DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP20-477-000]


Spire Storage West, LLC; Notice of Request Under Blanket 
Authorization

    Take notice that on June 4, 2020, Spire Storage West, LLC (Spire 
Storage), 3773 Richmond Avenue, Suite 300, Houston, TX 77046, filed in 
the above referenced docket, a prior notice request pursuant to 
Sec. Sec.  157.205 and 157.213(b) of the Commission's regulations under 
the Natural Gas Act (NGA) and Spire Storage's blanket certificate 
issued in Docket No. CP11-24-000, for authorization to install one 
compressor unit and related equipment; relocate one natural gas liquids 
tank, two condensate tanks, and NGL and condensate truck load-out 
facilities and to replace two existing fuel supply tanks. The project, 
referred to as the Compression at Clear Creek Project, is located 
adjacent to Spire Storage's existing central gas handling facility at 
its Clear Creek Storage Field in Uinta County, Wyoming. Details of 
Spire Storage's Compression at Clear Creek Project is more fully set 
forth in the application which is on file with the Commission and open 
to public inspection. In addition to publishing the full text of this 
document in the Federal Register, the Commission provides all 
interested persons an opportunity to view and/or print the contents of 
this document via the internet through the Commission's Home Page 
(http://ferc.gov) using the ``eLibrary'' link. Enter the docket number 
excluding the last three digits in the docket number field to access 
the document. At this time, the Commission has suspended access to the 
Commission's Public Reference Room, due to the proclamation declaring a 
National Emergency concerning the Novel Coronavirus Disease (COVID-19), 
issued by the President on March 13, 2020. For assistance, contact FERC 
at [email protected] or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions regarding this prior notice request should be 
directed to Sean P. Jamieson, General Counsel, Spire Storage West LLC, 
3773 Richmond Avenue, Suite 300, Houston, TX 77046, phone: (346) 308-
7555 or email: [email protected] or Damien R. Lyster, Vinson 
& Elkins LLP, 1001 Fannin Street, Suite 2500, Houston, TX 77002, phone: 
713-758-2025 or email: [email protected].
    Any person or the Commission's staff may, within 60 days after the 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention. Any person filing to intervene, or 
the Commission's staff may, pursuant to Sec.  157.205 of the 
Commission's Regulations under the NGA (18 CFR 157.205) file a protest 
to the request. If no protest is filed within the time allowed 
therefore, the proposed activity shall be deemed to be authorized 
effective the day after the time allowed for protest. If a protest is 
filed and not withdrawn within 30 days after the time allowed for 
filing a protest, the instant request shall be treated as an 
application for authorization pursuant to section 7 of the NGA.

[[Page 35650]]

    Pursuant to Sec.  157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list and will be 
notified of any meetings associated with the Commission's environmental 
review process. Environmental commenters will not be required to serve 
copies of filed documents on all other parties. However, the non-party 
commenters will not receive copies of all documents filed by other 
parties or issued by the Commission and will not have the right to seek 
court review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the internet in lieu of paper. See 18 
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's 
website (http://www.ferc.gov) under the ``e-Filing'' link.

    Dated: June 5, 2020.
Kimberly D. Bose,
Secretary.
[FR Doc. 2020-12640 Filed 6-10-20; 8:45 am]