Lock+TM Hydro Friends Fund XX, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On March 1, 2019, Lock\+TM\ Hydro Friends Fund XX, LLC, filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the Blue 
Marsh Dam Hydropower Project to be located at the U.S. Army Corps of 
Engineers' (Corps) Blue Marsh Dam on the Tulpehocken Creek in Berks 
County, Pennsylvania. The sole purpose of a preliminary permit, if 
issued, is to grant the permit holder priority to file a license 
application during the permit term. A preliminary permit does not 
authorize the permit holder to perform any land-disturbing activities 
or otherwise enter upon lands or waters owned by others without the 
owners' express permission.
    The proposed project would consist of the following: (1) A new 30-
foot-long, 30-foot-wide, 160-foot-high Large Frame Module; (2) two 
turbine-generator units with a total rated capacity of 1.75 megawatts; 
(3) a new 4-foot-long, 4-foot-wide, 3-foot-high pad-mounted 
transformer; (4) a new 200-foot-long, 13-kilovolt transmission line 
connecting the new transformer to an existing distribution line; and 
(5) appurtenant facilities. The proposed project would have an annual 
generation of 7,750 megawatt-hours.
    Applicant Contact: Wayne Krouse, Lock+TM Hydro Friends 
Fund XX, LLC, P.O. Box 43796, Birmingham, AL 35243; phone: 877-556-6566 
ext. 709.
    FERC Contact: Woohee Choi; phone: (202) 502-6336.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please

[[Page 45147]]

send a paper copy to: Secretary, Federal Energy Regulatory Commission, 
888 First Street NE, Washington, DC 20426. The first page of any filing 
should include docket number P-14973-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the eLibrary link of the 
Commission's website at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14973) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

     Dated: August 22, 2019.
Kimberly D. Bose,
Secretary.
[FR Doc. 2019-18541 Filed 8-27-19; 8:45 am]