ENVIRONMENTAL PROTECTION AGENCY
40 CFR Part 52
[EPA-R09-OAR-2025-0216; FRL-12613-02-R9]
Air Plan Approval; Guam; Guam Environmental Protection Agency;
New Source Review
AGENCY: Environmental Protection Agency (EPA).
ACTION: Final rule.
-----------------------------------------------------------------------
SUMMARY: The Environmental Protection Agency (EPA) is finalizing an
approval of a revision to the Guam state implementation plan (SIP).
This revision governs the Guam Environmental Protection Agency's (GEPA)
issuance of permits for stationary sources and focuses on the
preconstruction review and permitting of major sources and major
modifications under the Clean Air Act (CAA or ``the Act'').
DATES: This rule is effective on October 20, 2025.
ADDRESSES: The EPA has established a docket for this action under
Docket ID No. EPA-R09-OAR-2025-0216 at https://www.regulations.gov. All
documents in the docket are listed on the https://www.regulations.gov
website. Although listed in the index, some information is not publicly
[[Page 44988]]
available, e.g., Confidential Business Information (CBI) or other
information the disclosure of which is restricted by statute. Certain
other material, such as copyrighted material, is not placed on the
internet and will be publicly available only in hard copy form.
Publicly available docket materials are available through https://www.regulations.gov, or please contact the person identified in the FOR
FURTHER INFORMATION CONTACT section. If you need assistance in a
language other than English or if you are a person with disabilities
who needs a reasonable accommodation at no cost to you, please contact
the person identified in the FOR FURTHER INFORMATION CONTACT section.
FOR FURTHER INFORMATION CONTACT: Cecelia Working, EPA Region IX, 75
Hawthorne St., San Francisco, CA 94105; telephone number: (213) 244-
1911; email address: [email protected].
SUPPLEMENTARY INFORMATION: Throughout this document, ``we,'' ``us,''
and ``our'' refer to the EPA.
Table of Contents
I. Proposed Action
II. Public Comments and EPA Action
III. Incorporation by Reference
IV. Statutory and Executive Order Reviews
I. Proposed Action
On June 18, 2025 (90 FR 25984), the EPA proposed to approve the
rule listed in table 1. The GEPA is the air pollution control agency
for Guam and the designated state \1\ lead agency for submitting
revisions of the Guam SIP to the EPA. The rule that is the subject of
the EPA's current action was adopted into the Guam Administrative Rules
and Regulations (GAR) on December 28, 2022, and became effective on
December 29, 2022.\2\
---------------------------------------------------------------------------
\1\ CAA section 302(d) defines the term ``State'' to include
Guam.
\2\ The Guam Governor signed the law completing the multi-step
process for adopting Article 8 into the GAR on December 28, 2022,
following an earlier rulemaking process by the GEPA that concluded
on October 17, 2022, and a subsequent legislative approval process
that concluded on December 16, 2022.
Table 1--Submitted Rule
----------------------------------------------------------------------------------------------------------------
State State State
Air agency Rule or regulation Rule title adoption effective submittal
No. date date date
----------------------------------------------------------------------------------------------------------------
GEPA.................... Title 22, Division Guam Air Pollution 12/28/2022 12/29/2022 03/13/2025
1, Chapter 1, Standards and
Article 8. Regulations New Source
Review Requirements for
New and Modified Major
Sources in SO2
Nonattainment Areas
Adopted on October 17,
2022.
----------------------------------------------------------------------------------------------------------------
In our proposed action, we proposed approval of the GEPA's
submitted nonattainment new source review (NNSR) rule because the rule
satisfies the applicable NNSR requirements associated with the
designation of the Piti-Cabras area as nonattainment for the 2010 1-
hour sulfur dioxide (SO2) standard. Our proposed action
contains more information on the rule and our evaluation.
II. Public Comments and EPA Action
The EPA's proposed action provided a 30-day public comment period.
During this period, no comments were submitted on our proposal.
Therefore, the EPA continues to find that the submitted rule should be
approved into the Guam SIP because it fulfills all relevant CAA
requirements. As authorized in section 110(k)(3) of the Act, the EPA is
approving the submitted rule because it fulfills all relevant
requirements. Our action will be codified through revisions to 40 CFR
52.2670 (Identification of plan). With this final action, the NNSR
element of the EPA's obligation as to this nonattainment area under the
consent decree in Center for Biological Diversity et al. v. Regan, No.
