DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 15300-000]
Heard County Pumped Storage Project; Notice of Preliminary Permit
Application Accepted for Filing and Soliciting Comments, Motions To
Intervene, and Competing Applications
On January 31, 2023, BOST1 Hydroelectric, LLC., filed an
application for a preliminary permit, pursuant to section 4(f) of the
Federal Power Act (FPA), proposing to study the feasibility of a pumped
storage hydropower project located near the City of Enon Grove, Heard
County, Georgia. The sole purpose of a preliminary permit, if issued,
is to grant the permit holder priority to file a license application
during the permit term. A preliminary permit does not authorize the
permit holder to perform any land-disturbing activities or otherwise
enter upon lands or waters owned by others without the owners' express
permission.
The proposed Heard County Pumped Storage Project would consist of
the following: (1) a 20-foot-long, 30-foot-deep reinforced concrete
intake structure with trash racks, and a pumping station on Hilly Mill
Creek; (2) a 24-inch-diameter fill pipeline to the upper reservoir; (3)
a geotextile lined rock filled embankment forming an enclosed upper
reservoir; (4) a 66-foot-deep enclosed upper reservoir with a storage
capacity of 5,300 acre-feet; (5) a lower underground reservoir
consisting of concentric circular tunnels reaching a depth of 2,100
feet below the surface, with the total length of the tunnels being
170,000 feet; (6) a reinforced morning glory type water intake situated
within the upper reservoir with an outer diameter of 95 feet and an
inside diameter of 38 feet; (7) a 23-foot-diameter, 2,300-foot-long
granite bedrock vertical tunnel trifurcating into three 10-foot-
diameter steel lined penstocks leading to three reversible Francis pump
turbines; (8) a 460-foot-long, 80-foot-wide, 160-foot-high powerhouse,
200 feet below the lower reservoir containing the three pump turbine
units with a total installed capacity of 1,000 megawatts; (9) a
separate 60-foot-wide, 410-foot-long, 160-foot-high underground
transformer gallery near the powerhouse; and (10) a 1-mile-long, 500
kilovolt transmission line east of the proposed upper reservoir. The
lower reservoir tunneling would be accomplished using two 42.5-foot-
diameter tunnel boring machines with an access ramp of the same size
from the surface. The powerhouse would be excavated using traditional
drill and blast methods. The proposed project would have an estimated
annual generation of 2,628,000 megawatt-hours.
Applicant Contact: Douglas Spaulding, Nelson Energy, 8441 Wayzata
Blvd., Suite 101, Golden Valley, MN 55426; phone: (952) 544-8133.
FERC Contact: Michael Spencer; phone: (202) 502-6093, or by email
at [email protected].
Deadline for filing comments, motions to intervene, competing
applications (without notices of intent), or notices of intent to file
competing applications: 60 days from the issuance of this notice.
Competing applications and notices of intent must meet the requirements
of 18 CFR 4.36.
The Commission strongly encourages electronic filing. Please file
comments, motions to intervene, notices of intent, and competing
applications using the Commission's eFiling system at https://ferconline.ferc.gov/eFiling.aspx. Commenters can submit brief comments
up to 6,000 characters, without prior registration, using the eComment
system at https://ferconline.ferc.gov/QuickComment.aspx. You must
include your name and contact information at the end of your comments.
For assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, you may submit a paper copy.
Submissions sent via the U.S. Postal Service must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE, Room 1A, Washington, DC 20426. Submissions sent via
any other carrier must be addressed to: Kimberly D. Bose, Secretary,
Federal Energy Regulatory Commission, 12225 Wilkins Avenue, Rockville,
Maryland 20852. The first page of any filing should include docket
number P-15300-000.
More information about this project, including a copy of the
application, can be viewed or printed on the ``eLibrary'' link of the
Commission's website at
[[Page 20875]]
https://elibrary.ferc.gov/eLibrary/search. Enter the docket number (P-
15300) in the docket number field to access the document. For
assistance, contact FERC Online Support.
Dated: April 3, 2023.
Kimberly D. Bose,
Secretary.
[FR Doc. 2023-07391 Filed 4-6-23; 8:45 am]
BILLING CODE 6717-01-P