[Federal Register Volume 84, Number 167 (Wednesday, August 28, 2019)]
[Notices]
[Pages 45178-45182]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-18490]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-293; NRC-2019-0152]


Entergy Nuclear Operations, Inc.; Pilgrim Nuclear Power Station

AGENCY: Nuclear Regulatory Commission.

ACTION: Exemption; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an 
exemption in response to a November 16, 2018, request from Entergy 
Nuclear Operations, Inc. (ENOI), on behalf of Entergy Nuclear 
Generation Company (to be renamed Holtec Pilgrim, LLC) and Holtec 
Decommissioning International, LLC (HDI). The exemption permits Holtec 
Pilgrim, LLC and HDI to use funds from the Pilgrim decommissioning 
trust fund for management of spent fuel and site restoration 
activities. By Order dated

[[Page 45179]]

August 22, 2019, the NRC approved the request for the direct transfer 
of ENOI's operating authority to HDI and the indirect transfer of 
control of the Renewed Facility Operating License No. DPR-35 for 
Pilgrim, as well as the general license for the Pilgrim Independent 
Spent Fuel Storage Installation, to Holtec International. This 
exemption is being issued simultaneously with the license transfer 
Order and will be effective upon the NRC's issuance of a conforming 
license amendment reflecting Holtec Pilgrim, LLC and HDI as the 
licensees for Pilgrim, following consummation of the license transfer 
transaction.

DATES: The exemption was issued on August 22, 2019.

ADDRESSES: Please refer to Docket ID NRC-2019-0152 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov and search for Docket ID NRC-2019-0152. Address 
questions about NRC docket IDs in Regulations.gov to Jennifer Borges; 
telephone: 301-287-9127; email: [email protected]. For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced (if it is available in ADAMS) is provided the first 
time that it is mentioned in this document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Scott P. Wall, Office of Nuclear 
Reactor Regulation; U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-2855; email: [email protected].

SUPPLEMENTARY INFORMATION: The text of the exemption is attached.

    Dated at Rockville, Maryland, this 22nd day of August, 2019.

    For the Nuclear Regulatory Commission.
Scott P. Wall,
Senior Project Manager, Plant Licensing Branch III, Division of 
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.

Attachment--Exemption

NUCLEAR REGULATORY COMMISSION

Docket No. 50-293

Holtec Decommissioning International, LLC

Pilgrim Nuclear Power Station

Exemption

I. Background

    By letter dated November 10, 2015 (Agencywide Documents Access 
and Management System (ADAMS) Accession No. ML15328A053), Entergy 
Nuclear Operations, Inc. (ENOI), submitted a notification to the 
U.S. Nuclear Regulatory Commission (NRC) indicating that it would 
permanently shut down Pilgrim Nuclear Power Station (Pilgrim) no 
later than June 1, 2019. By letter dated June 10, 2019 (ADAMS 
Accession No. ML19161A033), ENOI submitted to the NRC a 
certification in accordance with Sec.  50.82(a)(1) of Title 10 of 
the Code of Federal Regulations (10 CFR), stating that Pilgrim 
permanently ceased power operations on May 31, 2019, and that as of 
June 9, 2019, all fuel had been permanently removed from the Pilgrim 
reactor vessel and placed in the spent fuel pool. Accordingly, 
pursuant to 10 CFR 50.82(a)(2), the Pilgrim renewed facility 
operating license no longer authorizes operation of the reactor or 
emplacement or retention of fuel in the reactor vessel. By letter 
dated November 16, 2018 (ADAMS Accession No. ML18320A036), ENOI 
submitted the updated Pilgrim spent fuel management plan (SFMP) 
pursuant to 10 CFR 50.54(bb) and preliminary decommissioning cost 
estimate (DCE). By letter dated November 16, 2018 (ADAMS Accession 
No. ML18320A034), as supplemented by letter dated January 9, 2019 
(ADAMS Accession No. ML19015A020) and letter dated July 29, 2019 
(ADAMS Accession No. ML19210E470), ENOI submitted a post-shutdown 
decommissioning activities report (PSDAR) and the site-specific DCE 
for Pilgrim.
    By letter dated November 16, 2018 (ADAMS Accession No. 
ML18320A031), ENOI, on behalf of itself and Entergy Nuclear 
Generation Company (ENGC) (to be known as Holtec Pilgrim, LLC 
(Holtec Pilgrim)), Holtec International (Holtec), and Holtec 
Decommissioning International (HDI) submitted a license transfer 
application (LTA) requesting that the NRC consent to the direct 
transfer of ENOI's operating authority to HDI and the indirect 
transfer of control of the Pilgrim Renewed Facility Operating 
License and the General License for the Pilgrim Independent Spent 
Fuel Storage Installation (ISFSI) to Holtec. By letter dated 
November 16, 2018 (ADAMS Accession No. ML18320A040), HDI submitted a 
``Notification of Revised Post-Shutdown Decommissioning Activities 
Report and Revised Site-Specific Decommissioning Cost Estimate for 
Pilgrim Nuclear Power Station'' (revised PSDAR), to notify the NRC 
of changes to accelerate the schedule for the prompt decommissioning 
(i.e., the DECON method for decommissioning) of Pilgrim and 
unrestricted release of all portions of the site (excluding the 
ISFSI) within 8 years after the license transfer.
    Under the proposed transfers, Holtec Pilgrim will own the 
Pilgrim nuclear facility and will have responsibility for Pilgrim as 
its licensed owner. Holtec Pilgrim will enter into an agreement for 
decommissioning services with HDI, with HDI acting as Holtec 
Pilgrim's agent and with Holtec Pilgrim paying for all HDI expenses 
related to decommissioning, spent fuel management, and site 
restoration. Accordingly, HDI will become the licensed operator for 
decommissioning.