4:24-cv-01900-HSG (N.D. Cal.), doc. 28, paragraph 1.c-d will also be
met.
III. Incorporation by Reference
In this rule, the EPA is finalizing regulatory text that includes
incorporation by reference. In accordance with requirements of 1 CFR
51.5, the EPA is incorporating by reference Guam Administrative Rules
and Regulations Title 22, Division 1, Chapter 1, Article 8, ``Guam Air
Pollution Standards and Regulations New Source Review Requirements for
New and Modified Major Sources in SO2 Nonattainment Areas
Adopted on October 17, 2022,'' which was adopted by Guam on December
28, 2022, and effective December 29, 2022. Article 8 is intended to
address the CAA's statutory and regulatory requirements for NNSR permit
programs for major sources emitting nonattainment air pollutants under
part D of title I of the CAA. The EPA has made, and will continue to
make, these materials available through https://www.regulations.gov and
at the EPA Region IX Office (please contact the person identified in
the FOR FURTHER INFORMATION CONTACT section of this preamble for more
information).
IV. Statutory and Executive Order Reviews
Under the CAA, the Administrator is required to approve a SIP
submission that complies with the provisions of the Act and applicable
federal regulations. 42 U.S.C. 7410(k); 40 CFR 52.02(a). Thus, in
reviewing SIP submissions, the EPA's role is to approve state choices,
provided that they meet the criteria of the CAA. Accordingly, this
action merely approves state law as meeting federal requirements and
does not impose additional requirements beyond those imposed by state
law. For that reason, this action:
Is not a significant regulatory action subject to review
by the Office of Management and Budget under Executive Order 12866 (58
FR 51735, October 4, 1993);
Is not subject to Executive Order 14192 (90 FR 9065,
February 6, 2025) because SIP actions are exempt from review under
Executive Order 12866;
Does not impose an information collection burden under the
provisions of the Paperwork Reduction Act (44 U.S.C. 3501 et seq.);
Is certified as not having a significant economic impact
on a substantial number of small entities under the Regulatory
Flexibility Act (5 U.S.C. 601 et seq.);
Does not contain any unfunded mandate or significantly or
uniquely affect small governments, as described in the Unfunded
Mandates Reform Act of 1995 (Pub. L. 104-4);
Does not have federalism implications as specified in
Executive Order 13132 (64 FR 43255, August 10, 1999);
[[Page 44989]]
Is not subject to Executive Order 13045 (62 FR 19885,
April 23, 1997) because it approves a state program;
Is not a significant regulatory action subject to
Executive Order 13211 (66 FR 28355, May 22, 2001); and
Is not subject to requirements of section 12(d) of the
National Technology Transfer and Advancement Act of 1995 (15 U.S.C. 272
note) because application of those requirements would be inconsistent
with the CAA.
In addition, the SIP is not approved to apply on any Indian
reservation land or in any other area where the EPA or an Indian Tribe
has demonstrated that a Tribe has jurisdiction. In those areas of
Indian country, the rule does not have Tribal implications and will not
impose substantial direct costs on Tribal governments or preempt Tribal
law as specified by Executive Order 13175 (65 FR 67249, November 9,
2000).
This action is subject to the Congressional Review Act (CRA), and
the EPA will submit a rule report to each House of the Congress and to
the Comptroller General of the United States. This action is not a
``major rule'' as defined by 5 U.S.C. 804(2).
Under section 307(b)(1) of the Clean Air Act, petitions for
judicial review of this action must be filed in the United States Court
of Appeals for the appropriate circuit by November 17, 2025. Filing a
petition for reconsideration by the Administrator of this final rule
does not affect the finality of this action for the purposes of
judicial review nor does it extend the time within which a petition for
judicial review may be filed, and shall not postpone the effectiveness
of such rule or action. This action may not be challenged later in
proceedings to enforce its requirements (see section 307(b)(2)).
List of Subjects in 40 CFR Part 52
Environmental protection, Administrative practice and procedure,
Air pollution control, Incorporation by reference, Intergovernmental
relations, Reporting and recordkeeping requirements, and Sulfur
dioxide.
