NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-003, 50-247, 50-286, and 72-051; NRC-2021-0125]
Holtec Decommissioning International, LLC; Indian Point Nuclear
Generating, Unit Nos. 1, 2, and 3; Post-Shutdown Decommissioning
Activities Report
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of receipt; availability; public meeting; and request
for comment.
-----------------------------------------------------------------------
SUMMARY: On December 19, 2019, Holtec Decommissioning International,
LLC (HDI) submitted to the U.S. Nuclear Regulatory Commission (NRC) a
letter enclosing the post-shutdown decommissioning activities report
(PSDAR) for the Indian Point Nuclear Generating, Unit Nos. 1, 2, and 3
(Indian Point Energy Center (IPEC)), contingent upon the transfer of
the IPEC licenses to HDI. The PSDAR, which includes the site-specific
decommissioning cost estimate (DCE), provides an overview of HDI's
planned activities, schedule, projected costs, and environmental
impacts for the decommissioning of the IPEC. The IPEC license transfer
transaction closed on May 28, 2021. Accordingly, the NRC is noticing
receipt of the PSDAR and making it available for public comment. The
NRC will hold a public meeting in the vicinity of the IPEC to discuss
the PSDAR's content and receive comments. The date, time, and location
of the meeting will be provided in a future Federal Register notice.
DATES: Submit comments by October 22, 2021. Comments received after
this date will be considered, if it is practical to do so, but the NRC
is able to ensure consideration only for comments received on or before
this date.
ADDRESSES: You may submit comments by any of the following methods;
however, the NRC encourages electronic comment submission through the
Federal Rulemaking website:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0125. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann;
telephone: 301-415-0624; email: [email protected]. For technical
questions, contact the individual listed in the FOR FURTHER INFORMATION
CONTACT section of this document.
Mail comments to: Office of Administration, Mail Stop:
TWFN-7-A60M, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001, ATTN: Program Management, Announcements and Editing Staff.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Richard V. Guzman, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001, telephone: 301-415-1030; email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2021-0125 when contacting the NRC
about
[[Page 33384]]
the availability of information for this action. You may obtain
publicly available information related to this action by any of the
following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0125.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The IPEC PSDAR is available in ADAMS
under Accession No. ML19354A698.
Attention: The PDR, where you may examine and order copies
of public documents, is currently closed. You may submit your request
to the PDR via email at [email protected] or call 1-800-397-4209 or
301-415-4737, between 8:00 a.m. and 4:00 p.m. (EST), Monday through
Friday, except Federal holidays.
B. Submitting Comments
The NRC encourages electronic comment submission through the
Federal Rulemaking website (https://www.regulations.gov). Please
include Docket ID NRC-2021-0125 in your comment submission.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at
https://www.regulations.gov as well as entering the comment submissions
into ADAMS. The NRC does not routinely edit comment submissions to
remove identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Discussion
HDI has the authority to conduct licensed activities under
Provisional License No. DPR-5, Renewed Facility License No. DPR-26, and
Renewed Facility License No. DPR-64 for the IPEC and the general
license for the IPEC independent spent fuel storage installation. These
licenses provide, among other things, that the respective facilities
are subject to all rules, regulations, and orders of the NRC now or
hereafter in effect. The facilities consist of three pressurized-water
reactors located in Buchanan, New York, in Westchester County, all of
which are permanently shutdown.
On December 19, 2019, HDI submitted to the NRC the PSDAR for the
IPEC, contingent upon the transfer of the IPEC licenses to HDI (ADAMS
Accession No. ML19354A698). Paragraph 50.82(a)(4)(i) of title 10 of the
Code of Federal Regulations (10 CFR) states that a PSDAR must contain a
description of the planned decommissioning activities along with a
schedule for their accomplishment, a discussion that provides the
reasons for concluding that the environmental impacts associated with
site-specific decommissioning activities will be bounded by appropriate
previously issued environmental impact statements, and a site-specific
DCE, including the projected cost of managing irradiated fuel. The IPEC
license transfer transaction closed on May 28, 2021. Accordingly,
pursuant to 10 CFR 50.82(a)(4)(ii), the NRC is noticing receipt of the
PSDAR and making it available for public comment.
III. Request for Comment and Public Meeting
The NRC is requesting public comments on the PSDAR, including the
DCE, for the IPEC. The NRC will hold a public meeting in the vicinity
of the IPEC to discuss the PSDAR's content and receive comments. The
date, time, and location of the meeting will be provided in a future
Federal Register notice. The NRC requests that comments that are not
provided during the meeting be submitted as noted in section I,
``Obtaining Information and Submitting Comments,'' of this document in
writing by October 22, 2021.
Dated: June 15, 2021.
For the Nuclear Regulatory Commission.
James G. Danna,
Chief, Plant Licensing Branch I, Division of Operating Reactor
Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2021-13474 Filed 6-23-21; 8:45 am]