[Federal Register Volume 86, Number 96 (Thursday, May 20, 2021)]
[Notices]
[Pages 27485-27487]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2021-10596]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2021-0097]
Environmental Assessments and Findings of no Significant Impact
of Independent Spent Fuel Storage Facilities Decommissioning Funding
Plans
AGENCY: Nuclear Regulatory Commission.
ACTION: Environmental assessment and finding of no significant impact;
issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is publishing
this notice regarding the issuance of a final Environmental Assessment
(EA) and a Finding of No Significant Impact (FONSI) for its review and
approval of the initial decommissioning funding plans (DFPs) submitted
by independent spent fuel storage installation (ISFSI) licensees for
ISFSIs listed in the ``Discussion'' section of this document.
DATES: The EA and FONSI referenced in this document are available on
May 20, 2021.
ADDRESSES: Please refer to Docket ID NRC-2021-0097 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly available information related to this document
using any of the following methods:
Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2021-0097. Address
questions about Docket IDs in Regulations.gov to Stacy Schumann: 301-
415-0624; email: [email protected]. For technical questions,
contact the individual listed in the FOR FURTHER INFORMATION CONTACT
section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly available documents online in the
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS
Search.'' For problems with ADAMS, please contact the NRC's Public
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or
by email to [email protected]. The ADAMS accession number for each
document referenced (if it is available in ADAMS) is provided the first
time that it is mentioned in this document.
Attention: The PDR, where you may examine and order copies
of public documents, is currently closed. You may submit your request
to the PDR via email at [email protected] or call 1-800-397-4209 or
301-415-4737, between 8:00 a.m. and 4:00 p.m. (EST), Monday through
Friday, except Federal holidays.
FOR FURTHER INFORMATION CONTACT: Yen-Ju Chen, Office of Nuclear
Material Safety and Safeguards, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001; telephone: 301-415-1018, email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is considering the approval of the initial DFPs submitted
by ISFSI licensees. The NRC staff has prepared a final EA and FONSI
determination for each of the initial ISFSI DFPs in accordance with the
NRC regulations in part 51 of title 10 of the Code of Federal
Regulations (10 CFR), ``Environmental Protection Regulations for
Domestic Licensing and Related Regulatory Functions,'' which implement
the National Environmental Policy Act of 1969, as amended (42 U.S.C.
4321 et seq.).
The NRC requires its licensees to plan for the eventual
decommissioning of their licensed facilities prior to license
termination. On June 17, 2011, the NRC published a final rule in the
Federal Register amending its decommissioning planning regulations (76
FR 35512). The final rule amended the NRC regulation, 10 CFR 72.30,
which concerns financial assurance and decommissioning for ISFSIs. This
regulation requires each holder of, or applicant for, a license under
10 CFR part 72 to submit a DFP for the NRC's review and approval. The
DFP is to demonstrate the licensee's financial assurance, i.e., that
funds will be available to decommission the ISFSI. The NRC staff will
later publish its financial analyses of the DFP submittals which will
be available for public inspection in ADAMS.
II. Discussion
The table in this notice includes the plant name, docket number,
licensee, and ADAMS accession number for the
[[Page 27486]]
final EA and FONSI determination for each of the individual ISFSIs. The
table also includes the ADAMS accession numbers for other relevant
documents, including the initial and updated DFP submittals. For
further details with respect to these actions, see the NRC staff's
final EA and FONSI determinations which are available for public
inspection in ADAMS and at https://www.regulations.gov under Docket ID
NRC-2021-0097. For additional direction on accessing information
related to this document, see the ADDRESSES section of this document.
Finding of No Significant Impact
------------------------------------------------------------------------
------------------------------------------------------------------------
Facility........................ Joseph M. Farley Nuclear Plant, Units
1 and 2, ISFSI.
Docket No....................... 72-42.
Licensee........................ Southern Nuclear Operating Company,
Inc. (SNC).
Proposed Action................. The NRC's review and approval of SNC's
initial DFP submitted in accordance
with 10 CFR 72.30(b).
