202) 
502-8659. The eLibrary link also provides access to the texts of all 
formal documents issued by the Commission, such as orders, notices, and 
rulemakings.
    Public sessions or site visits will be posted on the Commission's 
calendar located at https://www.ferc.gov/news-events/events along with 
other related information.

(Authority: 18 CFR 2.1)

    Dated: December 12, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-23224 Filed 12-17-25; 8:45 am]
BILLING CODE 6717-01-P