[Federal Register Volume 90, Number 229 (Tuesday, December 2, 2025)]
[Notices]
[Pages 55321-55325]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-21747]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2025-1172]


Applications for Amendments to Facility Operating Licenses 
Involving Proposed No Significant Hazards Consideration Determination 
and Containing Sensitive Unclassified Non-Safeguards Information and 
Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information

AGENCY: Nuclear Regulatory Commission.

ACTION: License amendment request; notice of opportunity to comment, 
request a hearing, and petition for leave to intervene; order imposing 
procedures.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC, the Commission) 
received, and is considering approval of, two amendment requests. The 
amendment requests are for Indian Point Station, Unit Nos. 1, 2 and 3; 
and Salem Nuclear Generating Station, Unit Nos. 1 and 2. For each 
amendment request, the NRC proposes to determine that it involves no 
significant hazards consideration (NSHC). Because each amendment 
request contains sensitive unclassified non-safeguards information 
(SUNSI), the NRC is issuing an order imposing procedures to obtain 
access to SUNSI for contention preparation by persons who file a 
hearing request or petition for leave to intervene.

DATES: Comments must be received by January 2, 2026. A request for a 
hearing or a petition for leave to intervene must be filed by February 
2, 2026. Any potential party as defined in section 2.4 of title 10 of 
the Code of Federal Regulations (10 CFR) who believes access to SUNSI 
is necessary to respond to this notice must request document access by 
December 12, 2025.

ADDRESSES: You may submit comments by any of the following methods; 
however, the NRC encourages electronic comment submission through the 
Federal rulemaking website.
     Federal rulemaking website: Go to https://www.regulations.gov and search for Docket ID NRC-2025-1172. Address 
questions about Docket IDs in Regulations.gov to Bridget Curran; 
telephone: 301-415-1003; email: [email protected]. For technical 
questions, contact the individual(s) listed in the FOR FURTHER 
INFORMATION CONTACT section of this document.
     Mail comments to: Office of Administration, Mail Stop: 
TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, ATTN: Program Management, Announcements and Editing Staff.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Angela Baxter, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-8209; email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2025-1172, facility name, unit 
numbers, docket numbers, application date, and subject when contacting 
the NRC about the availability of information for this action. You may 
obtain publicly available information related to this action by any of 
the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2025-1172.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin ADAMS Public Search.'' 
For problems with ADAMS, please contact the NRC's Public Document Room 
(PDR) reference staff at 1-800-397-4209, at 301-415-4737, or by email 
to [email protected]. The ADAMS accession number for each document 
referenced (if it is available in ADAMS) is provided the first time 
that it is mentioned in this document.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

B. Submitting Comments

    The NRC encourages electronic comment submission through the 
Federal rulemaking website (https://www.regulations.gov). Please 
include Docket ID NRC-2025-1172, facility name, unit number(s), docket 
number(s), application date, and subject, in your comment submission.

[[Page 55322]]

    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC will post all comment submissions at 
https://www.regulations.gov as well as enter the comment submissions 
into ADAMS. The NRC does not routinely edit comment submissions to 
remove identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment into ADAMS.

II. Background

    Pursuant to section 189a.(1)-(2) of the Atomic Energy Act of 1954, 
as amended (the Act), the NRC is publishing this notice. The Act 
requires the Commission to publish notice of any amendments issued or 
proposed to be issued and grants the Commission the authority to issue 
and make immediately effective any amendment to an operating license or 
combined license, as applicable, upon a determination by the Commission 
that such amendment involves NSHC, notwithstanding the pendency before 
the Commission of a request for a hearing from any person.
    This notice includes notices of amendments containing SUNSI.

III. Notice of Consideration of Issuance of Amendments to Facility 
Operating Licenses, Proposed No Significant Hazards Consideration 
Determination, and Opportunity for a Hearing

