[Federal Register Volume 84, Number 249 (Monday, December 30, 2019)]
[Notices]
[Pages 71918-71919]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-28126]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP20-8-000]
ANR Pipeline Company; Notice of Schedule for Environmental Review
of the Grand Chenier Xpress Project
On October 28, 2019, ANR Pipeline Company (ANR), filed an
application in Docket No. CP20-8-000 requesting a Certificate of Public
Convenience and Necessity pursuant to sections 7(b) and 7(c) of the
Natural Gas Act to abandon, construct, and operate certain natural gas
pipeline facilities. The proposed project is known as the Grand Chenier
XPress Project (Project), and includes facilities in Acadia, Jefferson
Davies, and Cameron Parishes, Louisiana. The Project would provide open
access firm transportation service of 400 million cubic feet per day of
incremental capacity from ANR's Southeast Head station \1\ to the
Mermentau River GCX Meter Station.
---------------------------------------------------------------------------
\1\ ANR's Head Station is a pooling point where natural gas is
aggregated from many receipt points.
---------------------------------------------------------------------------
On November 6, 2019, the Federal Energy Regulatory Commission
(Commission or FERC) issued its Notice of Application for the Project.
Among other things, that notice alerted agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on a request for a federal authorization
within 90 days of the date of issuance of the Commission staff's
Environmental Assessment (EA) for the Project. This instant notice
identifies the FERC staff's planned schedule for the completion of the
EA for the Project.
Schedule for Environmental Review
Issuance of EA: March 27, 2020.
90-day Federal Authorization Decision Deadline: June 25, 2020.
If a schedule change becomes necessary, additional notice will be
provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
The Grand Chenier XPress Project would consist of the following
facilities:
Modifications of ANR's existing Eunice Compressor Station
in Acadia Parish, Louisiana, to increase the total certificated
horsepower (hp) from 24,000 hp to 39,370 hp, and abandonment of an
existing reciprocating compressor in place;
construction of a new 23,470 hp greenfield compressor
station (Mermentau Compressor Station) in Jefferson Davis Parish,
Louisiana;
modifications of the existing Dresser-Rand compressor unit
and installation of 42 feet of above ground piping at the Grand Chenier
Compressor Station in Cameron Parish, Louisiana; and
modifications of the Mermentau River GCX Meter Station
under ANR's blanket certificate (CP82-480-000), including the
installation of an additional meter run and related appurtenant
facilities in order to increase the delivery capability from 700
million cubic feet per day to 1.1 billion cubic feet per day.
Background
On December 5, 2019, the Commission issued a Notice of Intent to
Prepare an Environmental Assessment for the Proposed Grand Chenier
XPress Project and Request for Comments on Environmental Issues (NOI).
The NOI was sent to affected landowners; federal, state, and local
government agencies; elected officials; environmental and public
interest groups; Native American tribes; other interested parties; and
local libraries and newspapers. All substantive comments will be
addressed in the EA.
Additional Information
In order to receive notification of the issuance of the EA and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription. This can
reduce the amount of time you spend researching proceedings by
automatically providing you with notification of these filings,
document summaries, and direct links to the documents. Go to
www.ferc.gov/docs-filing/esubscription.asp.
Additional information about the Project is available from the
Commission's Office of External Affairs at (866) 208-FERC or on the
FERC website (www.ferc.gov). Using the eLibrary link, select General
Search from the eLibrary menu, enter the selected date range and Docket
Number excluding the last three digits (i.e., CP20-8), and follow the
instructions. For assistance with access to eLibrary, the helpline can
be reached at (866) 208-3676, TTY (202) 502-8659, or at
[email protected]. The eLibrary link on the FERC website also
provides access to the texts of formal documents issued by the
Commission, such as orders, notices, and rule makings.
[[Page 71919]]
Dated: December 20, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-28126 Filed 12-27-19; 8:45 am]
BILLING CODE 6717-01-P