II. Request/Action

    The requested exemption from 10 CFR 50.82(a)(8)(i)(A) would 
permit Holtec Pilgrim and HDI to use funds from the Pilgrim 
Decommissioning Trust Fund (DTF) for spent fuel management and site 
restoration activities in accordance with HDI's site-specific DCE 
for Pilgrim. HDI submitted a revised site-specific DCE for Pilgrim 
by letter dated November 16, 2018, as part of the revised PSDAR. A 
similar exemption request from Entergy was approved by the NRC for 
Pilgrim by letter dated July 22, 2019 (ADAMS Accession No. 
ML19162A334).
    The 10 CFR 50.82(a)(8)(i)(A) requirement restricts the use of 
DTF withdrawals to expenses for legitimate decommissioning 
activities consistent with the definition of decommissioning that 
appears in 10 CFR 50.2. The definition of ``decommission'' in 10 CFR 
50.2 reads as follows:

To remove a facility or site safely from service and reduce residual 
radioactivity to a level that permits--
    (1) Release of the property for unrestricted use and termination 
of the license; or
    (2) Release of the property under restricted conditions and 
termination of the license.

This definition does not include activities associated with spent 
fuel management or site restoration activities. Therefore, an 
exemption from 10 CFR 50.82(a)(8)(i)(A) is needed to allow Holtec 
Pilgrim and HDI to use funds from the DTF for spent fuel management 
and site restoration activities.
    Similar to 10 CFR 50.82(a)(8)(i)(A), provisions of 10 CFR 
50.75(h)(1)(iv) and (h)(2) dictate that with certain exceptions, 
disbursements from nuclear decommissioning trusts ``are restricted 
to decommissioning expenses.'' However, in accordance with 10 CFR 
50.75(h)(5), these provisions do not apply to ``any licensee that as 
of December 24, 2003, has existing license conditions relating to 
decommissioning trust agreements, so long as the licensee does not 
elect to amend those license conditions.'' The operating license for 
Pilgrim included ``existing license conditions relating to 
decommissioning trust agreements'' on December 24, 2003, and as 
such, Pilgrim is exempt from the provisions of sections (h)(1) 
through (h)(3) of 10 CFR 50.75, pursuant to the terms of 10 CFR 
50.75(h)(5).