    The Commission has made a proposed determination that the following 
amendment requests involve NSHC. Under the Commission's regulations in 
10 CFR 50.92, this means that operation of the facility in accordance 
with the proposed amendments would not (1) involve a significant 
increase in the probability or consequences of an accident previously 
evaluated, or (2) create the possibility of a new or different kind of 
accident from any accident previously evaluated, or (3) involve a 
significant reduction in a margin of safety. The basis for this 
proposed determination for each amendment request is shown as follows.
    The Commission is seeking public comments on these proposed 
determinations. Any comments received within 30 days after the date of 
publication of this notice will be considered in making any final 
determination.
    Normally, the Commission will not issue the amendments until the 
expiration of 60 days after the date of publication of this notice. The 
Commission may issue any of these license amendments before expiration 
of the 60-day period provided that its final determination is that the 
amendments involve no significant hazards consideration. In addition, 
the Commission may issue any of these amendments prior to the 
expiration of the 30-day comment period if circumstances change during 
the 30-day comment period such that failure to act in a timely way 
would result, for example, in derating or shutdown of the facility. If 
the Commission takes action on any of these amendments prior to the 
expiration of either the comment period or the notice period, it will 
publish a notice of issuance in the Federal Register. If the Commission 
makes a final no significant hazards consideration determination for 
any of these amendments, any hearing on those amendments will take 
place after issuance. The Commission expects that the need to take this 
action will occur very infrequently.

A. Opportunity To Request a Hearing and Petition for Leave To Intervene

    Within 60 days after the date of publication of this notice, any 
person (petitioner) whose interest may be affected by any of these 
actions may file a request for a hearing and petition for leave to 
intervene (petition) with respect to that action. Petitions shall be 
filed in accordance with the Commission's ``Agency Rules of Practice 
and Procedure'' in 10 CFR part 2. Interested persons should consult a 
current copy of 10 CFR 2.309. If a petition is filed, the Commission or 
a presiding officer will rule on the petition and, if appropriate, a 
notice of a hearing will be issued.
    Petitions must be filed no later than 60 days from the date of 
publication of this notice in accordance with the filing instructions 
in the ``Electronic Submissions (E-Filing)'' section of this document. 
Petitions and motions for leave to file new or amended contentions that 
are filed after the deadline will not be entertained absent a 
determination by the presiding officer that the filing demonstrates 
good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i) 
through (iii).
    If a hearing is requested, and the Commission has not made a final 
determination on the issue of no significant hazards consideration, the 
Commission will make a final determination on the issue of no 
significant hazards consideration, which will serve to establish when 
the hearing is held. If the final determination is that the amendment 
request involves no significant hazards consideration, the Commission 
may issue the amendment and make it immediately effective, 
notwithstanding the request for a hearing. Any hearing would take place 
after issuance of the amendment. If the final determination is that the 
amendment request involves a significant hazards consideration, then 
any hearing held would take place before the issuance of the amendment 
unless the Commission finds an imminent danger to the health or safety 
of the public, in which case it will issue an appropriate order or rule 
under 10 CFR part 2.
    A State, local governmental body, Federally recognized Indian 
Tribe, or designated agency thereof, may submit a petition to the 
Commission to participate as a party under 10 CFR 2.309(h) no later 
than 60 days from the date of publication of this notice. 
Alternatively, a State, local governmental body, Federally recognized 
Indian Tribe, or agency thereof may participate as a non-party under 10 
CFR 2.315(c).
    For information about filing a petition and about participation by 
a person not a party under 10 CFR 2.315, see ADAMS Accession No. 
ML20340A053 (https://adamswebsearch2.nrc.gov/webSearch2/main.jsp?AccessionNumber=ML20340A053) and on the NRC's public website 
at https://www.nrc.gov/about-nrc/regulatory/adjudicatory/hearing.html#participate.

B. Electronic Submissions (E-Filing)

    All documents filed in NRC adjudicatory proceedings, including 
documents filed by an interested State, local governmental body, 
Federally recognized Indian Tribe, or designated agency thereof that 
requests to participate under 10 CFR 2.315(c), must be filed in 
accordance with 10 CFR 2.302. The E-Filing process requires 
participants to submit and serve all adjudicatory documents over the 
internet, or in some cases, to mail copies on electronic storage media, 
unless an exemption permitting an alternative filing method, as further 
discussed, is granted. Detailed guidance on electronic submissions is 
located in the ``Guidance for Electronic Submissions to the NRC'' 
(ADAMS Accession No. ML13031A056), and on the NRC's public website 
(https://www.nrc.gov/site-help/e-submittals.html).

