NUCLEAR REGULATORY COMMISSION
[Docket No. 50-440; NRC-2023-0136]
Vistra Operations Company, LLC; Perry Nuclear Power Plant, Unit
1; License Renewal and Record of Decision
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued
Renewed Facility Operating License No. NPF-58 to Vistra Operations
Company, LLC (Vistra or the licensee), for Perry Nuclear Power Plant
(Perry), Unit 1. In addition, the NRC has prepared a record of decision
(ROD) that supports the NRC's decision to issue Renewed Facility
Operating License No. NPF-58.
DATES: The Renewed Facility Operating License No. NPF-58 was issued on
July 7, 2025.
ADDRESSES: Please refer to Docket ID NRC-2023-0136 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0136. Address
questions about Docket IDs in Regulations.gov to Bridget Curran;
telephone: 301-415-1003; email: [email protected]. For technical
questions, contact the individual listed in the FOR FURTHER INFORMATION
CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737,
or by email to [email protected]. For the convenience of the reader,
instructions about obtaining materials referenced in this document are
provided in the ``Availability of Documents'' section.
NRC's PDR: The PDR, where you may examine and order copies
of publicly available documents, is open by appointment. To make an
appointment to visit the PDR, please send an email to
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except
Federal holidays.
FOR FURTHER INFORMATION CONTACT: Vaughn Thomas, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-5897; email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Discussion
Notice is hereby given that the NRC has issued Renewed Facility
Operating License No. NPF-58 to Vistra for Perry, Unit 1. Vistra is the
operator of the facility. Renewed Facility Operating License No. NPF-58
authorizes Vistra to operate Perry, Unit 1 at reactor core power levels
not in excess of 3,758 megawatts thermal, in accordance with the
provisions of Perry, Unit 1, renewed operating license and technical
specifications. Notice is also given that the ROD that supports the
NRC's decision to issue Renewed Facility Operating License No. NPF-58
is available in the ``Availability of Documents'' section of this
document.
As discussed in the ROD and the final supplemental environmental
impact statement (EIS), published as NUREG-1437, ``Generic
Environmental Impact Statement for License Renewal of Nuclear Plants,
Supplement 61, Regarding License Renewal of Perry Nuclear Power Plant,
Final Report,'' dated April 2025. The final EIS documents the NRC
staff's environmental review, including the determination that the
adverse environmental impacts of license renewal for Perry, Unit 1 are
not so great that preserving the option of license renewal for energy
planning decisionmakers would be unreasonable. The final EIS conclusion
is based on (1) information provided in the environmental report
submitted by Vistra, as supplemented, (2) the NRC staff's consultations
with Federal, State, Tribal, and local agencies, (3) the NRC staff's
independent environmental review, and (4) the NRC staff's consideration
of public comments received during the scoping process and on the 2024
draft site-specific EIS, as well as the consideration of mitigation
measures.
Perry, Unit 1 is a Mark 3, boiling water reactor located on the
shore of Lake Erie in Lake County, Ohio, approximately 35 miles
northeast of Cleveland, Ohio. The application for the renewed license,
``Perry Nuclear Power Plant, Unit 1, License Renewal Application,'' is
dated July 3, 2023, and has been supplemented (see ``Availability of
Documents'' section, of this document). The NRC staff has detemined
that Vistra's application complies with the standards and requirements
of the Atomic Energy Act of 1954, as amended (the Act), and the NRC's
regulations. As required by the Act and NRC regulations in chapter 1 of
title 10 of the Code of Federal Regulations (10 CFR), the NRC has made
appropriate findings, which are set forth in the renewed license.
A public notice of the NRC's acceptance for docketing of the
renewed license application and an opportunity for a hearing was
published in the Federal Register on September 29, 2023 (88 FR 67373).
