[Federal Register Volume 84, Number 137 (Wednesday, July 17, 2019)]
[Notices]
[Page 34174]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-15177]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Combined Notice of Filings #1

    Take notice that the Commission received the following exempt 
wholesale generator filings:

    Docket Numbers: EG19-148-000.
    Applicants: Grazing Yak Solar, LLC.
    Description: Notice of Self-Certification of Exempt Wholesale 
Generator Status of Grazing Yak Solar, LLC.
    Filed Date: 7/10/19.
    Accession Number: 20190710-5127.
    Comments Due: 5 p.m. ET 7/31/19.

    Docket Numbers: EG19-149-000.
    Applicants: Caden Energix Hickory LLC.
    Description: Self-Certification of EG or FC of Caden Energix 
Hickory LLC.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5099.
    Comments Due: 5 p.m. ET 8/1/19.

    Take notice that the Commission received the following electric 
rate filings:

    Docket Numbers: ER19-1900-001.
    Applicants: Golden Spread Electric Cooperative, Inc.
    Description: Compliance filing: ER19-1900 Deficiency Letter 
Response to be effective 5/20/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5057.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-1902-001.
    Applicants: Deseret Generation & Transmission Co-operative, Inc.
    Description: Compliance filing: ER19-1902 Deficiency Letter 
Response to be effective 5/20/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5019.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-1943-001.
    Applicants: NorthWestern Corporation.
    Description: Compliance filing: Response to Deficiency Letter re 
Order No. 845/845-A Compliance Filing to be effective 5/22/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5072.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2376-000.
    Applicants: Deseret Generation & Transmission Co-operative, Inc.
    Description: Compliance filing: OATT Order No. 845 Compliance--
Deficiency Response to be effective 5/20/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5015.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2377-000.
    Applicants: Midcontinent Independent System Operator, Inc., 
Michigan Electric Transmission Company.
    Description: Sec.  205(d) Rate Filing: 2019-07-11_SA 3330 Assembly 
Solar LLC-METC E&P (J796) to be effective 9/10/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5047.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2378-000.
    Applicants: Sterlington Power LLC.
    Description: Compliance filing: Notice of Succession, Baseline Re-
file, and Request for Admin Cancellation to be effective 5/15/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5049.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2379-000.
    Applicants: Duke Energy Progress, LLC.
    Description: Sec.  205(d) Rate Filing: DEP-DEC ASOA (Asheville CC) 
Concurrence Filing (DEP SA No. 362) to be effective 6/19/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5056.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2380-000.
    Applicants: Midcontinent Independent System Operator, Inc.
    Description: Sec.  205(d) Rate Filing: 2019-07-11_SA 3228 
Interstate Power and Light Co-ITC Midwest 1st Rev GIA (J495) to be 
effective 6/26/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5074.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2381-000.
    Applicants: PJM Interconnection, L.L.C.
    Description: Sec.  205(d) Rate Filing: Amendment to ISA, SA No. 
2053, NQ121 (amend) to be effective 6/2/2015.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5078.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2382-000.
    Applicants: Story County Wind, LLC.
    Description: Baseline eTariff Filing: Story County Wind, LLC 
Application for Market-Based Rate Authority to be effective 9/10/2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5081.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2383-000.
    Applicants: AEP Texas Inc.
    Description: Sec.  205(d) Rate Filing: AEPTX-Karankawa Wind I 
Interconnection Agreement First Amend & Restated to be effective 6/20/
2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5082.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2384-000.
    Applicants: AEP Texas Inc.
    Description: Sec.  205(d) Rate Filing: AEPTX-La Chalupa 
Interconnection Agreement First Amend & Restated to be effective 6/25/
2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5083.
    Comments Due: 5 p.m. ET 8/1/19.

    Docket Numbers: ER19-2385-000.
    Applicants: AEP Texas Inc.
    Description: Sec.  205(d) Rate Filing: AEPTX-Karankawa Wind II 
Interconnection Agreement First Amend & Restated to be effective 6/27/
2019.
    Filed Date: 7/11/19.
    Accession Number: 20190711-5084.
    Comments Due: 5 p.m. ET 8/1/19.

    The filings are accessible in the Commission's eLibrary system by 
clicking on the links or querying the docket number.
    Any person desiring to intervene or protest in any of the above 
proceedings must file in accordance with Rules 211 and 214 of the 
Commission's Regulations (18 CFR 385.211 and 385.214) on or before 5:00 
p.m. Eastern time on the specified comment date. Protests may be 
considered, but intervention is necessary to become a party to the 
proceeding.
    eFiling is encouraged. More detailed information relating to filing 
requirements, interventions, protests, service, and qualifying 
facilities filings can be found at: http://www.ferc.gov/docs-filing/efiling/filing-req.pdf. For other information, call (866) 208-3676 
(toll free). For TTY, call (202) 502-8659.

    Dated: July 11, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-15177 Filed 7-16-19; 8:45 am]
BILLING CODE 6717-01-P