Environmental Impact of Proposed The NRC staff has determined that the
Action. proposed action, the review and
approval of SNC's initial DFP,
submitted in accordance with 10 CFR
72.30(b), will not authorize changes
to licensed operations or maintenance
activities, or result in changes in
the types, characteristics, or
quantities of radiological or non-
radiological effluents released into
the environment from the ISFSI, or
result in the creation of solid
waste. Moreover, the approval of the
initial DFP will not authorize any
construction activity, facility
modification, or other land-
disturbing activity. The NRC staff
has concluded that the proposed
action is a procedural and
administrative action that will not
have a significant impact on the
environment.
Finding of No Significant Impact The proposed action does not require
changes to the ISFSI's licensed
routine operations, maintenance
activities, or monitoring programs,
nor does it require new construction
or land-disturbing activities. The
scope of the proposed action concerns
only the NRC's review and approval of
SNC's initial DFP. The scope of the
proposed action does not include, and
will not result in, the review and
approval of decontamination or
decommissioning activities or license
termination for the ISFSI or for
other parts of Joseph M. Farley
Nuclear Plant, Units 1 and 2.
Therefore, the NRC staff determined
that approval of the initial DFP for
the Farley ISFSI will not
significantly affect the quality of
the human environment, and
accordingly, the staff has concluded
that a FONSI is appropriate. The NRC
staff further finds that preparation
of an environmental impact statement
(EIS) is not required.
Available Documents............. Alabama Emergency Management Agency.
Review of the Draft EA and FONSI for
the Farley Nuclear Plant Units 1 and
2 ISFSI DFP, dated March 18, 2021.
ADAMS Accession No. ML21081A039.
Southern Nuclear Operating Company,
Inc. ISFSI DFP, dated March 31, 2014.
ADAMS Accession No. ML14091A008.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning
Planning, dated February 1, 2009.
ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission.
Note to File, Re: ESA Section 7 No
Effect Determination for ISFSI DFP
Reviews, dated May 15, 2017. ADAMS
Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for
the Farley Nuclear Plant Units 1 and
2 ISFSI DFP, dated March 9, 2021.
ADAMS Accession No. ML21057A252.
U.S. Nuclear Regulatory Commission.
Final EA and FONSI for the Southern
Nuclear Operating Company, Inc's
Initial DFP Submitted in Accordance
with 10 CFR 72.30(b) for Joseph M.
Farley Nuclear Plant, Units 1 and 2,
ISFSI, dated May 10, 2021. ADAMS
Package Accession No. ML21085A675.
Facility........................ Edwin I. Hatch Nuclear Plant Unit Nos.
1 and 2, ISFSI.
Docket No....................... 72-36.
Licensee........................ Southern Nuclear Operating Company,
Inc. (SNC).
Proposed Action................. The NRC's review and approval of SNC's
initial DFP submitted in accordance
with 10 CFR 72.30(b).
Environmental Impact of Proposed The NRC staff has determined that the
Action. proposed action, the review and
approval of SNC's initial DFP,
submitted in accordance with 10 CFR
72.30(b), will not authorize changes
to licensed operations or maintenance
activities, or result in changes in
the types, characteristics, or
quantities of radiological or non-
radiological effluents released into
the environment from the ISFSI, or
result in the creation of solid
waste. Moreover, the approval of the
initial DFP will not authorize any
construction activity, facility
modification, or other land-
disturbing activity. The NRC staff
has concluded that the proposed
action is a procedural and
administrative action that will not
have a significant impact on the
environment.
Finding of No Significant Impact The proposed action does not require
changes to the ISFSI's licensed
routine operations, maintenance
activities, or monitoring programs,
nor does it require new construction
or land-disturbing activities. The
scope of the proposed action concerns
only the NRC's review and approval of
SNC's initial DFP. The scope of the
proposed action does not include, and
will not result in, the review and
approval of decontamination or
decommissioning activities or license
termination for the ISFSI or for
other parts of Edwin I. Hatch Nuclear
Plant, Unit Nos. 1 and 2. Therefore,
the NRC staff determined that
approval of the initial DFP for the
Hatch ISFSI will not significantly
affect the quality of the human
environment, and accordingly, the
staff has concluded that a FONSI is
appropriate. The NRC staff further
finds that preparation of an
environmental impact statement (EIS)
is not required.