[[Page 45180]]

III. Discussion

    Pursuant to 10 CFR 50.12, the Commission may, upon application 
by any interested person or upon its own initiative, grant 
exemptions from the requirements of 10 CFR part 50(1) when the 
exemptions are authorized by law, will not present an undue risk to 
the public health and safety, and are consistent with the common 
defense and security; and (2) when any of the special circumstances 
listed in 10 CFR 50.12(a)(2) are present. These special 
circumstances include, among other things:
    (a) Application of the regulation in the particular 
circumstances would not serve the underlying purpose of the rule or 
is not necessary to achieve the underlying purpose of the rule; and
    (b) Compliance would result in undue hardship or other costs 
that are significantly in excess of those contemplated when the 
regulation was adopted, or that are significantly in excess of those 
incurred by others similarly situated.

A. Authorized by Law

    The requested exemption from 10 CFR 50.82(a)(8)(i)(A) would 
allow Holtec Pilgrim and HDI to use a portion of the funds from the 
DTF for spent fuel management and site restoration activities at 
Pilgrim in the same manner that withdrawals are made under 10 CFR 
50.82(a)(8) for radiological decommissioning activities. As stated 
above, 10 CFR 50.12 allows the NRC to grant exemptions from the 
requirements of 10 CFR part 50 when the exemptions are authorized by 
law. The NRC staff has determined, as explained further below, that 
there is reasonable assurance of adequate funding for radiological 
decommissioning because the Applicants' use of the DTF for 
activities associated with spent fuel management and site 
restoration will not negatively impact the availability of funding 
for radiological decommissioning. Accordingly, the exemption is 
authorized by law because granting the licensee's proposed exemption 
will not result in a violation of the Atomic Energy Act of 1954, as 
amended, or the Commission's regulations.

B. No Undue Risk to Public Health and Safety

    The underlying purpose of 10 CFR 50.82(a)(8)(i)(A) is to provide 
reasonable assurance that adequate funds will be available for the 
radiological decommissioning of power reactors and license 
termination. As explained in further detail in Section D below, 
based on NRC staff's review of HDI's revised site-specific DCE and 
the staff's independent cash flow analysis contained in Attachment 1 
to the NRC staff's safety evaluation for the associated LTA (ADAMS 
Accession No. ML19170A250), the NRC staff finds that the use of the 
Pilgrim DTF for spent fuel management and site restoration 
activities at Pilgrim will not adversely impact Holtec Pilgrim and 
HDI's ability to terminate the Pilgrim license (i.e., complete 
radiological decommissioning) as planned, consistent with the 
schedule and costs contained in the revised PSDAR.
    Furthermore, withdrawals from the DTF for spent fuel management 
and site restoration are still constrained by the provisions of 10 
CFR 50.82(a)(8)(i)(B)-(C) and are reviewable under the annual 
reporting requirements of 10 CFR 50.82(a)(8)(v)-(vii).
    There are no new accident precursors created by using the DTF in 
the proposed manner. Thus, the probability of postulated accidents 
is not increased. Also, based on the above, the consequences of 
postulated accidents are not increased. No changes are being made in 
the types or amounts of effluents that may be released offsite. 
There is no significant increase in occupational or public radiation 
exposure. Therefore, the requested exemption will not present an 
undue risk to the public health and safety.

C. Consistent With the Common Defense and Security

    The requested exemption would allow Holtec Pilgrim and HDI to 
use funds from the Pilgrim DTF for spent fuel management and site 
restoration activities at Pilgrim. Spent fuel management under 10 
CFR 50.54(bb) is an integral part of the planned decommissioning and 
license termination process and will not adversely affect Holtec 
Pilgrim and HDI's ability to physically secure the site or protect 
special nuclear material. This change to enable the use of a portion 
of the funds from the DTF for spent fuel management and site 
restoration activities has no relation to security issues. 
Therefore, the common defense and security is not impacted by the 
requested exemption.