[[Page 55323]]

    To comply with the procedural requirements of E-Filing, at least 10 
days prior to the filing deadline, the participant should contact the 
Office of the Secretary by email at [email protected], or by 
telephone at 301-415-1677, to: (1) request a digital identification 
(ID) certificate which allows the participant (or its counsel or 
representative) to digitally sign submissions and access the E-Filing 
system for any proceeding in which it is participating; and (2) advise 
the Secretary that the participant will be submitting a petition or 
other adjudicatory document (even in instances in which the 
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the 
Secretary will establish an electronic docket for the proceeding if the 
Secretary has not already established an electronic docket.
    Information about applying for a digital ID certificate is 
available on the NRC's public website at https://www.nrc.gov/site-help/e-submittals/getting-started.html. After a digital ID certificate is 
obtained and a docket is created, the participant must submit 
adjudicatory documents in the Portable Document Format. Guidance on 
submissions is available on the NRC's public website at https://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing is 
considered complete at the time the document is submitted through the 
NRC's E-Filing system. To be timely, an electronic filing must be 
submitted to the E-Filing system no later than 11:59 p.m. ET on the due 
date. Upon receipt of a transmission, the E-Filing system time-stamps 
the document and sends the submitter an email confirming receipt of the 
document. The E-Filing system also distributes an email that provides 
access to the document to the NRC's Office of the General Counsel and 
any others who have advised the Office of the Secretary that they wish 
to participate in the proceeding, so that the filer need not serve the 
document on those participants separately. Therefore, applicants and 
other participants (or their counsel or representative) must apply for 
and receive a digital ID certificate before adjudicatory documents are 
filed in order to obtain access to the documents via the E-Filing 
system.
    A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC's Electronic 
Filing Help Desk through the ``Contact Us'' link located on the NRC's 
public website at https://www.nrc.gov/site-help/e-submittals.html, by 
email to [email protected], or by a toll-free call at 1-866-672-
7640. The NRC Electronic Filing Help Desk is available between 9 a.m. 
and 6 p.m., ET, Monday through Friday, except Federal holidays.
    Participants who believe that they have good cause for not 
submitting documents electronically must file an exemption request, in 
accordance with 10 CFR 2.302(g), with their initial paper filing 
stating why there is good cause for not filing electronically and 
requesting authorization to continue to submit documents in paper 
format. Such filings must be submitted in accordance with 10 CFR 
2.302(b)-(d). Participants filing adjudicatory documents in this manner 
are responsible for serving their documents on all other participants. 
Participants granted an exemption under 10 CFR 2.302(g)(2) must still 
meet the electronic formatting requirement in 10 CFR 2.302(g)(1), 
unless the participant also seeks and is granted an exemption from 10 
CFR 2.302(g)(1).
    Documents submitted in adjudicatory proceedings will appear in the 
NRC's electronic hearing docket, which is publicly available at https://adams.nrc.gov/ehd, unless otherwise excluded pursuant to an order of 
the presiding officer. If you do not have an NRC-issued digital ID 
certificate as previously described, click ``cancel'' when the link 
requests certificates and you will be automatically directed to the 
NRC's electronic hearing docket where you will be able to access any 
publicly available documents in a particular hearing docket. 
Participants are requested not to include personal privacy information 
such as social security numbers, home addresses, or personal phone 
numbers in their filings unless an NRC regulation or other law requires 
submission of such information. With respect to copyrighted works, 
except for limited excerpts that serve the purpose of the adjudicatory 
filings and would constitute a Fair Use application, participants 
should not include copyrighted materials in their submission.
    The following table provides the nuclear power plant names, docket 
numbers, dates of application, ADAMS accession numbers, and locations 
in the application of the licensees' proposed NSHC determination. For 
further details with respect to these license amendment applications, 
see the applications for amendment, publicly available portions of 
which are available for public inspection in ADAMS. For additional 
direction on accessing information related to this document, see the 
``Obtaining Information and Submitting Comments'' section of this 
document.
    The following table provides the plant names, docket numbers, date 
of application, ADAMS accession number, and location in the application 
of the licensee's proposed NSHC determination. For further details with 
respect to these license amendment applications, see the applications 
for amendment, publicly available portions of which are available for 
public inspection in ADAMS. For additional direction on accessing 
information related to this document, see the ``Obtaining Information 
and Submitting Comments'' section of this document.

