NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-293 and 72-1044; NRC-2023-0040]
Holtec Decommissioning International, LLC; Pilgrim Nuclear Power
Station Independent Spent Fuel Storage Installation
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued an
exemption to Holtec Decommissioning International, LLC, (HDI), for
Pilgrim Nuclear Power Station (PNPS), Independent Spent Fuel Storage
Installation (ISFSI). The exemption allows PNPS to deviate from the
requirements in Certificate of Compliance (CoC) No. 1014, Amendment No.
14, Appendix A, Technical Specifications (TS) for the HI-STORM 100
System, Section 5.4, ``Radioactive Effluent Control Program,''
subsection c related to the timing of submission for an annual
radiological effluent report.
DATES: The exemption was issued on January 31, 2023.
ADDRESSES: Please refer to Docket ID NRC-2023-0040 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2023-0040. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
[[Page 11485]]
telephone: 301-415-0624; email: [email protected]. For technical
questions, contact the individual listed in the For Further Information
Contact section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document.
NRC's PDR: You may examine and purchase copies of public
documents, by appointment, at the NRC's PDR, Room P1 B35, One White
Flint North, 11555 Rockville Pike, Rockville, Maryland 20852. To make
an appointment to visit the PDR, please send an email to
[email protected] or call 1-800-397-4209 or 301-415-4737, between 8
a.m. and 4 p.m. eastern time (ET), Monday through Friday, except
Federal holidays.
FOR FURTHER INFORMATION CONTACT: Tilda Liu, Office of Nuclear Material
Safety and Safeguards, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001; telephone: 404-997-4730, email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Background
Holtec Decommissioning International, LLC, (HDI) submitted a
request to the NRC for an exemption from title 10 of the Code of
Federal Regulations (10 CFR) 72.212(a)(2), (b)(2), (b)(3), (b)(4),
(B)(5)(i), (b)(11), and 72.214 for Pilgrim Independent Spent Fuel
Storage Facility (ISFSI) Annual Radioactive Effluent Release Report
(ARERR), by letter dated August 29, 2022 (ADAMS Accession No.
ML22241A112), as supplemented by letter dated December 9, 2022 (ADAMS
Accession No. ML22343A165). In particular, the exemption request, if
approved, would allow Pilgrim Nuclear Power Station (PNPS) to deviate
from the requirements in Certificate of Compliance (CoC) No. 1014,
Amendment No. 14, Appendix A, Technical Specifications (TS) for the HI-
STORM 100 System, Section 5.4, ``Radioactive Effluent Control
Program,'' subsection c related to the timing of submission for its
ARERR.
In its August 29, 2022 letter, HDI requested relief regarding the
60-day reporting requirement, so that the annual liquid and gaseous
effluent release report for the PNPS ISFSI be incorporated into, and
submitted with, the Pilgrim site ARERR on or before May 15, rather than
prior to March 1, of each year to align with the submittal of its ARERR
as required by PNPS Renewed Facility Operating License, DPR-35, PNPS
Defueled Safety Analysis Report Section 5.0, ``Administrative
Controls,'' Appendix B, Section B-5.6.3, ``Radioactive Effluent Release
Report.''
II. Discussion
The NRC issued an exemption (ADAMS Package Accession No.
ML22356A070) to HDI for the PNPS ISFSI. The exemption granted provides
relief from the 60-day requirement so that the annual effluent release
report for the PNPS ISFSI may be submitted on or before May 15, rather
than prior to March 1, of each year. The granted exemption only changes
the due date and not the content of the information that the licensee
would provide in the annual report.
III. Conclusion
Based on the staff's evaluation, the NRC has determined that,
pursuant to 10 CFR 72.7, ``Specific Exemptions,'' the exemption is
authorized by law, will not endanger life or property or the common
defense and security, and is otherwise in the public interest.
Accordingly, the NRC granted HDI an exemption from 10 CFR 72.212(a)(2),
(b)(2), (b)(3), (b)(4), (b)(5)(i), (b)(11), and 72.214.
Dated: February 16, 2023.
For the Nuclear Regulatory Commission.
Tilda Y. Liu,
Acting Chief, Storage and Transportation Licensing Branch, Division of
Fuel Management, Office of Nuclear Material Safety and Safeguards.
[FR Doc. 2023-03695 Filed 2-22-23; 8:45 am]