[Federal Register Volume 87, Number 61 (Wednesday, March 30, 2022)]
[Notices]
[Pages 18365-18366]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2022-06697]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP22-25-000]
Notice of Scoping Period Requesting Comments on Environmental
Issues for the Proposed Venture Global Calcasieu Pass, LLC Calcasieu
Pass Uprate Amendment Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental document, that will discuss
the environmental impacts of the Calcasieu Pass Uprate Amendment
Project (Project) involving operation of facilities by Venture Global
Calcasieu Pass, LLC (Calcasieu Pass) in Cameron Parish, Louisiana. The
Commission will use this environmental document in its decision-making
process to determine whether the project is in the public interest.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies regarding the project. As part of the National Environmental
Policy Act (NEPA) review process, the Commission takes into account
concerns the public may have about proposals and the environmental
impacts that could result from its action whenever it considers the
issuance of an authorization. This gathering of public input is
referred to as ``scoping.'' The main goal of the scoping process is to
focus the analysis in the environmental document on the important
environmental issues. Additional information about the Commission's
NEPA process is described below in the NEPA Process and Environmental
Document section of this notice.
By this notice, the Commission requests public comments on the
scope of issues to address in the environmental document. To ensure
that your comments are timely and properly recorded, please submit your
comments so that the Commission receives them in Washington, DC on or
before 5:00 p.m. Eastern Time on April 25, 2022. Comments may be
submitted in written form. Further details on how to submit comments
are provided in the Public Participation section of this notice.
Your comments should focus on the potential environmental effects,
reasonable alternatives, and measures to avoid or lessen environmental
impacts. Your input will help the Commission staff determine what
issues they need to evaluate in the environmental document. Commission
staff will consider all written comments during the preparation of the
environmental document.
If you submitted comments on this project to the Commission before
the opening of this docket on December 3, 2021, you will need to file
those comments in Docket No. CP22-25-000 to ensure they are considered
as part of this proceeding.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
Venture Global provided landowners with a fact sheet prepared by
the FERC entitled ``An Interstate Natural Gas Facility On My Land? What
Do I Need To Know?'' which addresses typically asked questions,
including the use of eminent domain and how to participate in the
Commission's proceedings. This fact sheet along with other landowner
topics of interest are available for viewing on the FERC website
(www.ferc.gov) under the Natural Gas Questions or Landowner Topics
link.
Public Participation
There are three methods you can use to submit your comments to the
Commission. Please carefully follow these instructions so that your
comments are properly recorded. The Commission encourages electronic
filing of comments and has staff available to assist you at (866) 208-
3676 or [email protected].
(1) You can file your comments electronically using the eComment
feature, which is located on the Commission's website (www.ferc.gov)
under the link to FERC Online. Using eComment is an easy method for
submitting brief, text-only comments on a project;
(2) You can file your comments electronically by using the eFiling
feature, which is also located on the Commission's website
(www.ferc.gov) under the link to FERC Online. With eFiling, you can
provide comments in a variety of formats by attaching them as a file
with your submission. New eFiling users must first create an account by
clicking on ``eRegister.'' You will be asked to select the type of
filing you are making; a comment on a particular project is considered
a ``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the Commission. Be sure to reference the project docket number (CP22-
25-000) on your letter. Submissions sent via the U.S. Postal Service
must be addressed to: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC
20426. Submissions sent via any other carrier must be addressed to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission,
12225 Wilkins Avenue, Rockville, Maryland 20852.
Additionally, the Commission offers a free service called
eSubscription which makes it easy to stay informed of all issuances and
submittals regarding the dockets/projects to which you subscribe. These
instant email notifications are the fastest way to receive notification
and provide a link to the document files which can reduce the amount of
time you spend researching proceedings. Go to https://www.ferc.gov/ferc-online/overview to register for eSubscription.
Summary of the Proposed Project
Calcasieu Pass proposes to increase the Export Terminal's
authorized peak liquefaction capacity achievable under optimal
conditions from 12.0 million metric tons per annum to 12.4 million
metric tons per annum of LNG--or from approximately 620 billion cubic
feet to approximately 640.666 billion cubic feet per year (gas
equivalence). According to Calcasieu Pass, this proposed increase in
the peak liquefaction capacity reflects refinements in the conditions
and assumptions concerning the maximum potential operations. The
requested increase does not involve the
[[Page 18366]]
construction of any new facilities nor any modification of the
previously authorized facilities. There would be no land disturbance
required for this Project.
