[Federal Register Volume 90, Number 86 (Tuesday, May 6, 2025)]
[Notices]
[Pages 19197-19200]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-07875]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2426-235]


California Department of Water Resources & Los Angeles Department 
of Water and Power; Notice of Intent To Prepare an Environmental Impact 
Statement for the South State Water Project Hydroelectric Project, 
Schedule for Environmental Review, and Request for Comments

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare draft and final environmental impact 
statements (EIS) to evaluate potential environmental impacts of 
continued operation and maintenance of the proposed South State Water 
Project Hydroelectric Project (South SWP Project; FERC No. 2426). The 
South SWP Project is located on the West Branch of the California 
Aqueduct (non-project) in Los Angeles County, California.\1\ The 
California Aqueduct and the South SWP Hydroelectric Project are 
components of the larger State Water Project (SWP), an approximately 
705-mile-long water storage and delivery system of reservoirs, 
aqueducts, power plants, and pumping plants, which distributes water 
collected from rivers in northern California to the Central Valley and

[[Page 19198]]

Southern California for drinking water, industrial use, and irrigation. 
The Commission will use this EIS in its decision-making process in 
accordance with the National Environmental Policy Act (NEPA). The 
schedule for preparing the EIS is discussed in the Schedule for 
Environmental Review section of this notice.
---------------------------------------------------------------------------

    \1\ For tracking purposes under the National Environmental 
Policy Act, the unique identification number for documents relating 
to this environmental review is EISX-019-20-000-1745337097.
---------------------------------------------------------------------------

    As part of the NEPA review process, the Commission takes into 
account concerns the public may have about proposals and the 
environmental impacts that could result whenever it considers the 
issuance of a license. This gathering of public input is referred to as 
``scoping.'' On September 30, 2016, Commission staff issued Scoping 
Document 1, initiating the scoping process for the project. Commission 
staff conducted an environmental site visit open to the public on 
October 25, 2016, and held two public scoping meetings. Two scoping 
meetings were held in Valencia, California on October 26, 2016. A court 
reporter recorded oral comments made during the scoping meetings. On 
January 13, 2017, Commission staff issued a revised scoping document 
(Scoping Document 2) based on the comments received during the scoping 
comment period, which ended November 29, 2016. Scoping Document 2 
describes the project, project alternatives, and the current view of 
anticipated environmental effects that will be addressed in the EIS.
    In accordance with the Commission's regulations, on December 2, 
2020, Commission staff issued a notice that the project was ready for 
environmental analysis and soliciting comments, recommendations, terms 
and conditions, and prescriptions (REA Notice). The comment period for 
the REA Notice closed on January 31, 2021. Based on the information in 
the record, including comments filed during scoping and in response to 
the REA Notice, staff has determined that licensing the project may 
constitute a major federal action significantly affecting the quality 
of the human environment. Therefore, Commission staff will prepare a 
draft and final EIS for the proposed South SWP Project, which will 
address the concerns raised during prior comment periods and comments 
received in response to this notice.
    By this notice, the Commission requests any additional comments on 
the scope of issues to address in the EIS, including comments on 
potential alternatives and impacts, and any relevant information, 
studies, or analyses of any kind concerning impacts affecting the 
quality of the human environment. If you previously submitted comments 
and recommendations to the Commission, you do not need to file those 
comments and recommendations again. To ensure that your comments are 
timely and properly recorded, please submit your comments so that the 
Commission receives them in Washington, DC on or before 5:00 p.m. 
Eastern Time on May 30, 2025.

Public Participation

    There are three methods you can use to submit your comments to the 
Commission. The Commission encourages electronic filing of comments and 
has staff available to assist you at (866) 208-3676 or 
[email protected]. Please carefully follow these instructions 
so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. Using eComment is an easy method for 
submitting brief, text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature, which is located on the Commission's website (www.ferc.gov) 
under the link to FERC Online. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on ``eRegister.'' You will be asked to select the type of filing you 
are making; a comment on a particular project is considered a ``Comment 
on a Filing''; or
    (3) You can file a paper copy of your comments by mailing them to 
the Commission. Be sure to reference the project docket number (P-2426-
235) on your letter. Submissions sent via the U.S. Postal Service must 
be addressed to: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426. Submissions sent via any other carrier must be addressed to: 
Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 
12225 Wilkins Avenue, Rockville, Maryland 20852.
    Additionally, the Commission offers a free service called 
eSubscription. This service provides automatic notification of filings 
made to subscribed project dockets, document summaries, and direct 
links to the documents. Go to https://www.ferc.gov/ferc-online/overview 
to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or [email protected].