Authority: 42 U.S.C. 7401 et seq.
Dated: September 10, 2025.
Michael Martucci,
Acting Regional Administrator, Region IX.
For reasons stated in the preamble, the Environmental Protection
Agency amends part 52, chapter I, title 40 of the Code of Federal
Regulations as follows:
PART 52--APPROVAL AND PROMULGATION OF IMPLEMENTATION PLANS
0
1. The authority citation for part 52 continues to read as follows:
Authority: 42 U.S.C. 7401 et seq.
Subpart AAA--Guam
0
2. In Sec. 52.2670, the table in paragraph (c) is amended by adding
the center heading ``Post-2011 Compilation of Rules and Regulations'',
``Title 22, Division 1, Chapter 1'', ``Article 8'' and the entries
``Section 1801'', ``Section 1801.1'', ``Section 1801.2'', ``Section
1801.3'', ``Section 1801.4'', ``Section 1801.5'', ``Section 1801.6'',
``Section 1801.7'', ``Section 1801.8'', ``Section 1802'', ``Section
1803'', ``Section 1803.1'', ``Section 1803.2'', ``Section 1803.3'',
``Section 1803.4'', ``Section 1803.5'', ``Section 1803.6'', ``Section
1804'', ``Section 1804.1'', ``Section 1804.2'', ``Section 1804.3'',
``Section 1804.4'' ``Section 1804.5'', ``Section 1805'', ``Section
1805.1'', ``Section 1805.2'', ``Section 1805.3'', ``Section 1806'',
``Section 1806.1'', ``Section 1806.2'', ``Section 1806.3'', ``Section
1806.4'', ``Section 1806.5'', ``Section 1806.6'', ``Section 1807'',
``Section 1807.1'', ``Section 1807.2'', ``Section 1807.3'', ``Section
1807.4'', ``Section 1808'', ``Section 1809'', ``Section 1810'', and
``Section 1811'' after the entry ``Chapter 17.1-17.4'' to read as
follows:
Sec. 52.2670 Identification of plan.
* * * * *
(c) * * *
Table 52.2670--EPA Approved Territory of Guam Regulations
----------------------------------------------------------------------------------------------------------------
Effective
State citation Title/subject date EPA approval date Explanation
----------------------------------------------------------------------------------------------------------------
* * * * * * *
----------------------------------------------------------------------------------------------------------------
Post-2011 Compilation of Rules and Regulations
----------------------------------------------------------------------------------------------------------------
Title 22, Division 1, Chapter 1
----------------------------------------------------------------------------------------------------------------
Article 8
----------------------------------------------------------------------------------------------------------------
Section 1801................. Applicability 12/29/2022 9/18/2025, 90 FR Submitted on March
Procedures. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1801.1............... Preconstruction Review 12/29/2022 9/18/2025, 90 FR Submitted on March
Requirements. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1801.2............... Nonattainment Major 12/29/2022 9/18/2025, 90 FR Submitted on March
New Source Review [INSERT FEDERAL 13, 2025, as an
(NSR) Permit REGISTER PAGE WHERE attachment to a
Requirement. THE DOCUMENT BEGINS]. letter of the same
date.
Section 1801.3............... Emission Calculation 12/29/2022 9/18/2025, 90 FR Submitted on March
Requirements to [INSERT FEDERAL 13, 2025, as an
Determine New Source REGISTER PAGE WHERE attachment to a
Review (NSR) THE DOCUMENT BEGINS]. letter of the same
Applicability. date.
Section 1801.4............... Major Sources with 12/29/2022 9/18/2025, 90 FR Submitted on March
Plant-Wide [INSERT FEDERAL 13, 2025, as an
Applicability REGISTER PAGE WHERE attachment to a
Limitations. THE DOCUMENT BEGINS]. letter of the same
date.