D. Special Circumstances

    Special circumstances, in accordance with 10 CFR 
50.12(a)(2)(ii), are present whenever application of the regulation 
in the particular circumstances is not necessary to achieve the 
underlying purpose of the regulation.
    The underlying purpose of 10 CFR 50.82(a)(8)(i)(A), which 
restricts withdrawals from DTFs to expenses for radiological 
decommissioning activities, is to provide reasonable assurance that 
adequate funds will be available for radiological decommissioning of 
power reactors and license termination. Strict application of this 
requirement would prohibit the withdrawal of funds from the Pilgrim 
DTF for spent fuel management and site restoration activities, until 
final radiological decommissioning at Pilgrim has been completed.
    ENOI's March 28, 2019, annual report (ADAMS Accession No. 
ML19087A318) on the status of decommissioning funding for Pilgrim 
reports a DTF balance of approximately $1.028 billion as of December 
31, 2018, and approximately $1.043 billion as of February 28, 2019. 
The cash flow analysis in Table 1 of the November 16, 2018, 
application is based on a beginning DTF balance of $1.030 billion 
(following closure of the equity sale in 2019).\1\ HDI states that 
this beginning DTF balance reflects the fund value post-closure of 
the asset sale. Furthermore, the application states that the 2019 
costs include estimated pre-closure and post-closure costs. In the 
NRC staff's analysis provided in its safety evaluation for the LTA, 
the staff used the opening DTF balance of $1.030 billion as the 
money available to cover radiological decommissioning, spent fuel 
management, and site restoration costs.
---------------------------------------------------------------------------

    \1\ The terms of the Equity Purchase and Sales Agreement 
describes the after-tax market value of the DTF must be no less than 
$1.030 billion at time of transaction closing.
---------------------------------------------------------------------------

    The analysis in the November 16, 2018 revised PSDAR, projects 
the total radiological decommissioning cost of Pilgrim to be 
approximately $593 million in 2018 dollars which is lower than the 
10 CFR 50.75(c) minimum formula amount of approximately $633 
million. The revised PSDAR estimated decommissioning costs are 
consistent with the estimated costs for radiological 
decommissioning, including ISFSI decommissioning costs, provided in 
the November 16, 2018 request for exemptions. However, the LTA and 
the exemption request did not provide any explanation for the 
difference in funding levels for radiological decommissioning costs 
between the site-specific DCE and the 10 CFR 50.75(c) minimum 
formula amount. Therefore, the staff sought supplemental information 
from the Applicants in a request for additional information (RAI) 
dated July 26, 2019, (ADAMS Accession No. ML19207B366). The RAI 
requested, among other things, that the Applicants provide 
justification for using a radiological decommissioning cost estimate 
value that is less than the 10 CFR 50.75(c) minimum formula amount.
    On July 29, 2019 (ADAMS Accession No. ML19210E470), HDI provided 
its justification, stating that the HDI site-specific DCE is a more 
reliable and precise estimate of decommissioning cost because it is 
based on Pilgrim-specific plant data and historical information, 
actual site conditions, regulatory requirements applicable to 
Pilgrim, and actual pricing information, as compared to the 10 CFR 
50.75(c) minimum formula amount, which is based on generic inputs. 
Additionally, in both the November 16, 2018 application and the July 
29, 2019 supplement, HDI states that its site-specific DCE was 
reviewed against the estimates of costs associated with license 
termination (radiological decommissioning) in NUREG/CR-6174, 
``Revised Analyses of Decommissioning for the Reference Boiling 
Water Reactor Power Station'' (ADAMS Accession No. ML14008A186), 
benchmarked against nine comparable decommissioning projects, and 
compared with costs from similar activities at seven boiling water 
reactors. Accordingly, as part of its review, the NRC staff compared 
the Pilgrim site-specific radiological decommissioning costs with 
the estimated activities of the four periods associated with the 
DECON decommissioning method as outlined in NUREG/CR-6174:
    (1) Pre-shutdown planning/engineering and regulatory reviews,
    (2) Plant deactivation and preparation for storage,
    (3) A period of plant safe storage with concurrent operations in 
the spent fuel pool until the pool inventory is zero, and
    (4) Decontamination and dismantlement of the radioactive 
portions of the plant, leading to license termination.
    The NRC staff also compared the Pilgrim site-specific estimated 
radiological decommissioning costs of approximately $593 million 
with the site-specific costs of similar decommissioning projects.