Summary of the South SWP Project

    On January 30, 2020, the California Department of Water Resources 
(DWR) and the Los Angeles Department of Water and Power (LADWP) (co-
applicants) filed an application for a new license with the Commission 
to continue to operate and maintain the existing 1,350-megawatt (MW) 
South SWP Project. The project occupies 2,807.28 acres of federal land, 
including 2,790.02 acres within the Angeles National Forest of Los 
Padres National Forest administered by U.S. Department of Agriculture, 
Forest Service (Forest Service), and 17.26 acres administered by the 
U.S. Department of the Interior, Bureau of Land Management (BLM).

Existing Project Facilities

    The South SWP Project consists of two developments--DWR's Warne 
Development (upstream) and LADWP's Castaic Development (downstream).\2\ 
The project generates an average of 824,803 megawatt-hours of energy 
annually.\3\
---------------------------------------------------------------------------

    \2\ The project's remaining development, Devil Canyon, is 
located along the East Branch of the California Aqueduct and is 
currently being relicensed as a separate project (Devil Canyon 
Project No. 14797).
    \3\ DWR and LADWP's average annual generation is for the period 
from calendar years 2007 through 2017.
---------------------------------------------------------------------------

Warne Development

    The Warne Development consists of the following existing 
facilities: (1) a 15-foot-high embankment impounding the 288-acre Quail 
Lake with a maximum capacity of 7,583 acre-feet at normal maximum water 
surface elevation (NMWSE) of 3,325 feet; (2) the Quail Lake outlet 
consisting of a 12-foot by 12-foot reinforced concrete double box with 
four 6-foot by 12-foot remotely controlled slide gates, a service bay, 
and outlet transition (2) the 2-mile-long, concrete-lined Lower Quail 
canal with a maximum flow capacity of 3,129 cubic feet per second 
(cfs), which along with Quail Lake serves as the forebay to the 
powerplant; (3) the 350-foot-long, 50-

[[Page 19199]]

foot-high Peace Valley pipeline intake embankment and intake structure 
located at the downstream end of Lower Quail canal that conveys water 
to the Peace Valley pipeline; (4) the 12-foot-diameter, 5.5-mile-long 
Peace Valley pipeline located entirely underground and extending to the 
penstock; (5) the 78-inch-diameter Gorman bypass channel extending 5.9 
miles from the Lower Quail canal to Pyramid Lake serves to divert flows 
exceeding the pipeline's capacity or during a pipeline outage; (6) a 
penstock bifurcating into two 8-foot-diameter steel branches with a 
combined maximum capacity of 1,564 cfs; (7) the Warne powerplant 
located at the northern (upstream) end of Pyramid Lake at the terminus 
of the Peace Valley pipeline, with an installed capacity of 74.29 MW 
and housing two 38.25-MW Pelton-type turbines each connected to a 
three-phase generator; (8) a switchyard adjacent to the powerplant; (8) 
the 2.95-mile-long, single-circuit, 220-kilovolt (kV) Warne 
transmission line; (9) the Quail Lake fishing access path and day use 
area; and (10) appurtenant facilities.

