NUCLEAR REGULATORY COMMISSION
[Docket No. 99902056; NRC-2024-0146]
Tennessee Valley Authority; Clinch River Nuclear Site;
Construction Permit Application
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice; receipt.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is providing
public notice each week for four consecutive weeks of receipt and
availability of an application for a construction permit (CP) from
Tennessee Valley Authority (TVA) for the Clinch River Nuclear Site in
Roane County, Tennessee. The application, proposing to construct a GE-
Hitachi BWRX-300 reactor, was received in two parts on April 25 and May
20, 2025. This notice is being provided to make the public and other
stakeholders aware that the CP application is available for inspection.
DATES: June 10, 2025.
ADDRESSES: Please refer to Docket ID NRC-2024-0146 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2024-0146. Address
questions about Docket IDs in Regulations.gov to Bridget Curran;
telephone: 301-415-1003; email: [email protected]. For technical
questions, contact the individual listed in the ``For Further
Information Contact'' section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737,
or by email to [email protected]. The ADAMS accession number for
each document referenced (if it is available in ADAMS) is provided the
first time that it is mentioned in this document.
NRC's PDR: The PDR, where you may examine and order copies
of publicly available documents, is open by appointment. To make an
appointment to visit the PDR, please send an email to
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except
Federal holidays.
FOR FURTHER INFORMATION CONTACT: Allen Fetter, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-8556; email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Discussion
In response to a letter from TVA dated August 17, 2023 (NNP-23-003,
ADAMS Accession No. ML23229A569), the Commission on November 21, 2023
granted an exemption from certain requirements of paragraph 2.101(a)(5)
of title 10 of the Code of Federal Regulations (10 CFR), which allowed
TVA to submit a construction permit application in two parts with the
information required under 10 CFR 50.34(a)(1) included in the second
part of the application (ADAMS Accession No. ML23045A008).
Tennessee Valley Authority filed with the NRC, pursuant to 10 CFR
part 50, ``Domestic Licensing of Production and Utilization
Facilities,'' both parts of the application for a construction permit
to construct a GEH BWRX-300 reactor at the Clinch River Nuclear Site in
Roane County, Tennessee, on April 28, 2025 (NNP-25-003, ADAMS Accession
No. ML25118A209), and May 20, 2025, (NPP-25-004, ADAMS Package
Accession No. ML25140A062), respectively. These notices are being
provided in accordance with the requirements in 10 CFR 50.43(a)(3).
The NRC staff is currently undertaking its acceptance review of
both parts of the application. If both parts of the application are
accepted for docketing, a subsequent Federal Register notice will be
issued that addresses the acceptability of the construction permit
application for docketing and provisions for
[[Page 24426]]
participation of the public in the permitting process.
Dated: June 5, 2025.
For the Nuclear Regulatory Commission.
Michelle Hayes,
Chief, New Reactor Licensing and Infrastructure Branch, Division of New
and Renewed Licenses, Office of Nuclear Reactor Regulation.
[FR Doc. 2025-10465 Filed 6-9-25; 8:45 am]