[Federal Register Volume 85, Number 109 (Friday, June 5, 2020)]
[Notices]
[Page 34714]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2020-12115]
-----------------------------------------------------------------------
DEPARTMENT OF TRANSPORTATION
Federal Highway Administration
Rescinding the Notice of Intent To Prepare Environmental Impact
Statement: South Kohala, Hawaii
AGENCY: Federal Highway Administration (FHWA), DOT.
ACTION: Notice to rescind notice of intent (NOI) to prepare an
environmental impact statement (EIS).
-----------------------------------------------------------------------
SUMMARY: The FHWA is issuing this notice to advise the public that the
FHWA is rescinding its NOI and will not be preparing an EIS to evaluate
alternatives to realign and/or widen an existing highway in South
Kohala in the County of Hawaii. An NOI to prepare an EIS was published
in the Federal Register on November 29, 2002.
FOR FURTHER INFORMATION CONTACT: Ralph Rizzo, Division Administrator,
Federal Highway Administration, 300 Ala Moana Boulevard, Box 50206,
Honolulu, Hawaii 96850, Telephone: (808) 541-2700.
SUPPLEMENTARY INFORMATION: The FHWA, in cooperation with the State of
Hawaii Department of Transportation (HDOT), initiated an EIS with an
NOI published in the Federal Register on November 29, 2002, at 67 FR
71231, to prepare an EIS.
The study area begins near the intersection of Mud Lane and the
Hawaii Belt Road (State Route 19) and terminates along Mamalahoa
Highway (State Route 190) near the Waimea-Kohala Airport. The study
also included a 1.7 mile spur to connect with Lindsey Road.
Improvements were considered necessary to improve highway safety and
reduce congestion, while preserving the character and ambience of the
historic Waimea village. The Project would impact a sizable number of
historic and archaeological resources due to the sheer number of
archaeological sites identified during the survey. Avoidance of all
these sites would be difficult and may not be feasible. Also, the
County recently completed intersection improvements on the existing
highway that improved congestion. Finally, the cost for the estimated
right-of-way and construction would likely be substantial because of
limited funding availability. Therefore, HDOT has decided not to
proceed with the project and the preparation of the EIS is being
terminated.
(Catalog of Federal Domestic Assistance Program Number 20.205,
Highway Planning and Construction. The regulations implementing
Executive Order 12372 regarding intergovernmental consultation on
Federal programs and activities apply to this program.)
(Authority: 23 U.S.C. 139, 23 CFR 771, and 40 CFR 1500-1508)
Issued on: May 29, 2020.
Ralph Rizzo,
Division Administrator, Honolulu, HI.
[FR Doc. 2020-12115 Filed 6-4-20; 8:45 am]
BILLING CODE 4910-RY-P