[[Page 45181]]

    Based on the review of the Pilgrim site-specific radiological 
decommissioning costs of approximately $593 million, as compared to 
NUREG/CR-6174, the staff concludes that HDI's method for developing 
the Pilgrim site-specific radiological decommissioning cost estimate 
is reasonable. Further, when compared to radiological 
decommissioning costs associated with similar decommissioning 
projects, the staff finds that the HDI's Pilgrim site-specific 
radiological decommissioning costs of approximately $593 million is 
reasonable.
    As such, the staff used the value of approximately $593 million 
for radiological decommissioning costs when it conducted its 
independent cash flow analysis. As allowed by 10 CFR 
50.75(e)(1)(ii), the staff began its cost analysis using a 2% real 
rate of return on annual balances. In its application dated November 
16, 2018, HDI states they also used a 2% real rate of return. 
However, in Table 1 of the November 16, 2018, application, HDI noted 
that the Year Ending DTF Balance is after-taxes. Therefore, in its 
cost analysis, the staff found that Table 1 reflects an actual 
annual real rate of return of 1.42%. The staff notes that this is 
conservative to the 2% annual real rate of return allowed by 10 CFR 
50.75(e)(1)(ii). To be consistent in validating HDI's site-specific 
DCE, the staff used the more conservative 1.42% annual real rate of 
return. The staff's independent cash flow analysis is contained in 
Attachment 1 to the NRC staff's safety evaluation for the associated 
LTA.
    As noted above, HDI's site-specific DCE relies on estimated 
radiological decommissioning costs of approximately $593 million, 
which is lower than the 10 CFR 50.75(c) minimum formula amount of 
approximately $633 million. In its RAI dated July 26, 2019, the 
staff requested a justification for this lower amount and, in case 
the Applicants' failed to provide sufficient justification, the 
staff also requested that the Applicants provide a revised 
decommissioning cash flow analysis using the higher minimum formula 
amount of $633,267,558. In Attachment 1 of the July 29, 2019, 
supplement, HDI provided the requested revised cash flow analysis. 
Although the staff completed a separate, independent cash flow 
analysis to validate this revised cash flow analysis, ultimately, as 
noted above, the staff determined that HDI's site-specific DCE, 
which uses $592,553,000 for the estimated site-specific radiological 
decommissioning costs for Pilgrim, is reasonable and sufficiently 
justified.
    Based on its evaluation above and the cash flow analysis 
contained in Attachment 1 to the NRC staff's safety evaluation for 
the associated LTA, the staff finds that the funds in the DTF are 
expected to be available and sufficient to cover the estimated costs 
of approximately $593 million for the radiological decommissioning 
of the facility (including the ISFSI). Therefore, the NRC staff 
finds that HDI has provided reasonable assurance that adequate funds 
will be available for the radiological decommissioning of Pilgrim, 
even with the disbursement of funds from the DTF for spent fuel 
management and site restoration activities. Consequently, the NRC 
staff concludes that application of the 10 CFR 50.82(a)(8)(i)(A) 
requirement that funds from the DTF only be used for radiological 
decommissioning activities and not for spent fuel management and 
site restoration activities is not necessary to achieve the 
underlying purpose of the rule; thus, special circumstances are 
present supporting approval of the exemption request.
    By granting the exemption to 10 CFR 50.82(a)(8)(i)(A), 
withdrawals from the DTF for spent fuel management and site 
restoration activities, consistent with the licensee's submittal 
dated November 16, 2018, are authorized. As stated previously, the 
NRC staff has determined that there are sufficient funds in the DTF 
to complete radiological decommissioning activities as well as to 
conduct spent fuel management and site restoration activities 
consistent with the revised PSDAR, DCE, SFMP, and the November 16, 
2018, exemption request. Pursuant to the requirements in 10 CFR 
50.82(a)(8)(v) and (vii), licensees are required to monitor and 
annually report to the NRC the status of the DTF and the licensee's 
funding for managing spent fuel. These reports provide the NRC staff 
with awareness of, and the ability to take action on, any actual or 
potential funding deficiencies. Additionally, 10 CFR 50.82(a)(8)(vi) 
requires that the annual financial assurance status report must 
include additional financial assurance to cover the estimated cost 
of completion if the sum of the balance of any remaining 
decommissioning funds, plus earnings on such funds calculated at not 
greater than a 2% real rate of return, together with the amount 
provided by other financial assurance methods being relied upon, 
does not cover the estimated cost to complete the decommissioning. 
The requested exemption would not allow the withdrawal of funds from 
the DTF for any other purpose that is not currently authorized in 
the regulations without prior approval from the NRC.
    Special circumstances, in accordance with 10 CFR 
50.12(a)(2)(iii), are present whenever compliance would result in 
undue hardship or other costs that are significantly in excess of 
those contemplated when the regulation was adopted, or that are 
significantly in excess of those incurred by others similarly 
situated. HDI states that the DTF contains funds in excess of the 
estimated costs of radiological decommissioning and that these 
excess funds are needed for spent fuel management and site 
restoration activities. The NRC does not preclude the use of funds 
from the decommissioning trust in excess of those needed for 
radiological decommissioning for other purposes, such as spent fuel 
management or site restoration activities (see NRC Regulatory Issue 
Summary 2001-07, Rev. 1, ``10 CFR 50.75 Reporting and Recordkeeping 
for Decommissioning Planning,'' dated January 8, 2009 (ADAMS 
Accession No. ML083440158), and Regulatory Guide 1.184, Revision 1, 
``Decommissioning of Nuclear Power Reactors,'' dated October 2013 
(ADAMS Accession No. ML13144A840)). Preventing access to those 
excess funds in the DTF because spent fuel management and site 
restoration activities are not associated with radiological 
decommissioning would create an unnecessary financial burden without 
any corresponding safety benefit. The adequacy of the DTF to cover 
the cost of activities associated with spent fuel management and 
site restoration, in addition to radiological decommissioning, is 
supported by the site-specific DCE. If the licensee cannot use its 
DTF for spent fuel management and site restoration activities, it 
would need to obtain additional funding that would not be 
recoverable from the DTF, or the licensee would have to modify its 
decommissioning approach and methods. The NRC staff concludes that 
either outcome would impose an unnecessary and undue burden 
significantly in excess of that contemplated when 10 CFR 
50.82(a)(8)(i)(A) was adopted.
    The underlying purposes of 10 CFR 50.82(a)(8)(i)(A) would be 
achieved by allowing Holtec Pilgrim and HDI to use a portion of the 
Pilgrim DTF for spent fuel management and site restoration 
activities, and compliance with the regulation would result in an 
undue hardship or other costs that are significantly in excess of 
those contemplated when the regulations were adopted. Thus, the 
special circumstances required by 10 CFR 50.12(a)(2)(ii) and 10 CFR 
50.12(a)(2)(iii) exist and support the approval of the requested 
exemption.