Section 1801.5............... Projects That Rely on 12/29/2022 9/18/2025, 90 FR Submitted on March
a Projected Actual [INSERT FEDERAL 13, 2025, as an
Emissions Test. REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1801.6............... Secondary Emissions... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
[[Page 44990]]
Section 1801.7............... Stationary Sources.... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1801.8............... Environmental 12/29/2022 9/18/2025, 90 FR Submitted on March
Protection Agency [INSERT FEDERAL 13, 2025, as an
Determination. REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1802................. Definitions........... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1803................. Application 12/29/2022 9/18/2025, 90 FR Submitted on March
Requirements. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1803.1............... Application Submittal. 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1803.2............... Application Content... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1803.3............... Lowest Achievable 12/29/2022 9/18/2025, 90 FR Submitted on March
Emission Rate (LAER). [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1803.4............... Certification of 12/29/2022 9/18/2025, 90 FR Submitted on March
Compliance. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1803.5............... Analysis of 12/29/2022 9/18/2025, 90 FR Submitted on March
Alternatives. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1803.6............... Application Fees...... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1804................. Emissions Offsets..... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1804.1............... Offset Requirements... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1804.2............... Timing................ 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1804.3............... Quantity.............. 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1804.4............... Emission Reduction 12/29/2022 9/18/2025, 90 FR Submitted on March
Requirements. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1804.5............... Restrictions on 12/29/2022 9/18/2025, 90 FR Submitted on March
Trading Pollutants. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1805................. Administrative 12/29/2022 9/18/2025, 90 FR Submitted on March
Requirements. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1805.1............... Ambient Air Quality 12/29/2022 9/18/2025, 90 FR Submitted on March
Standards. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1805.2............... Air Quality Models.... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1805.3............... Stack Height 12/29/2022 9/18/2025, 90 FR Submitted on March
Procedures. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1806................. Nonattainment Major 12/29/2022 9/18/2025, 90 FR Submitted on March
New Source Review [INSERT FEDERAL 13, 2025, as an
(NSR) Permit-- REGISTER PAGE WHERE attachment to a
Decision. THE DOCUMENT BEGINS]. letter of the same
date.
Section 1806.1............... Preliminary Decision.. 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1806.2............... Nonattainment Major 12/29/2022 9/18/2025, 90 FR Submitted on March
New Source Review [INSERT FEDERAL 13, 2025, as an
(NSR) Permit-- REGISTER PAGE WHERE attachment to a
Preliminary Decision THE DOCUMENT BEGINS]. letter of the same
Requirements. date.
[[Page 44991]]
Section 1806.3............... Nonattainment Major 12/29/2022 9/18/2025, 90 FR Submitted on March
New Source Review [INSERT FEDERAL 13, 2025, as an
(NSR) Permit Contents. REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1806.4............... Nonattainment Major 12/29/2022 9/18/2025, 90 FR Submitted on March
New Source Review [INSERT FEDERAL 13, 2025, as an
(NSR) Permit--Final REGISTER PAGE WHERE attachment to a
Decision. THE DOCUMENT BEGINS]. letter of the same
date.
Section 1806.5............... Ongoing Permit 12/29/2022 9/18/2025, 90 FR Submitted on March
Requirements. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1806.6............... Technology 12/29/2022 9/18/2025, 90 FR Submitted on March
Clearinghouse. [INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1807................. Source Obligations.... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1807.1............... Enforcement........... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1807.2............... Termination........... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1807.3............... Compliance............ 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1807.4............... Relaxation in 12/29/2022 9/18/2025, 90 FR Submitted on March
Enforceable [INSERT FEDERAL 13, 2025, as an
Limitations. REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1808................. Public Participation.. 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1809................. Plant-Wide 12/29/2022 9/18/2025, 90 FR Submitted on March
Applicability Limits [INSERT FEDERAL 13, 2025, as an
(PAL). REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1810................. Invalidation.......... 12/29/2022 9/18/2025, 90 FR Submitted on March
[INSERT FEDERAL 13, 2025, as an
REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
Section 1811................. Effective Date for 12/29/2022 9/18/2025, 90 FR Submitted on March
Referenced Federal [INSERT FEDERAL 13, 2025, as an
Regulations. REGISTER PAGE WHERE attachment to a
THE DOCUMENT BEGINS]. letter of the same
date.
----------------------------------------------------------------------------------------------------------------
* * * * *
[FR Doc. 2025-18062 Filed 9-17-25; 8:45 am]
BILLING CODE 6560-50-P