[Federal Register Volume 89, Number 15 (Tuesday, January 23, 2024)]
[Notices]
[Pages 4290-4291]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2024-01262]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2544-052]
Hydro Technology, Inc.; Notice of Intent To Prepare an
Environmental Assessment
On December 27, 2021, Hydro Technology, Inc filed an application
for a subsequent license to continue operating the existing 1,200-
kilowatt Meyers Falls Hydroelectric Project No. 2544 (Meyers Falls
Project or project). The project is located on the Colville River in
Stevens County, Washington. The project does not occupy federal land.
In accordance with the Commission's regulations, on March 28, 2023,
[[Page 4291]]
Commission staff issued a notice that the project was ready for
environmental analysis (REA notice). Based on the information in the
record, including comments filed on the REA notice, staff does not
anticipate that licensing the project would constitute a major federal
action significantly affecting the quality of the human environment. On
June 7, 2023, the Commission issued a notice indicating that staff
intended to prepare a draft and final Environmental Assessment (EA).
However, upon further review, staff intends to prepare a single EA on
the application to relicense the Meyers Falls Project.
The EA will be issued and circulated for review by all interested
parties. All comments filed on the EA will be analyzed by staff and
considered in the Commission's final licensing decision.
The Commission's Office of Public Participation (OPP) supports
meaningful public engagement and participation in Commission
proceedings. OPP can help members of the public, including landowners,
environmental justice communities, Tribal members and others, access
publicly available information and navigate Commission processes. For
public inquiries and assistance with making filings such as
interventions, comments, or requests for rehearing, the public is
encouraged to contact OPP at (202) 502-6595 or [email protected].
By this notice, Commission staff is updating the procedural
schedule for completing the EA. The revised schedule is shown below.
Further revisions to the schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues EA...................... May 2024.\1\
Comments on EA............................ June 2024.
------------------------------------------------------------------------
Any questions regarding this notice may be directed to Maryam
Zavareh at (202) 502-8474 or [email protected].
---------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations
under 40 CFR 1501.10(b)(1) (2022) require that EAs be completed
within 1 year of the federal action agency's decision to prepare an
EA. See National Environmental Policy Act, 42 U.S.C. 4321 et seq.,
as amended by section 107(g)(1)(B)(iii) of the Fiscal Responsibility
Act of 2023, Public Law 118-5, 4336a, 137 Stat. 42.
Dated: January 17, 2024.
Debbie-Anne A. Reese,
Acting Secretary.
[FR Doc. 2024-01262 Filed 1-22-24; 8:45 am]
BILLING CODE 6717-01-P