[Federal Register Volume 90, Number 66 (Tuesday, April 8, 2025)]
[Notices]
[Pages 15144-15145]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2025-06016]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 15116-001]


Ocean Renewable Power Company, Inc.; Notice of Intent To File 
License Application, Filing of Draft Application, Request for Waivers 
of Integrated Licensing Process Regulations Necessary for Expedited 
Processing of a Hydrokinetic Pilot Project License Application, and 
Soliciting Comments

    a. Type of Filing: Notice of Intent to File a License Application 
for an Original License for a Hydrokinetic Pilot Project.
    b. Project No.: 15116-001.
    c. Date Filed: March 18, 2025.
    d. Submitted By: Ocean Renewable Power Company, Inc. (ORPC).
    e. Name of Project: East Foreland Tidal Energy Project.
    f. Location: On the Cook Inlet waterway near Nikiski, Alaska and 
adjacent lands of the Kenai Peninsula Borough, Alaska.
    g. Filed Pursuant to: 18 CFR 5.3 of the Commission's regulations.
    h. Applicant Contact: Nathan Johnson, Vice President, Development, 
ORPC, 254 Commercial Street, Suite 119B, Portland, ME 04101; (207) 712-
2927; [email protected].
    i. FERC Contact: Amy Chang at (202) 502-6154 or email at 
[email protected].
    j. ORPC has filed with the Commission: (1) a notice of intent (NOI) 
to file an application for an original license for a hydrokinetic pilot 
project and a draft license application with monitoring plans; (2) a 
request for waivers of the integrated licensing process regulations 
necessary for expedited processing of a hydrokinetic pilot project 
license application; (3) a proposed process plan and schedule; (4) a 
request to be designated as the non-federal representative for section 
7 of the Endangered Species Act (ESA) consultation; and (5) a request 
to be designated as the non-federal representative for section 106 
consultation under the National Historic Preservation Act (collectively 
the pre-filing materials).
    k. With this notice, we are soliciting comments on the pre-filing 
materials listed in paragraph j above, including the draft license 
application and monitoring plans. All comments should be sent to the 
address above in paragraph h. In addition, all comments must be filed 
with the Commission. The Commission strongly encourages electronic 
filing. Please file comments using the Commission's eFiling system at 
https://ferconline.ferc.gov/FERCOnline.aspx. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at https://ferconline.ferc.gov/QuickComment.aspx. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, you may submit a paper 
copy. Submissions sent via the U.S. Postal Service must be addressed 
to: Debbie-Anne A. Reese, Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE, Room 1A, Washington, DC 20426. 
Submissions sent via any other carrier must be addressed to: Debbie-
Anne A. Reese, Secretary, Federal Energy Regulatory Commission, 12225 
Wilkins Avenue, Rockville, Maryland 20852. All filings must clearly 
identify the project name and docket number on the first page: East 
Foreland Tidal Energy Project (P-15116-001). Any individual or entity 
interested in submitting comments on the pre-filing materials must do 
so by May 17, 2025.
    l. With this notice, we are approving ORPC's request to be 
designated as the non-federal representative for section 7 of the ESA 
and its request to initiate consultation under section 106 of the 
National Historic Preservation Act; and recommending that it begin 
informal consultation with: (a) the U.S. Fish and Wildlife Service and 
NOAA Fisheries as required by section 7 of ESA; and (b) the Alaska 
State Historic Preservation Officer, as required by section 106 of the 
National Historic Preservation Act, and the implementing regulations of 
the Advisory Council on Historic Preservation at 36 CFR 800.2.
    m. With this notice, we also are asking federal, state, local, and 
tribal agencies with jurisdiction and/or expertise with respect to 
environmental issues to cooperate with us in the preparation of the 
environmental document. Agencies who would like to request cooperating 
status should follow the instructions for filing comments described in 
paragraph ``k'' above.
    n. This notice does not constitute the Commission's approval of 
ORPC's request to use the Pilot Project Licensing Procedures. Upon its 
review of the project's overall characteristics relative to the pilot 
project criteria, the draft license application contents, and any 
comments filed, the Commission will determine whether there is adequate 
information to conclude the pre-filing process.
    o. The East Foreland Tidal Energy Project would consist of: (1) a 
1.75-megawatt (MW) Proteus Marine Renewables AR1750 tidal device and 
associated anchoring system; (2) a 0.23 MW ORPC TidGen80[supreg] tidal 
device and associated mooring system; (3) two dedicated power and data 
cables running from the tidal devices to respective shore stations; (4) 
four pre-fabricated standard shipping container shore stations; (5) a 
transmission line; and (6) appurtenant facilities. The project would 
have a total estimated average annual generation of 6,078,000 kilowatt 
hours per year.
    p. A copy of the draft license application and all pre-filing 
materials are available for review on the Commission's website (http://www.ferc.gov), using the ``eLibrary'' link. Enter the docket number, 
excluding the last three digits of the sub-docket in the docket number 
field, to access documents. For assistance,

[[Page 15145]]

contact FERC Online Support. A copy is also available via the contact 
in paragraph h.
    q. Pre-filing Process Schedule. The pre-filing process will be 
conducted pursuant to the following tentative schedule. Revisions to 
the schedule below may be made based on staff's review of the draft 
application and any comments received.

------------------------------------------------------------------------
                Milestone                              Date
------------------------------------------------------------------------
Comments on pre-filing materials due....  May 17, 2025.
Issuance of meeting notice (if needed)..  June 1, 2025.
Public meeting/technical conference (if   July 1, 2025.
 needed).
------------------------------------------------------------------------

    The Commission's Rules of Practice and Procedure provide that if a 
filing deadline falls on a Saturday, Sunday, holiday, or other day when 
the Commission is closed for business, the filing deadline does not end 
until the close of business on the next business day. 18 CFR 
385.2007(a)(2).
    r. Register online at https://ferconline.ferc.gov/FERCOnline.aspx 
to be notified via email of new filings and issuances related to this 
or other pending projects. For assistance, contact FERC Online Support.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
Tribal members and others, access publicly available information and 
navigate Commission processes. For public inquiries and assistance with 
making filings such as interventions, comments, or requests for 
rehearing, the public is encouraged to contact OPP at (202) 502-6595, 
or at [email protected].

    Dated: April 2, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-06016 Filed 4-7-25; 8:45 am]
BILLING CODE 6717-01-P