The general location of the Calcasieu Pass Export Terminal is shown
in appendix 1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary''. For instructions on
connecting to eLibrary, refer to the last page of this notice. At
this time, the Commission has suspended access to the Commission's
Public Reference Room due to the proclamation declaring a National
Emergency concerning the Novel Coronavirus Disease (COVID-19),
issued by the President on March 13, 2020. For assistance, contact
FERC at [email protected] or call toll free, (886) 208-3676
or TTY (202) 502-8659.
---------------------------------------------------------------------------
NEPA Process and the Environmental Document
Any environmental document issued by the Commission will discuss
impacts that could occur as a result of the proposed project uprate
under the relevant general resource areas:
Environmental justice;
air quality; and
reliability and safety.
Commission staff will also evaluate reasonable alternatives to the
proposed project or portions of the project and make recommendations on
how to lessen or avoid impacts on the various resource areas. Your
comments will help Commission staff identify and focus on the issues
that might have an effect on the human environment and potentially
eliminate others from further study and discussion in the environmental
document.
Commission staff will determine whether to prepare an Environmental
Assessment (EA) or an Environmental Impact Statement (EIS), which will
present Commission staff's independent analysis of the issues. If
Commission staff prepares an EA, a Notice of Schedule for the
Preparation of an Environmental Assessment will be issued. The EA may
be issued for an allotted public comment period. The Commission would
consider timely comments on the EA before making its decision regarding
the proposed project. If Commission staff prepares an EIS, a Notice of
Intent to Prepare an EIS/Notice of Schedule will be issued, which will
open up an additional comment period. Staff will then prepare a draft
EIS which will be issued for public comment. Commission staff will
consider all timely comments received during the comment period on the
draft EIS and revise the document, as necessary, before issuing a final
EIS. Any EA or draft and final EIS will be available in electronic
format in the public record through eLibrary \2\ and the Commission's
natural gas environmental documents web page (https://www.ferc.gov/industries-data/natural-gas/environment/environmental-documents). If
eSubscribed, you will receive instant email notification when the
environmental document is issued.
---------------------------------------------------------------------------
\2\ For instructions on connecting to eLibrary, refer to the
last page of this notice.
---------------------------------------------------------------------------
With this notice, the Commission is asking agencies with
jurisdiction by law and/or special expertise with respect to the
environmental issues of this project to formally cooperate in the
preparation of the environmental document.\3\ Agencies that would like
to request cooperating agency status should follow the instructions for
filing comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Section 1501.8.
---------------------------------------------------------------------------
Consultation Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, the Commission is using this notice to initiate
consultation with the applicable State Historic Preservation Office(s),
and to solicit their views and those of other government agencies,
interested Indian tribes, and the public on the project's potential
effects on historic properties.\4\ The environmental document for this
project will document findings on the impacts on historic properties
and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project and includes a mailing address with their
comments. Commission staff will update the environmental mailing list
as the analysis proceeds to ensure that Commission notices related to
this environmental review are sent to all individuals, organizations,
and government entities interested in and/or potentially affected by
the proposed project.
If you need to make changes to your name/address, or if you would
like to remove your name from the mailing list, please complete one of
the following steps:
(1) Send an email to [email protected] stating your
request. You must include the docket number CP22-25-000 in your
request. If you are requesting a change to your address, please be sure
to include your name and the correct address. If you are requesting to
delete your address from the mailing list, please include your name and
address as it appeared on this notice. This email address is unable to
accept comments.
OR
(2) Return the attached ``Mailing List Update Form'' (appendix 2).
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC website at www.ferc.gov using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number
in the ``Docket Number'' field. Be sure you have selected an
appropriate date range. For assistance, please contact FERC Online
Support at [email protected] or (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of all formal documents issued by the Commission, such as orders,
notices, and rulemakings.
Public sessions or site visits will be posted on the Commission's
calendar located at https://www.ferc.gov/news-events/events along with
other related information.
Dated: March 24, 2022.
Debbie-Anne A. Reese,
Deputy Secretary.
[FR Doc. 2022-06697 Filed 3-29-22; 8:45 am]