E. Environmental Considerations

    In accordance with 10 CFR 51.31(a), the Commission has 
determined that the granting of the exemption will not have a 
significant effect on the quality of the human environment (see 
Environmental Assessment and Finding of No Significant Impact 
published in the Federal Register on August 20, 2019 (84 FR 43186).

IV. Conclusions

    In consideration of the above, the NRC staff finds that the 
proposed exemption confirms the adequacy of funding in the Pilgrim 
DTF to complete radiological decommissioning of the site and to 
terminate the license and also to cover estimated spent fuel 
management and site restoration activities. The NRC staff also finds 
that there is reasonable assurance that adequate funds are available 
in the DTF to complete all activities associated with radiological 
decommissioning.
    Accordingly, the Commission has determined that, pursuant to 10 
CFR 50.12(a), the exemption is authorized by law, will not present 
an undue risk to the public health and safety, and is consistent 
with the common defense and security. Also, special circumstances 
are present. Therefore, the Commission hereby grants Holtec Pilgrim 
and HDI an exemption from 10 CFR 50.82(a)(8)(i)(A) to allow them to 
use of a portion of the funds from the Pilgrim DTF for spent fuel 
management and site restoration activities consistent with the 
revised PSDAR and site-specific DCE dated November 16, 2018.
    These exemptions are effective upon the NRC's issuance of a 
conforming license amendment reflecting HDI and Holtec Pilgrim as 
the licensees for Pilgrim, following NRC approval of the license 
transfer application and the Applicants' completion of the 
transaction.


[[Page 45182]]


    Dated at Rockville, Maryland, this 22nd day of August, 2019.

    For the Nuclear Regulatory Commission.

/RA/

Gregory F. Suber,
Deputy Director, Division of Operating Reactor Licensing, Office of 
Nuclear Reactor Regulation.

[FR Doc. 2019-18490 Filed 8-27-19; 8:45 am]
 BILLING CODE 7590-01-P