 Holtec Decommissioning International, LLC, Holtec Indian Point 2, LLC,
and Holtec Indian Point 3, LLC; Indian Point Station, Unit Nos. 1, 2 and
                        3; Westchester County, NY
------------------------------------------------------------------------
Docket Nos......................  50-247, 50-286, 50-003.
Application Date................  July 23, 2025.
ADAMS Accession No..............  ML25231A152.
Location in Application of NSHC.  Pages 9-12 of the Enclosure.
Brief Description of Amendments.  The proposed amendment requests from
                                   Holtec Decommissioning International,
                                   LLC, for Indian Point Energy Center
                                   (collectively consists of Indian
                                   Point Station, Unit Nos. 1, 2, and 3)
                                   would terminate the NRC preemption
                                   authority at the Indian Point Energy
                                   Center.
Proposed Determination..........  NSHC.
Name of Attorney for Licensee,    Erin Connolly, Corporate Counsel--
 Mailing Address.                  Legal, Holtec International, Krishna
                                   P. Singh Technology Campus, 1 Holtec
                                   Blvd., Camden, NJ 08104.
NRC Project Manager, Telephone    Amy Snyder, 301-415-6822.
 Number.
------------------------------------------------------------------------
 PSEG Nuclear LLC; Salem Nuclear Generating Station, Unit Nos. 1 and 2;
                            Salem County, NJ
------------------------------------------------------------------------
Docket Nos......................  50-272, 50-311.

[[Page 55324]]

 
Application Date................  July 21, 2025.
ADAMS Accession No..............  ML25203A071.
Location in Application of NSHC.  Pages 13-15 of Enclosure 1.
Brief Description of Amendments.  The proposed amendments would revise
                                   the nuclear criticality safety
                                   analysis and the technical
                                   specifications for fresh and spent
                                   fuel storage at Salem Nuclear
                                   Generating Station, Unit Nos. 1 and
                                   2.
Proposed Determination..........  NSHC.
Name of Attorney for Licensee,    Francis Romano, PSEG--Services
 Mailing Address.                  Corporation, 80 Park Plaza, T-10,
                                   Newark, NJ 07102.
NRC Project Manager, Telephone    Audrey Klett, 301-415-0489.
 Number.
------------------------------------------------------------------------

Order Imposing Procedures for Access to Sensitive Unclassified Non-
Safeguards Information for Contention Preparation

Holtec Decommissioning International, LLC, Holtec Indian Point 2, LLC, 
and Holtec Indian Point 3, LLC; Indian Point Station, Unit Nos. 1, 2 
and 3; Westchester County, NY

PSEG Nuclear LLC; Salem Nuclear Generating Station, Unit Nos. 1 and 2; 
Salem County, NJ

    A. This Order contains instructions regarding how potential parties 
to this proceeding may request access to documents containing Sensitive 
Unclassified Non-Safeguards Information (SUNSI).
    B. Within 10 days after publication of this notice of hearing or 
opportunity for hearing, any potential party who believes access to 
SUNSI is necessary to respond to this notice may request access to 
SUNSI. A ``potential party'' is any person who intends to participate 
as a party by demonstrating standing and filing an admissible 
contention under 10 CFR 2.309. Requests for access to SUNSI submitted 
later than 10 days after publication of this notice will not be 
considered absent a showing of good cause for the late filing, 
addressing why the request could not have been filed earlier.
    C. The requestor shall submit a letter requesting permission to 
access SUNSI to the Office of the Secretary, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001, Attention: Rulemakings and 
Adjudications Staff, and provide a copy to the Deputy General Counsel 
for Licensing, Hearings, and Enforcement, Office of the General 
Counsel, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001. 
The expedited delivery or courier mailing address for both offices is: 
U.S. Nuclear Regulatory Commission, 11555 Rockville Pike, Rockville, 
Maryland 20852. The email addresses for the Office of the Secretary and 
the Office of the General Counsel are [email protected] and 
[email protected], respectively.\1\ The request must 
include the following information:
---------------------------------------------------------------------------

    \1\ While a request for hearing or petition to intervene in this 
proceeding must comply with the filing requirements of the NRC's 
``E-Filing Rule,'' the initial request to access SUNSI under these 
procedures should be submitted as described in this paragraph.
---------------------------------------------------------------------------