For further details with respect to this action, see: (1) Vistra
Operations Company, LLC's license renewal application for Perry, Unit
1, dated July 3, 2023, as supplemented by letters dated through January
30, 2025; (2) the NRC's safety evaluation, published in May 2025; (3)
the NRC's final environmental impact statement (NUREG-1437, Supplement
61) for Perry, Unit 1, published in April 2025; and (4) the NRC's ROD,
issued on July 7, 2025.
II. Availability of Documents
The documents identified in the following table are available to
interested persons through one or more of the following methods, as
indicated.
------------------------------------------------------------------------
Document description ADAMS Accession No.
------------------------------------------------------------------------
License Renewal Application ML23184A081.
for the Perry Nuclear Power
Plant, dated July 3, 2023.
Record of Decision--License ML25160A138.
Renewal Application Review--
Perry Nuclear Power Plant
Unit 1, dated July 7, 2025.
Safety Evaluation Report, ML25148A362.
Related to the License
Renewal of Perry Nuclear
Power Plant, Unit 1,
published May 2025.
NUREG-1437, ``Generic ML25113A032.
Environmental Impact
Statement for License
Renewal of Nuclear Plants,
Supplement 61, Regarding
License Renewal of Perry
Nuclear Power Plant, Final
Report,'' published April
2025.
[[Page 30708]]
NUREG-1437, ``Generic ML13107A023 (package).
Environmental Impact
Statement for License
Renewal of Nuclear Plants,
Revision 1, Volumes 1-3,
Final Report,'' published
June 2013.
NUREG-1437, ``Generic ML24087A133 (package).
Environmental Impact
Statement for License
Renewal of Nuclear Plants,
Revision 2, Volumes 1-3,
Final Report,'' published
August 2024.
Perry Nuclear Power Plant, ML24220A270.
Unit 1, License Renewal
Application--Supplement 1,
dated August 7, 2024.
Perry Nuclear Power Plant, ML24180A010.
Unit 1, License Renewal
Application--Supplement 2,
dated June 27, 2024.
Perry Nuclear Power Plant, ML24206A150.
Unit 1, License Renewal
Application--Supplement 3,
dated July 24, 2024.
Perry Nuclear Power Plant, ML24249A123.
Unit 1, License Renewal
Application--Supplement 4,
dated September 5, 2024.
Perry Nuclear Power Plant, ML24295A352.
Unit 1, License Renewal
Application--Supplement 5,
dated October 21, 2024.
Perry Nuclear Power Plant, ML24312A368.
Unit 1, License Renewal
Application--Supplement 6,
dated November 7, 2024.
Perry Nuclear Power Plant, ML24354A265.
Unit 1, License Renewal
Application--Supplement 7,
dated December 19, 2024.
Perry Nuclear Power Plant, ML25027A327.
Unit 1, License Renewal
Application--Supplement 8,
dated January 27, 2025.
License Renewal Application-- ML24260A266.
Response to Request for
Additional Information--Set
1, dated September 16, 2024.
License Renewal Application-- ML24276A083.
Response to Request for
Additional Information--Set
2, dated October 2, 2024.
License Renewal Application-- ML24324A185.
Response to Request for
Additional Information--Set
3, dated November 19, 2024.
License Renewal Application-- ML25036A154.
Response to Request for
Additional Information--Set
4, dated February 5, 2025.
License Renewal Application-- ML25079A062.
Response to Request for
Additional Information--Set
5, dated March 20, 2025.
License Renewal Application-- ML24305A134.
Response to Requests for
Confirmatory Information--
Set 1, dated October 31,
2024.
License Renewal Application-- ML24339A066.
Response to Requests for
Confirmatory Information--
Set 2, dated December 4,
2024.
License Renewal Application-- ML25030A014.
Responses to Request for
Confirmatory Information--
Set 3, dated January 30,
2025.
------------------------------------------------------------------------
Dated: July 7, 2025.
For the Nuclear Regulatory Commission.
Michele Sampson,
Director, Division of New and Renewed Licenses, Office of Nuclear
Reactor Regulation.
[FR Doc. 2025-12782 Filed 7-9-25; 8:45 am]
BILLING CODE 7590-01-P