[Federal Register Volume 90, Number 115 (Tuesday, June 17, 2025)]
[Notices]
[Page 25648]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-11035]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 99902056; NRC-2024-0146]


Tennessee Valley Authority; Clinch River Nuclear Site; 
Construction Permit Application

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice; receipt.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is providing 
public notice each week for four consecutive weeks of receipt and 
availability of an application for a construction permit (CP) from 
Tennessee Valley Authority (TVA) for the Clinch River Nuclear Site in 
Roane County, Tennessee. The application, proposing to construct a GE-
Hitachi BWRX-300 reactor, was received in two parts on April 25 and May 
20, 2025. This notice is being provided to make the public and other 
stakeholders aware that the CP application is available for inspection.

DATES: June 17, 2025.

ADDRESSES: Please refer to Docket ID NRC-2024-0146 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2024-0146. Address 
questions about Docket IDs in Regulations.gov to Bridget Curran; 
telephone: 301-415-1003; email: [email protected]. For technical 
questions, contact the individual listed in the For Further Information 
Contact section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737, 
or by email to [email protected]. The ADAMS accession number for 
each document referenced (if it is available in ADAMS) is provided the 
first time that it is mentioned in this document.
     NRC's PDR: The PDR, where you may examine and order copies 
of publicly available documents, is open by appointment. To make an 
appointment to visit the PDR, please send an email to 
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8 
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except 
Federal holidays.

FOR FURTHER INFORMATION CONTACT: Allen Fetter, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-8556; email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Discussion

    In response to a letter from TVA dated August 17, 2023 (NNP-23-003, 
ADAMS Accession No. ML23229A569), the Commission on November 21, 2023 
granted an exemption from certain requirements of paragraph 2.101(a)(5) 
of title 10 of the Code of Federal Regulations (10 CFR), which allowed 
TVA to submit a construction permit application in two parts with the 
information required under 10 CFR 50.34(a)(1) included in the second 
part of the application (ADAMS Accession No. ML23045A008).
    Tennessee Valley Authority filed with the NRC, pursuant to 10 CFR 
part 50, ``Domestic Licensing of Production and Utilization 
Facilities,'' both parts of the application for a construction permit 
to construct a GEH BWRX-300 reactor at the Clinch River Nuclear Site in 
Roane County, Tennessee, on April 28, 2025 (NNP-25-003, ADAMS Accession 
No. ML25118A209), and May 20, 2025, (NPP-25-004, ADAMS Package 
Accession No. ML25140A062), respectively. These notices are being 
provided in accordance with the requirements in 10 CFR 50.43(a)(3).
    The NRC staff is currently undertaking its acceptance review of 
both parts of the application. If both parts of the application are 
accepted for docketing, a subsequent Federal Register notice will be 
issued that addresses the acceptability of the construction permit 
application for docketing and provisions for participation of the 
public in the permitting process.

    Dated: June 12, 2025.

    For the Nuclear Regulatory Commission.
Mahmoud Jardaneh,
Chief, New Reactor Licensing and Infrastructure Branch, Division of New 
and Renewed Licenses, Office of Nuclear Reactor Regulation.
[FR Doc. 2025-11035 Filed 6-16-25; 8:45 am]
BILLING CODE 7590-01-P