    (1) A description of the licensing action with a citation to this 
Federal Register notice;
    (2) The name and address of the potential party and a description 
of the potential party's particularized interest that could be harmed 
by the action identified in C.(1); and
    (3) The identity of the individual or entity requesting access to 
SUNSI and the requestor's basis for the need for the information in 
order to meaningfully participate in this adjudicatory proceeding. In 
particular, the request must explain why publicly available versions of 
the information requested would not be sufficient to provide the basis 
and specificity for a proffered contention.
    D. Based on an evaluation of the information submitted under 
paragraph C, the NRC staff will determine within 10 days of receipt of 
the request whether:
    (1) There is a reasonable basis to believe the petitioner is likely 
to establish standing to participate in this NRC proceeding; and
    (2) The requestor has established a legitimate need for access to 
SUNSI.
    E. If the NRC staff determines that the requestor satisfies both 
D.(1) and D.(2), the NRC staff will notify the requestor in writing 
that access to SUNSI has been granted. The written notification will 
contain instructions on how the requestor may obtain copies of the 
requested documents, and any other conditions that may apply to access 
to those documents. These conditions may include, but are not limited 
to, the signing of a Non-Disclosure Agreement or Affidavit, or 
Protective Order \2\ setting forth terms and conditions to prevent the 
unauthorized or inadvertent disclosure of SUNSI by each individual who 
will be granted access to SUNSI.
---------------------------------------------------------------------------

    \2\ Any motion for Protective Order or proposed Non-Disclosure 
Agreement or Affidavit for SUNSI must be filed with the presiding 
officer or the Chief Administrative Judge if the presiding officer 
has not yet been designated, within 30 days of the deadline for the 
receipt of the written access request.
---------------------------------------------------------------------------

    F. Filing of Contentions. Any contentions in these proceedings that 
are based upon the information received as a result of the request made 
for SUNSI must be filed by the requestor no later than 25 days after 
receipt of (or access to) that information. However, if more than 25 
days remain between the petitioner's receipt of (or access to) the 
information and the deadline for filing all other contentions (as 
established in the notice of hearing or opportunity for hearing), the 
petitioner may file its SUNSI contentions by that later deadline.
    G. Review of Denials of Access.
    (1) If the request for access to SUNSI is denied by the NRC staff 
after a determination on standing and requisite need, the NRC staff 
shall immediately notify the requestor in writing, briefly stating the 
reason or reasons for the denial.
    (2) The requestor may challenge the NRC staff's adverse 
determination by filing a challenge within 5 days of receipt of that 
determination with: (a) the presiding officer designated in this 
proceeding; or (b) if no presiding officer has been appointed, the 
Chief Administrative Judge, or if this individual is unavailable, 
another administrative judge, or an Administrative Law Judge with 
jurisdiction pursuant to 10 CFR 2.318(a); or (c) if another officer has 
been designated to rule on information access issues, then with that 
officer.
    (3) Further appeals of decisions under this paragraph must be made 
pursuant to 10 CFR 2.311.
    H. Review of Grants of Access. A party other than the requestor may 
challenge an NRC staff determination granting access to SUNSI whose 
release would harm that party's interest independent of the proceeding. 
Such a challenge must be filed within 5 days of the notification by the 
NRC staff of its grant of access and must be filed with: (a) the 
presiding officer designated in this proceeding; or (b) if no presiding 
officer has been appointed, the Chief Administrative Judge, or if this 
individual is unavailable, another administrative judge, or an

[[Page 55325]]

Administrative Law Judge with jurisdiction pursuant to 10 CFR 2.318(a); 
or (c) if another officer has been designated to rule on information 
access issues, then with that officer.
    If challenges to the NRC staff determinations are filed, these 
procedures give way to the normal process for litigating disputes 
concerning access to information. Interlocutory review by the 
Commission on orders ruling on such NRC staff determinations (whether 
granting or denying access) is governed by 10 CFR 2.311.\3\
---------------------------------------------------------------------------

    \3\ Requestors should note that the filing requirements of the 
NRC's E-Filing Rule (72 FR 49139; August 28, 2007, as amended at 77 
FR 46562; August 3, 2012, 78 FR 34247, June 7, 2013) apply to 
appeals of NRC staff determinations (because they must be served on 
a presiding officer or the Commission, as applicable), but not to 
the initial SUNSI request submitted to the NRC staff under these 
procedures.
---------------------------------------------------------------------------

    I. The Commission expects that the NRC staff and presiding officers 
(and any other reviewing officers) will consider and resolve requests 
for access to SUNSI, and motions for Protective Orders, in a timely 
fashion in order to minimize any unnecessary delays in identifying 
those petitioners who have standing and who have propounded contentions 
meeting the specificity and basis requirements in 10 CFR part 2. The 
attachment to this Order summarizes the general target schedule for 
processing and resolving requests under these procedures.
    It is so ordered.

