[Federal Register Volume 90, Number 79 (Friday, April 25, 2025)]
[Notices]
[Pages 17428-17429]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-07150]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP14-119-003; CP14-120-003]


Notice of Request for Extension of Time: Trunkline Gas Company, 
LLC; Lake Charles LNG Company, LLC; Lake Charles LNG Export Company, 
LLC

    Take notice that on April 11, 2025, Lake Charles LNG Company, LLC; 
Lake Charles LNG Export Company, LLC (collectively, Lake Charles LNG); 
and Trunkline Gas Company, LLC (Trunkline; collectively, the 
Applicants) requested that the Commission grant an extension of time, 
until December 31, 2031, to construct and place into service its 
Liquefaction Project and Pipeline Modifications Project (collectively, 
the Project) located in Arkansas, Mississippi, and Louisiana as 
authorized in the Order Granting Section 3 and Section 7 Authorizations 
and Approving Abandonment (Order).\1\ The Order required Trunkline to 
complete construction of the Pipeline Modifications Project and make it 
available for service within four years of the date of the Order, or by 
December 17, 2019; the Order further required Lake Charles LNG to 
complete construction of the Liquefaction Project and make it available 
for service within five years of the date of the Order, or by December 
17, 2020.
---------------------------------------------------------------------------

    \1\ Lake Charles LNG Company, LLC, et al., 153 FERC ] 61,300 
(2015), reh'g denied, 155 FERC ] 61,328 (2016) (Order).
---------------------------------------------------------------------------

    On December 5, 2019, the Commission granted the Applicants an 
extension of time until December 16, 2025 to complete construction of 
the Project and make it available for service.\2\ The Commission has 
subsequently granted a second extension of time, making December 17, 
2028 the current date for the Project to be constructed and placed into 
service.\3\
---------------------------------------------------------------------------

    \2\ Lake Charles LNG Company, LLC, et al., Docket Nos. CP14-119-
000, et al., delegated letter order (December 5, 2019).
    \3\ Lake Charles LNG Company, LLC, et al., 179 FERC ] 61,086 at 
P 21 (2022).
---------------------------------------------------------------------------

    The Applicants experienced delays due to the effects of COVID-19, 
changes in global demand for liquefied natural gas (LNG), material 
development of a Project sponsor resulting in Energy Transfer LP 
(Energy Transfer) assuming 100% of the Project, and the need to re-
engage engineering, procurement, and construction contractors.
    The Applicants state that it, along with Energy Transfer, have made 
significant progress toward execution of a commercially viable level of 
long-term commercial agreements with LNG offtake customers for the 
Project and reaching a final investment decision (FID). The Applicants 
state that numerous Project construction-related activities have been, 
and continue to be, undertaken. The Applicants assert that the FID 
requires that all Commission authorization remain in full force and 
effect during construction of the Project; thus, it requests a three-
year extension, until December 31, 2031, to complete the Project and 
place it into service.
    This notice establishes a 15-calendar day intervention and comment 
period deadline. Any person wishing to comment on the Applicants' 
request for an extension of time may do so. No reply comments or 
answers will be considered. If you wish to obtain legal status by 
becoming a party to the proceedings for this request, you should, on or 
before the comment date stated below, file a motion to intervene in 
accordance with the requirements of the Commission's Rules of Practice 
and Procedure (18 CFR 385.214 or 385.211) and the Regulations under the 
Natural Gas Act (NGA) (18 CFR 157.10).
    As a matter of practice, the Commission itself generally acts on 
requests for extensions of time to complete construction for NGA 
facilities when such requests are contested before order issuance. For 
those extension requests that are contested,\4\ the Commission will aim 
to issue an order acting on the request within 45 days.\5\ The 
Commission will address all arguments relating to whether the applicant 
has demonstrated there is good cause to grant the extension.\6\ The 
Commission will not consider arguments that re-litigate the issuance of 
the certificate order, including whether the Commission properly found 
the

[[Page 17429]]

project to be in the public convenience and necessity and whether the 
Commission's environmental analysis for the certificate complied with 
the National Environmental Policy Act (NEPA).\7\ At the time a pipeline 
requests an extension of time, orders on certificates of public 
convenience and necessity are final and the Commission will not re-
litigate their issuance.\8\ The Director of the Office of Energy 
Projects, or his or her designee, will act on all of those extension 
requests that are uncontested.
---------------------------------------------------------------------------

    \4\ Contested proceedings are those where an intervenor disputes 
any material issue of the filing. 18 CFR 385.2201(c)(1).
    \5\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
    \6\ Id. at P 40.
    \7\ Similarly, the Commission will not re-litigate the issuance 
of an NGA section 3 authorization, including whether a proposed 
project is not inconsistent with the public interest and whether the 
Commission's environmental analysis for the permit order complied 
with NEPA.
    \8\ Algonquin Gas Transmission, LLC, 170 FERC ] 61,144, at P 40 
(2020).
---------------------------------------------------------------------------

    In addition to publishing the full text of this document in the 
Federal Register, the Commission provides all interested persons an 
opportunity to view and/or print the contents of this document via the 
internet through the Commission's Home Page (http://www.ferc.gov). From 
the Commission's Home Page on the internet, this information is 
available on eLibrary. The full text of this document is available on 
eLibrary in PDF and Microsoft Word format for viewing, printing, and/or 
downloading. To access this document in eLibrary, type the docket 
number excluding the last three digits of this document in the docket 
number field.
    User assistance is available for eLibrary and the Commission's 
website during normal business hours from FERC Online Support at (202) 
502-6652 (toll free at 1-866-208-3676) or email at 
[email protected], or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at 
[email protected].
    The Commission strongly encourages electronic filings of comments 
in lieu of paper using the ``eFile'' link at http://www.ferc.gov. In 
lieu of electronic filing, you may submit a paper copy which must 
reference the Project docket number.

To file via USPS: Debbie-Anne A. Reese, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426.
To file via any other courier: Debbie-Anne A. Reese, Secretary, Federal 
Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville, Maryland 
20852.

    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or [email protected].
    Comment Date: 5 p.m. Eastern Time on May 6, 2025.

    Dated: April 21, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-07150 Filed 4-24-25; 8:45 am]
BILLING CODE 6717-01-P