[Federal Register Volume 88, Number 221 (Friday, November 17, 2023)]
[Notices]
[Page 80291]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2023-25398]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2639-028]
Northern States Power Company-Wisconsin; Notice of Intent To
Prepare an Environmental Assessment
On November 30, 2021, Northern States Power Company-Wisconsin filed
an application for a new major license to continue operating the
existing, licensed, 30.75-megawatt Cornell Hydroelectric Project No.
2639 (Cornell Project). The project is located on the Lower Chippewa
River, in the township of Cornell, in Chippewa County, Wisconsin. The
project does not occupy Federal land.
In accordance with the Commission's regulations, on July 14, 2023,
Commission staff issued a notice that the project was ready for
environmental analysis (REA notice). Based on the information in the
record staff does not anticipate that licensing the project would
constitute a major Federal action significantly affecting the quality
of the human environment. Therefore, staff intends to prepare an
Environmental Assessment (EA) on the application to license the Cornell
Project.
The EA will be issued and circulated for review by all interested
parties. All comments filed on the EA will be analyzed by staff and
considered in the Commission's final licensing decision.
The application will be processed according to the following
schedule. Revisions to the schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target date
------------------------------------------------------------------------
Commission issues EA.................. April 2024 \1\
Comments on EA........................ May 2024.
------------------------------------------------------------------------
\1\ The Council on Environmental Quality's (CEQ) regulations under 40
CFR 1501.10(b)(1) require that EAs be completed within 1 year of the
Federal action agency's decision to prepare an EA. This notice
establishes the Commission's intent to prepare an EA for the Cornell
Project. Therefore, in accordance with CEQ's regulations, the EA must
be issued within 1 year of the issuance date of this notice.
Any questions regarding this notice may be directed to Michael
Davis at [email protected] or call at 202-502-8339.
Dated: November 9, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-25398 Filed 11-16-23; 8:45 am]