Castaic Development

    The Castaic Development consists of the following existing 
facilities: (1) the 1,269-acre Pyramid Lake, with a storage capacity of 
161,375 acre-feet impounded by the 1,090-foot-long, 400-foot-high 
Pyramid Dam with a crest elevation at 2,606 feet; (2) a controlled 
service spillway with a flow capacity of 17,000 cfs; (3) an emergency, 
uncontrolled spillway with a spill capacity of 148,900 cfs; (4) a 15-
foot-diameter, 1,350-foot-long, low-level outlet tunnel lined with 
concrete with a flow capacity of 1,000 cfs used for downstream releases 
to Piru Creek; (5) the 30-foot-diameter, 7.2-mile-long Angeles tunnel 
with a flow capacity of 18,400 cfs; (6) the 120-foot-diameter, 383-
foot-tall Angeles tunnel surge chamber connected to the Angeles tunnel 
with a 108-foot-long junction structure with a 28-foot-diameter riser; 
(7) the Castaic penstock located immediately downstream of the south 
portal of the Angeles tunnel that consists of: (a) a double 
trifurcation with shutoff valves on each trifurcation branch, (b) six 
2,400-foot-long steel penstocks ranging in diameter from 9 feet to 13.5 
feet, and (c) a 1,900-foot-long steel penstock ranging in diameter from 
7 feet to 9 feet branching from a Y-connection between the Angeles 
tunnel portal and the main trifurcation; (8) the Castaic powerplant 
located on the upstream end of Elderberry Forebay, which is a pumping-
generating powerhouse containing six reversible Francis-type pump-
turbine units each with a dependable capacity of 205.35 MW; (9) one 
Pelton-type pump starting turbine unit, housed in a separate building, 
used solely to start the six main units and is not used for power 
generation; (10) a fenced switchyard adjacent to the powerhouse; (11) 
the 1,935-foot-long, 179-foot-high zoned earthfill Elderberry Forebay 
dam with a 25-foot-wide crest at elevation 1,550 feet; (12) the 496-
acre Elderberry Forebay that serves as an afterbay with a gross storage 
capacity of 31,196 acre-feet at an elevation of 1,540 feet; (13) an 
uncontrolled, emergency spillway with an overflow weir crest at 
elevation 1,540 feet and a spill capacity of at least 12,000 cfs 
connecting the Elderberry Forebay to the non-project Castaic Lake 
located immediately downstream of the forebay; (14) the Elderberry 
Forebay outlet, with a capacity of 17,000 cfs at 1,540-feet elevation, 
consisting of both high-level and low-level outlets equipped with slide 
gates facilities in a tower upstream of the dam; (15) the Storm Bypass 
Channel located on Castaic Creek above Elderberry Forebay with a series 
of three check-dam basins with a total area of about 21 acres; (16) the 
11.4 mile-long, 230-kV Castaic transmission line connecting the 
switchyard to the Haskell Junction substation; (17) recreation 
facilities include the Emigrant Landing Day Use Area, Vista Del Lago 
Visitor Center, Vaquero Day Use Area, Spanish Point Boat-in Picnic 
Area, Serrano Boat-in Picnic Area, Bear Trap Boat-in Picnic Area, 
Yellow Bar Boat-in Picnic Area, and Los Alamos Campground. There are 
project-related roads and trails associated with these facilities.

Applicants' Proposal

    The co-applicants propose to continue operating the project in the 
same manner as it is currently operated. The co-applicants also propose 
to make the following existing facilities part of the license for the 
South SWP Project: (1) the Quail detention embankment, located adjacent 
to the Peace Valley pipeline intake embankment along the northwest 
portion of the Lower Quail canal, which serves as a flood-management 
structure to attenuate waters from Quail Lake or the Lower Quail canal 
and to protect Interstate 5; (2) 99 project road segments totaling 55.4 
miles; and (3) the streamflow gage located on Piru Creek below Pyramid 
Lake near Gorman, CA. Additionally, the co-applicants propose to remove 
the Warne transmission line from the license because it is owned and 
operated by SCE as part of SCE's Pardee-Pastoria-Warne 220-kV 
transmission line and because the transmission line is part of the 
interconnected electric grid the co-applicants believe it is not within 
the Commission's licensing jurisdiction. The co-applicants state the 
transmission line would continue to function as it has historically.
    The purpose of the project is to continue to provide a source of 
hydroelectric power and flood control and serve as a water supply for 
domestic and irrigation purposes. Therefore, under the provisions of 
the Federal Power Act (FPA), the Commission must decide whether to 
issue a license to DWR and LADWP for the project and what conditions 
should be placed on any license issued.

The NEPA Process and the EIS

    The draft and final EIS issued by the Commission will discuss 
impacts that could occur because of the proposed project under the 
following relevant general resource areas:

 geology and soils resources
 aquatic resources
 terrestrial resources
 federally threatened and endangered species
 recreation, land use, and aesthetics
 cultural resources

    Some of the potential effects include: (1) erosion and 
sedimentation; (2) the timing and magnitude of operational flows in 
Piru Creek on water quality and aquatic habitat, including associated 
effects on threatened and endangered species and riparian habitat; (3) 
toxic algal blooms in Pyramid Lake and the spread of non-native, 
invasive mussel species on aquatic communities and project facilities; 
(4) the spread of non-native, invasive terrestrial plant species on 
terrestrial communities; (5) disturbance of vegetation and suitable 
habitat for special-status wildlife species; including federally listed 
plant species; (6) potential effects on recreation facilities and 
aesthetics; (7) public safety resulting from potential project-related 
wildfires; and (8) cultural resources.
    Commission staff will also make recommendations on how to lessen or 
avoid impacts on the various resource areas. Your comments will help 
Commission staff focus its analysis on the issues that may have a 
significant effect on the human environment.
    The draft and final EIS will present Commission staff's independent 
analysis of the issues. On September 30, 2016, Commission staff issued 
a notice of the co-applicant's intent to file a relicense application 
for the project, which also invited agencies wishing to cooperate in 
the preparation of the environmental document. No agencies filed 
requests for cooperating status. A

