DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP25-24-000]


Texas Eastern Transmission, LP; Notice of Schedule for the 
Preparation of an Environmental Assessment for the Entriken Amendment 
Project

    On November 22, 2024, Texas Eastern Transmission, LP (Texas 
Eastern) filed an application in Docket No. CP25-24-000, requesting 
permission to amend the Certificate of Public Convenience and Necessity 
for the Armagh and Entriken Replacement Project, issued on October 23, 
2023, under Docket No. CP22-486-000 (2023 Order). With the Entriken 
Amendment Project (Amendment), Texas Eastern proposes to modify the 
certificated facilities at the Entriken Compressor Station due to 
uncertainties regarding obtaining the electrical transmission power 
needed to support the electric-motor driven (EMD) compressor unit 
approved in the 2023 Order.
    On December 9, 2024, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing Federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a Federal authorization 
within 90 days of the date of issuance of the Commission staff's 
environmental document for the Project.
    This notice identifies Commission staff's intention to prepare an 
environmental assessment (EA) for the Project and the planned schedule 
for the completion of the environmental review.\1\
---------------------------------------------------------------------------

    \1\ For tracking purposes, the Council on Environmental Quality 
unique identification number for documents relating to this 
environmental review is EAXX-019-20-000-1739434223. 40 CFR 
1501.5(c)(4) (2024).
---------------------------------------------------------------------------

Schedule for Environmental Review

Issuance of EA--March 7, 2025
90-day Federal Authorization Decision Deadline \2\--June 5, 2025
---------------------------------------------------------------------------

    \2\ The Commission's deadline applies to the decisions of other 
Federal agencies, and State agencies acting under federally 
delegated authority, that are responsible for Federal 
authorizations, permits, and other approvals necessary for proposed 
projects under the Natural Gas Act. Per 18 CFR 157.22(a), the 
Commission's deadline for other agency's decisions applies unless a 
schedule is otherwise established by Federal law.

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Under the 2023 Order, the Armagh and Entriken Replacement Project 
consisted of the abandonment of pipeline facilities, construction of 
pipeline facilities, and the abandonment of gas-driven compression 
facilities to be replaced with EMD facilities. With the Amendment 
Project, Texas Eastern proposes to modify the certificated facilities 
at the Entriken Compressor Station from a 24,000 horsepower (hp) EMD 
compressor unit, to a 24,306 hp gas-driven compressor unit.

Background

    On January 14, 2025, the Commission issued a Notice of Scoping 
Period Requesting Comments on Environmental Issues for the Proposed 
Amendment to the Certificate of Public Convenience and Necessity for 
the Entriken Amendment Project (Notice of Scoping). The Notice of 
Scoping was sent to affected landowners; Federal, State, and local 
government agencies; elected officials; environmental and public 
interest groups; Native American Tribes; other interested parties; and 
local libraries and newspapers. No comments were received in response 
to the Notice of Scoping. All substantive comments will be addressed in 
the EA.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of formal issuances and submittals in specific dockets, the 
Commission offers a free service called eSubscription. This service 
provides automatic notification of filings made to subscribed dockets, 
document summaries, and direct links to the documents. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
    The Commission's Office of Public Participation (OPP) supports 
meaningful public engagement and participation in Commission 
proceedings. OPP can help members of the public, including landowners, 
community organizations, Tribal members and others, access publicly 
available information and navigate Commission processes. For public 
inquiries and assistance with making filings such as interventions, 
comments, or requests for rehearing, the public is encouraged to 
contact OPP at (202) 502-6595 or [email protected].
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC website (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP25-24), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
website also provides access to the texts of formal documents issued by 
the Commission, such as orders, notices, and rule makings.

    Dated: February 14, 2025.
Debbie-Anne A. Reese,
Secretary.
[FR Doc. 2025-02966 Filed 2-21-25; 8:45 am]
BILLING CODE 6717-01-P