[Federal Register Volume 84, Number 100 (Thursday, May 23, 2019)]
[Rules and Regulations]
[Pages 23727-23728]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-10766]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

40 CFR Part 63


National Emission Standards for Hazardous Air Pollutants for 
Source Categories

CFR Correction

    In Title 40 of the Code of Federal Regulations, Part 63, 63.8980 to 
end of part 63, revised as of July 1, 2018, make the following 
corrections in Subpart UUUUU:

0
1. On page 188, in Sec.  63.10021, paragraph (e)(9) is revised to read 
as follows:


Sec.  63.10021   How do I demonstrate continuous compliance with the 
emission limitations, operating limits, and work practice standards?

* * * * *
    (e) * * *
    (9) Report the dates of the initial and subsequent tune-ups in hard 
copy, as specified in Sec.  63.10031(f)(5), through June 30, 2020. On 
or after July 1, 2020, report the date of all tune-ups electronically, 
in accordance with Sec.  63.10031(f). The tune-up report date is the 
date when tune-up requirements in paragraphs (e)(6) and (7) of this 
section are completed.
* * * * *

0
2. On page 195, in Sec.  63.10031, paragraphs (f) introductory text, 
(f)(1), (2), (4), and (f)(6) introductory text are revised to read as 
follows:


Sec.  63.10031  What reports must I submit and when?

* * * * *
    (f) On or after July 1, 2020, within 60 days after the date of 
completing each performance test, you must submit the performance test 
reports required by this subpart to the EPA's WebFIRE database by using 
the Compliance and Emissions Data Reporting Interface (CEDRI) that is 
accessed through the EPA's Central Data Exchange (CDX) (https://cdx.epa.gov). Performance test data must be submitted in the file 
format generated through use of EPA's Electronic Reporting Tool (ERT) 
(see https://www.epa.gov/ttn/chief/ert/index.html). Only data collected 
using those test methods on the ERT website are subject to this 
requirement for submitting reports electronically to WebFIRE. Owners or 
operators who claim that some of the information being submitted for 
performance tests is confidential business information (CBI) must 
submit a complete ERT file including information claimed to be CBI on a 
compact disk or other commonly used electronic storage media 
(including, but not limited to, flash drives) to EPA. The electronic 
media must be clearly marked as CBI and mailed to U.S. EPA/OAPQS/CORE 
CBI Office, Attention: WebFIRE Administrator, MD C404-02, 4930 Old Page 
Rd., Durham, NC 27703. The same ERT file with the CBI omitted must be 
submitted to EPA via CDX as described earlier in this paragraph. At the 
discretion of the delegated authority, you must also submit these 
reports, including the confidential business information, to the 
delegated authority in the format specified by the delegated authority.
    (1) On or after July 1, 2020, within 60 days after the date of 
completing each CEMS (SO2, PM, HCl, HF, and Hg) performance 
evaluation test, as defined in Sec.  63.2 and required by this subpart, 
you must submit the relative accuracy test audit (RATA) data (or, for 
PM CEMS, RCA and RRA data) required by this subpart to EPA's WebFIRE 
database by using CEDRI that is accessed through EPA's CDX (https://cdx.epa.gov). The RATA data shall be submitted in the file format 
generated through use of EPA's Electronic Reporting Tool (ERT) (https://www.epa.gov/ttn/chief/ert/index.html). Only RATA data compounds listed 
on the ERT website are subject to this requirement. Owners or operators 
who claim that some of the information being submitted for RATAs is 
confidential business information (CBI) shall submit a complete ERT 
file including information claimed to be CBI on a compact disk or other 
commonly used electronic storage media (including, but not limited to, 
flash drives) by registered letter to EPA and the same ERT file with 
the CBI omitted to EPA via CDX as described earlier in this paragraph. 
The compact disk or other commonly used electronic storage media shall 
be clearly marked as CBI and mailed to U.S. EPA/OAPQS/CORE CBI Office, 
Attention: WebFIRE Administrator, MD C404-02, 4930 Old Page Rd., 
Durham, NC 27703. At the discretion of the delegated authority, owners 
or operators shall also submit these RATAs to the delegated authority 
in the format specified by the delegated authority. Owners or operators 
shall submit calibration error testing, drift checks, and other 
information required in the performance evaluation as described in 
Sec.  63.2 and as required in this chapter.
    (2) On or after July 1, 2020, for a PM CEMS, PM CPMS, or approved 
alternative monitoring using a HAP metals CEMS, within 60 days after 
the reporting periods ending on March 31st, June 30th, September 30th, 
and December 31st, you must submit quarterly reports to the EPA's 
WebFIRE database by using the CEDRI that is accessed through the EPA's 
CDX (https://cdx.epa.gov). You must use the appropriate electronic 
reporting form in CEDRI or provide an alternate electronic file 
consistent with EPA's reporting form output format. For each reporting 
period, the quarterly reports must include all of the calculated 30-
boiler operating day rolling average values derived from the CEMS and 
PM CPMS.
* * * * *
    (4) On or after July 1, 2020, submit the compliance reports 
required under paragraphs (c) and (d) of this section and the 
notification of compliance status required under Sec.  63.10030(e) to 
the EPA's WebFIRE database by using the CEDRI that is accessed through 
the EPA's CDX (https://cdx.epa.gov). You must use the appropriate 
electronic reporting form in CEDRI or provide an alternate electronic 
file consistent with EPA's reporting form output format.
* * * * *
    (6) Prior to July 1, 2020, all reports subject to electronic 
submittal in paragraphs (f) introductory text, (f)(1), (2), and (4) of 
this section shall be submitted to the EPA at the frequency specified 
in those paragraphs in electronic portable document format (PDF) using 
the ECMPS Client Tool. Each PDF version of a submitted report must 
include sufficient information to

[[Page 23728]]

assess compliance and to demonstrate that the testing was done 
properly. The following data elements must be entered into the ECMPS 
Client Tool at the time of submission of each PDF file:
* * * * *
[FR Doc. 2019-10766 Filed 5-22-19; 8:45 am]