NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-275 and 50-323; NRC-2023-0192]
Pacific Gas and Electric Company; Diablo Canyon Nuclear Power
Plant, Units 1 and 2; Draft Supplemental Environmental Impact Statement
AGENCY: Nuclear Regulatory Commission.
ACTION: Public meetings and request for comment.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing for
public comment draft Supplement 62 to the Generic Environmental Impact
Statement (GEIS) for License Renewal of Nuclear Plants, NUREG-1437,
regarding the proposed renewal of Facility Operating License Nos. DPR-
80 and DPR-82 for an additional 20 years for Diablo Canyon Nuclear
Power Plant, Units 1 and 2 (Diablo Canyon). Diablo Canyon is located in
San Luis Obispo County, California, approximately 12 miles west-
southwest of San Luis Obispo. Possible alternatives to the proposed
action of license renewal for Diablo Canyon include the no-action
alternative and replacement power alternatives.
DATES: The NRC will hold a virtual public meeting on November 14, 2024,
at 10 a.m. pacific time (PT) and an in-person public meeting on
November 20, 2024, at 6 p.m. PT. The public meeting details can be
found on the NRC's Public Meeting Schedule at https://www.nrc.gov/pmns/mtg. Members of the public are invited to submit comments by December
16, 2024. Comments received after that date will be considered if it is
practical to do so, but the NRC is able to ensure consideration only
for comments received on or before that date.
ADDRESSES: You may submit comments by any of the following methods;
however, the NRC encourages electronic comment submission through the
Federal rulemaking website:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0192. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
telephone: 301-415-0624; email: [email protected]. For technical
questions, contact the individual listed in the FOR FURTHER INFORMATION
CONTACT section of this document.
Email: Comments may be submitted to the NRC electronically
using the email address [email protected].
Mail comments to: Office of Administration, Mail Stop:
TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, ATTN: Program Management, Announcements and Editing Staff.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Kim Conway, Office of Nuclear Material
Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001; telephone: 301-415-1335; email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2023-0192 when contacting the NRC
about the availability of information for this action. You may obtain
publicly available information related to this action using any of the
following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0192.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, at 301-415-4737,
or by email to [email protected]. Draft Supplement 62 to the GEIS
for License Renewal of Nuclear Plants, NUREG-1437, is available in
ADAMS under Accession No. ML24299A167.
NRC's PDR: The PDR, where you may examine and order copies
of publicly available documents, is open by appointment. To make an
appointment to visit the PDR, please send an email to
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8
a.m. and 4 p.m. eastern time, Monday through Friday, except Federal
holidays.
Public Library: A copy of draft Supplement 62 to the GEIS
for License Renewal of Nuclear Plants, NUREG-1437, regarding the
proposed renewal of Facility Operating License Nos. DPR-80 and DPR-82
for an additional 20 years for Diablo Canyon will be available for
public review at the San Luis Obispo Library, 995 Palm St., San Luis
Obispo, CA 93403.
B. Submitting Comments
The NRC encourages electronic comment submission through the
Federal rulemaking website (https://www.regulations.gov). Please
include Docket ID NRC-2023-0192 in your comment submission.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at
https://www.regulations.gov as well as enter the comment submissions
into ADAMS. The NRC does not routinely edit comment submissions to
remove identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information
[[Page 87434]]
before making the comment submissions available to the public or
entering the comment into ADAMS.
II. Discussion
The NRC is issuing for public comment draft Supplement 62 to the
GEIS for License Renewal of Nuclear Plants, NUREG-1437, regarding the
proposed renewal of Facility Operating License Nos. DPR-80 and DPR-82
for an additional 20 years for Diablo Canyon. Draft Supplement 62 to
the GEIS includes the NRC staff's evaluation of the environmental
impacts of the proposed action and alternatives to the proposed action.
The NRC staff's preliminary recommendation is that the adverse
environmental impacts of license renewal for Diablo Canyon are not so
great that preserving the option of license renewal for energy-planning
decisionmakers would be unreasonable.
Dated: October 28, 2024.
For the Nuclear Regulatory Commission.
Theodore Smith,
Acting Deputy Director, Division of Rulemaking, Environmental, and
Financial Support, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2024-25444 Filed 10-31-24; 8:45 am]
BILLING CODE 7590-01-P