NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-277 and 50-278; NRC-2018-0130]


Exelon Generation Company, LLC; Peach Bottom Atomic Power 
Station, Units 2 and 3

AGENCY: Nuclear Regulatory Commission.

ACTION: Draft supplemental environmental impact statement; public 
meeting and request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing for 
public comment draft plant-specific Supplement 10, Second Renewal, to 
the Generic Environmental Impact Statement (GEIS) for License Renewal 
of Nuclear Plants, NUREG-1437, regarding the subsequent renewal of 
Facility Operating License Nos. DPR-44 and DPR-56 for an additional 20 
years of operation for Peach Bottom Atomic Power Station, Units 2 and 3 
(Peach Bottom). The Peach Bottom facility is located in York County, 
Pennsylvania. Possible alternatives to the proposed action (subsequent 
license renewal) include no action and reasonable replacement power 
alternatives. The NRC staff will hold a public meeting to present an 
overview of the draft plant-specific supplement to the GEIS and to 
accept public comment on the document.

DATES: The public meeting will be held on September 12, 2019, from 6:00 
p.m. to 8:00 p.m. at the Peach Bottom Inn, 6085 Delta Road, Delta, PA 
17314. Submit either electronic or written comments by September 23, 
2019. Comments received after this date will be considered, if it is 
practical to do so, but the NRC is able to ensure consideration only 
for comments received on or before this date.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov/ and search for Docket ID NRC-2018-0130. Address 
questions about NRC docket IDs to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER

[[Page 38677]]

INFORMATION CONTACT section of this document.
     Mail comments to: Office of Administration, Mail Stop: 
TWFN-7-A60M, ATTN: Program Management, Announcements and Editing Staff, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: David Drucker, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-6223; email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2018-0130 when contacting the NRC 
about the availability of information regarding this document. You may 
obtain publicly-available information related to this document by any 
of the following methods:
     Federal Rulemaking Website: Go to https://www.regulations.gov/ and search for Docket ID NRC-2018-0130.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may access publicly-available documents online in the 
ADAMS Public Documents collection at https://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``Begin Web-based ADAMS 
Search.'' For problems with ADAMS, please contact the NRC's Public 
Document Room (PDR) reference staff at 1-800-397-4209, 301-415-4737, or 
by email to [email protected]. The ADAMS accession number for each 
document referenced in this document (if that document is available in 
ADAMS) is provided the first time that the document is referenced here. 
Draft plant-specific Supplement 10, Second Renewal, to the GEIS for 
License Renewal of Nuclear Plants, NUREG-1437, is available in ADAMS 
under Accession No. ML19210D453.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.
     Library: A copy of draft plant-specific Supplement 10, 
Second Renewal, to the GEIS for License Renewal of Nuclear Plants, 
NUREG-1437, is available at the following location: Hartford County 
Public Library, Whiteford Branch, 2407 Whiteford Road, Whiteford, MD 
21160.

B. Submitting Comments

    Please include Docket ID NRC-2018-0130 in the subject line of your 
comment submission, in order to ensure that the NRC is able to make 
your comment submission available to the public in this docket.
    The NRC cautions you not to include identifying or contact 
information in comment submissions that you do not want to be publicly 
disclosed. The NRC will post all comment submissions at https://www.regulations.gov/ as well as enter the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment into ADAMS.

II. Discussion

    The NRC is issuing for public comment draft plant-specific 
Supplement 10, Second Renewal, to the GEIS for License Renewal of 
Nuclear Plants, NUREG-1437, regarding the subsequent renewal of 
Facility Operating License Nos. DPR-44 and DPR-56 for an additional 20 
years of operation for Peach Bottom Units 2 and 3. Draft plant-specific 
Supplement 10, Second Renewal, to the GEIS includes the preliminary 
analysis that evaluates the environmental impacts of the proposed 
action and alternatives to the proposed action. The NRC's preliminary 
recommendation is that the adverse environmental impacts of subsequent 
license renewal for Peach Bottom are not so great that preserving the 
option of subsequent license renewal for energy-planning decisionmakers 
would be unreasonable.

III. Public Meeting

    The NRC staff will hold a public meeting prior to the close of the 
public comment period to present an overview of the draft plant-
specific supplement to the GEIS and to accept public comment on the 
document. The meeting will be held on September 12, 2019, from 6:00 
p.m. to 8:00 p.m. at the Peach Bottom Inn, 6085 Delta Road, Delta, PA 
17314. There will be an open house one hour before the meeting for 
members of the public to meet with NRC staff members and sign in to 
speak. The meeting will be transcribed and will include: (1) A 
presentation of the contents of the draft plant-specific supplement to 
the GEIS and (2) the opportunity for interested government agencies, 
organizations, and individuals to provide comments on the draft plant-
specific supplement to the GEIS. To be considered in the final 
supplement to the GEIS, comments must be provided either at the 
transcribed public meeting or submitted in writing by the comment 
deadline identified above. Persons may pre-register to attend or 
present oral comments at the meeting by contacting Mr. David Drucker, 
the NRC Project Manager, at 301-415-6223, or by email at 
[email protected] no later than Thursday, August 29, 2019. Members 
of the public may also register to provide oral comments within 15 
minutes before the start of the meeting. Individual oral comments may 
be limited by the time available, depending on the number of persons 
who register. If special equipment or accommodations are needed to 
attend or present information at the public meeting, the need should be 
brought to Mr. Drucker's attention no later than Thursday, August 29, 
2019, to provide the NRC staff adequate notice to determine whether the 
request can be accommodated.

    Dated at Rockville, Maryland, this 1st day of August, 2019.

    For the Nuclear Regulatory Commission.
Eric R. Oesterle,
Chief, License Renewal Projects Branch, Division of Materials and 
License Renewal, Office of Nuclear Reactor Regulation.
[FR Doc. 2019-16794 Filed 8-6-19; 8:45 am]