[[Page 19200]]

draft EIS will be issued for public comment and circulated for review 
by all interested parties. Commission staff will consider all timely 
comments received during the comment period on the draft EIS and revise 
the document, as necessary, before issuing a final EIS. The draft and 
final EIS will be available in electronic format in the public record 
through eLibrary.\4\ If eSubscribed, you will receive an instant email 
notification when the environmental document is issued.
---------------------------------------------------------------------------

    \4\ For instructions on connecting to eLibrary, refer to the 
Additional Information section of this notice this notice.
---------------------------------------------------------------------------

Alternatives Under Consideration

    As part of our review in the EIS, the Commission will consider a 
range of reasonable alternatives that are technically and economically 
feasible and meet the purpose and need for the proposed action. 
Alternatives that do not meet these requirements will be summarized and 
dismissed from further consideration in the EIS document. In addition 
to the proposed action, staff will consider a no-action alternative. We 
are also considering an alternative to the proposed action that 
potentially meets the above criteria: the applicants' proposed action 
with staff modifications, including any mandatory conditions (i.e., the 
staff alternative with mandatory conditions).
    With this notice, we ask commenters to identify other potential 
reasonable alternatives for consideration. The alternatives considered 
may be expanded based on the comments received, provided they meet the 
criteria described above.

Schedule for Environmental Review

    This Notice of Intent identifies Commission staff's planned 
schedule for completion of the final EIS for the project, which is 
based on an issuance of a draft EIS in August 2025, opening a 45-day 
public comment period. All comments filed will be reviewed by staff and 
considered in the Commission's final decision on the proceeding.

Issuance of Notice of Availability of the final EIS March 31, 2026

    This notice identifies the Commission's anticipated schedule for 
issuance of a license order for the project, which serves as the 
Commission's record of decision. We currently anticipate issuing a 
license order for the project no later than:

Issuance of the License Order July 16, 2026

    If a schedule change becomes necessary, an additional notice will 
be provided so that the relevant agencies and interested stakeholders 
are kept informed of the project's progress.

Permits and Authorizations

    The table below lists the anticipated permits and authorizations 
for the project required under federal law. This list may not be all-
inclusive and does not preclude any permit or authorization if it is 
not listed here. Agencies with jurisdiction by law and/or special 
expertise may formally cooperate in the preparation of the Commission's 
EIS and may adopt the EIS to satisfy its NEPA responsibilities related 
to this project.

------------------------------------------------------------------------
                 Agency                      Permit or authorization
------------------------------------------------------------------------
FERC...................................  Non-Federal Hydropower License.
BLM....................................  Right-of-Way Permit; Resource
                                          Management Plan Amendment;
                                          Mandatory Conditioning
                                          Authority under Section 4(e)
                                          of the FPA.
Forest Service.........................  Mandatory Conditioning
                                          Authority under Section 4(e)
                                          of the FPA.
National Marine Fisheries Service......  Reservation of Authority to
                                          Prescribe Fishways under
                                          Section 18 of the FPA.
U.S. Fish and Wildlife Service.........  Consultation under Section 7 of
                                          the Endangered Species Act.
California State Historic Preservation   Consultation under Section 106
 Office.                                  of the National Historic
                                          Preservation Act.
California State Water Resources         Clean Water Act Section 401
 Control Board.                           Water Quality Certification.
------------------------------------------------------------------------

Additional Information

    Additional information about the project is available on the FERC 
website at www.ferc.gov using the eLibrary link. Click on the eLibrary 
link, click on ``General Search'' and enter the Docket No. P-2426 in 
the ``Docket Number'' field. Be sure you have selected an appropriate 
date range. For assistance, please contact FERC Online Support at 
[email protected] or (866) 208-3676, or for TTY, contact (202) 
502-8659.
    Any questions regarding this notice may be directed to Quinn 
Emmering, the FERC relicensing coordinator for the South SWP Project, 
at (202) 502-6382 or [email protected].

    Dated: April 30, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-07875 Filed 5-5-25; 8:45 am]
BILLING CODE 6717-01-P