[Federal Register Volume 90, Number 87 (Wednesday, May 7, 2025)]
[Notices]
[Pages 19368-19369]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-07931]


-----------------------------------------------------------------------

DEPARTMENT OF TRANSPORTATION

Federal Transit Administration


Limitation on Claims Against Proposed Public Transportation 
Projects--Ontario International Airport Connector Project and Draw One 
Bridge Replacement Project

AGENCY: Federal Transit Administration (FTA), Department of 
Transportation (DOT).

ACTION: Notice.

-----------------------------------------------------------------------

SUMMARY: This notice announces final environmental actions taken by the 
Federal Transit Administration (FTA) regarding two projects: the 
Ontario International Airport Connector Project, Cities of Rancho 
Cucamonga and Ontario, San Bernardino County, California; and the Draw 
One Bridge Replacement Project in Boston, Suffolk County and Cambridge, 
Middlesex County, Massachusetts. The purpose of this notice is to 
publicly announce FTA's environmental decisions on the subject 
projects, and to activate the limitation on any claims that may 
challenge these final environmental actions.

DATES: A claim seeking judicial review of FTA actions announced herein 
for the listed public transportation projects will be barred unless the 
claim is filed on or before October 6, 2025.

FOR FURTHER INFORMATION CONTACT: Kathryn Loster, Assistant Chief 
Counsel, Office of Chief Counsel, (202) 360-2322, or Saadat Khan, 
Environmental Protection Specialist, Office of Environmental Policy and 
Programs, (202) 366-9647. FTA is located at 1200 New Jersey Avenue SE, 
Washington, DC 20590. Office hours are from 9 a.m. to 5 p.m., Monday 
through Friday, except Federal holidays.

SUPPLEMENTARY INFORMATION: Notice is hereby given that FTA has taken 
final agency actions subject to 23 U.S.C. 139(l) by issuing certain 
approvals for the public transportation projects listed below. The 
actions on the projects, as well as the laws under which such actions 
were taken, are described in the documentation issued in connection 
with the project to comply with the National Environmental Policy Act 
(NEPA), and in other documents in the FTA environmental project files 
for the projects. Interested parties may contact either the project 
sponsor or the relevant FTA Regional Office for more information. 
Contact information for FTA's Regional Offices may be found at https://www.transit.dot.gov.
    This notice applies to all FTA decisions on the listed projects as 
of the issuance date of this notice and all laws under which such 
actions were taken, including, but not limited to, NEPA (42 U.S.C. 
4321-4375), Section 4(f) requirements (49 U.S.C. 303), Section 106 of 
the National Historic Preservation Act (54 U.S.C. 306108), Endangered 
Species Act (16 U.S.C. 1531), Magnuson-Stevens Fishery Conservation and 
Management Act of 1976 (16 U.S.C. 1801 et seq.), Clean Water Act (33 
U.S.C. 1251), and the Clean Air Act (42 U.S.C. 7401-7671q). This notice 
does not, however, alter or extend the limitation period for challenges 
of project decisions subject to previous notices published in the 
Federal Register. The projects actions that are the subject of this 
notice follow:
    1. Project name and location: Ontario International Airport (ONT) 
Connector Project (CA Project), Cities of Rancho Cucamonga and Ontario, 
San Bernardino County, California.
    Project Sponsor: San Bernardino County Transportation Authority 
(SBCTA).
    Project description: The CA Project would construct a 4.2-mile-long 
transit service tunnel directly connecting the Southern California 
Regional Rail Authority Cucamonga Metrolink Station in the City of 
Rancho Cucamonga with ONT in the City of Ontario. The CA Project would 
provide a direct airport connection from Cucamonga Metrolink Station to 
support ONT's projected growth. Transit facilities would be 
constructed, including stations to serve Cucamonga Metrolink Station, 
ONT Terminals 2 and 4; a maintenance and storage facility to store and 
maintain vehicles; and an emergency access and ventilation shaft to 
provide a means of emergency passenger egress and first responder 
access.
    Final agency action: Section 106 No Historic Properties Affected 
determination, dated December 2, 2024; and Finding of No Significant 
Impact (FONSI), dated April 10, 2025.
    Supporting documentation: The ONT Connector Project Environmental 
Assessment (EA), dated October 18, 2024. The FONSI, EA and associated 
documents can be viewed and downloaded from: https://

[[Page 19369]]

www.gosbcta.com/ontconnector/#ont-docs.
    2. Project name and location: Draw One Bridge Replacement Project 
(MA Project), Boston, Suffolk County, and Cambridge, Middlesex County, 
Massachusetts.
    Project Sponsor: Massachusetts Bay Transportation Authority (MBTA).
    Project description: The MA Project would involve the replacement 
of the Draw One Bridge, which carries Amtrak passenger and MBTA 
commuter rail traffic over the Charles River in the cities of Boston 
and Cambridge, Massachusetts. The existing two two-track bascule bridge 
spans would be replaced with three two-track, standalone vertical lift 
bridge structures within the footprint of the existing bridges. The new 
bridge structures would carry six tracks, rather than the four on the 
current crossings. The MA Project would also replace the Boston and 
Main Railroad (B&MRR) Signal Tower A and modify the Massachusetts 
Department of Conservation and Recreation-owned North Bank Bridge, 
which crosses the MBTA right-of-way north of the Draw One Bridge. The 
MA Project work would also include replacing the existing signal system 
and switch heaters associated with the Draw One Bridge, and installing 
a new drainage system.
    Final agency action: Section 106 Memorandum of Agreement, dated 
December 18, 2024; Section 4(f) de minimis, dated January 8, 2025; Draw 
One Bridge Replacement Project Finding of No Significant Impact 
(FONSI), dated January 16, 2025.
    Supporting documentation: Draw One Bridge Replacement Project, 
Final Environmental Assessment (Final EA), dated January 16, 2025. The 
FONSI, EA and supporting documents can be viewed and downloaded from: 
https://www.mbta.com/projects/north-station-drawbridge-replacement.
    Authority: 23 U.S.C. 139(l)(1).

Megan Blum,
Deputy Associate Administrator for Planning and Environment.
[FR Doc. 2025-07931 Filed 5-6-25; 8:45 am]
BILLING CODE 4910-57-P