Available Documents............. Southern Nuclear Operating Company,
Inc. ISFSI DFP, dated March 31, 2014.
ADAMS Accession No. ML14091A008.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning
Planning, dated February 1, 2009.
ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission.
Note to File, Re: ESA Section 7 No
Effect Determination for ISFSI DFP
Reviews, dated May 15, 2017. ADAMS
Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for
the Farley and Vogtle ISFSI DFP,
dated March 9, 2021. ADAMS Accession
No. ML21057A315.
U.S. Nuclear Regulatory Commission.
Final EA and FONSI for the Southern
Nuclear Operating Company, Inc.'s
Initial DFP Submitted in Accordance
with 10 CFR 72.30(b) for Hatch
Nuclear Plant Unit Nos. 1 and 2
ISFSI, dated May 10, 2021. ADAMS
Package Accession No. ML21085A829.
Facility........................ Vogtle Electric Generating Plant,
Units 1 and 2, ISFSI.
[[Page 27487]]
Docket No....................... 72-1039.
Licensee........................ Southern Nuclear Operating Company,
Inc. (SNC).
Proposed Action................. The NRC's review and approval of SNC's
initial DFP submitted in accordance
with 10 CFR 72.30(b).
Environmental Impact of Proposed The NRC staff has determined that the
Action. proposed action, the review and
approval of SNC's initial DFP,
submitted in accordance with 10 CFR
72.30(b), will not authorize changes
to licensed operations or maintenance
activities, or result in changes in
the types, characteristics, or
quantities of radiological or non-
radiological effluents released into
the environment from the ISFSI, or
result in the creation of solid
waste. Moreover, the approval of the
initial DFP will not authorize any
construction activity, facility
modification, or other land-
disturbing activity. The NRC staff
has concluded that the proposed
action is a procedural and
administrative action that will not
have a significant impact on the
environment.
Finding of No Significant Impact The proposed action does not require
changes to the ISFSI's licensed
routine operations, maintenance
activities, or monitoring programs,
nor does it require new construction
or land-disturbing activities. The
scope of the proposed action concerns
only the NRC's review and approval of
SNC's initial DFP. The scope of the
proposed action does not include, and
will not result in, the review and
approval of decontamination or
decommissioning activities or license
termination for the ISFSI or for
other parts of Vogtle Electric
Generating Plant, Units 1 and 2.
Therefore, the NRC staff determined
that approval of the initial DFP for
the Vogtle ISFSI will not
significantly affect the quality of
the human environment, and
accordingly, the staff has concluded
that a FONSI is appropriate. The NRC
staff further finds that preparation
of an environmental impact statement
(EIS) is not required.
Available Documents............. Southern Nuclear Operating Company,
Inc. ISFSI DFP, dated March 31, 2014.
ADAMS Accession No. ML14091A008.
U.S. Nuclear Regulatory Commission. EA
for Final Rule-Decommissioning
Planning, dated February 1, 2009.
ADAMS Accession No. ML090500648.
U.S. Nuclear Regulatory Commission.
Note to File, Re: ESA Section 7 No
Effect Determination for ISFSI DFP
Reviews, dated May 15, 2017. ADAMS
Accession No. ML17135A062.
U.S. Nuclear Regulatory Commission.
Review of the Draft EA and FONSI for
the Farley and Vogtle ISFSI DFP,
dated March 9, 2021. ADAMS Accession
No. ML21057A315.
U.S. Nuclear Regulatory Commission.
Final EA and FONSI for the Southern
Nuclear Operating Company, Inc.'s
Initial DFP Submitted in Accordance
with 10 CFR 72.30(b) for Vogtle
Electric Generating, Plant Units 1
and 2, ISFSI, dated May 10, 2021.
ADAMS Package Accession No.
ML21089A221.
------------------------------------------------------------------------
Dated: May 14, 2021.
For the Nuclear Regulatory Commission.
John B. McKirgan,
Chief, Storage and Transportation Licensing Branch, Division of Fuel
Management, Office of Nuclear Material Safety.
[FR Doc. 2021-10596 Filed 5-19-21; 8:45 am]
BILLING CODE 7590-01-P