    Dated: November 28, 2025.

    For the Nuclear Regulatory Commission.
Carrie Safford,
Secretary of the Commission.

Attachment 1--General Target Schedule for Processing and Resolving 
Requests for Access to Sensitive Unclassified Non-Safeguards 
Information in This Proceeding

------------------------------------------------------------------------
           Day                             Event/activity
------------------------------------------------------------------------
0........................  Publication of Federal Register notice of
                            hearing or opportunity for hearing,
                            including order with instructions for access
                            requests.
10.......................  Deadline for submitting requests for access
                            to Sensitive Unclassified Non-Safeguards
                            Information (SUNSI) which contains
                            information: (i) supporting the standing of
                            a potential party identified by name and
                            address; and (ii) describing the need for
                            the information in order for the potential
                            party to participate meaningfully in an
                            adjudicatory proceeding.
60.......................  Deadline for submitting petition for
                            intervention which contains: (i)
                            demonstration of standing; and (ii) all
                            contentions whose formulation does not
                            require access to SUNSI (+25 Answers to
                            petition for intervention; +7 petitioner/
                            requestor reply).
20.......................  U.S. Nuclear Regulatory Commission (NRC)
                            staff informs the requestor of the staff's
                            determination whether the request for access
                            provides a reasonable basis to believe
                            standing can be established and demonstrates
                            the need for SUNSI. (NRC staff also informs
                            any party to the proceeding whose interest
                            independent of the proceeding would be
                            harmed by the release of the information.)
                            If NRC staff makes the finding of need for
                            SUNSI and likelihood of standing, NRC staff
                            begins document processing (i.e.,
                            preparation of redactions or review of
                            redacted documents).
25.......................  If NRC staff finds no ``need'' or no
                            likelihood of standing, the deadline for
                            petitioner/requestor to file a motion
                            seeking a ruling to reverse the NRC staff's
                            denial of access; NRC staff files copy of
                            access determination with the presiding
                            officer (or Chief Administrative Judge or
                            other designated officer, as appropriate).
                            If NRC staff finds ``need'' for SUNSI, the
                            deadline for any party to the proceeding
                            whose interest independent of the proceeding
                            would be harmed by the release of the
                            information to file a motion seeking a
                            ruling to reverse the NRC staff's grant of
                            access.
30.......................  Deadline for NRC staff's reply to motions to
                            reverse NRC staff determination(s).
40.......................  (Receipt +30) If NRC staff finds standing and
                            need for SUNSI, deadline for NRC staff to
                            complete information processing and file
                            motion for Protective Order and proposed Non-
                            Disclosure Agreement or Affidavit. Deadline
                            for applicant/licensee to file proposed Non-
                            Disclosure Agreement or Affidavit for SUNSI.
A........................  If access is granted: issuance of presiding
                            officer or other designated officer decision
                            on motion for Protective Order for access to
                            SUNSI (including schedule for providing
                            access and submission of contentions) or
                            decision reversing a final adverse
                            determination by the NRC staff.
A + 3....................  Deadline for filing executed Non-Disclosure
                            Agreements or Affidavits. Access provided to
                            SUNSI consistent with decision issuing the
                            Protective Order.
A + 28...................  Deadline for submission of contentions whose
                            development depends upon access to SUNSI.
                            However, if more than 25 days remain between
                            the petitioner's receipt of (or access to)
                            the information and the deadline for filing
                            all other contentions (as established in the
                            notice of hearing or notice of opportunity
                            for hearing), the petitioner may file its
                            SUNSI contentions by that later deadline.
A + 53...................  (Contention receipt +25) Answers to
                            contentions whose development depends upon
                            access to SUNSI.
A + 60...................  (Answer receipt +7) Petitioner/Intervenor
                            reply to answers.
>A + 60..................  Decision on contention admission.
------------------------------------------------------------------------

[FR Doc. 2025-21747 Filed 12-1-25; 8:45 am]
BILLING CODE 7590-01-P