Mississippi Hub, LLC; Notice of Application

    Take notice that on April 22, 2019, Mississippi Hub, LLC (MS Hub), 
10375 Richmond Ave., Suite 1900, Houston, TX 77042, filed in Docket No. 
CP19-198-000, an application pursuant to section 7(c) of the Natural 
Gas Act and Part 157 of the Commission's regulations to continue to 
own, operate and maintain an existing 4,735 horsepower gas-driven 
compressor unit at MS Hub's existing storage terminal in Simpson 
County, Mississippi. The applicant states that ArcLight Energy Partners 
Fund VI, L.P. (ArcLight) acquired all of the ownership interests in MS 
Hub from Sempra Energy after which a post-acquisition regulatory audit 
was conducted. The applicant states that the Certificate authorization 
for Gas Compressor 4, which the applicant claims was placed in service 
in 2012 and continues to operate, may have been inadvertently vacated 
by the prior owner, all as more fully set forth in the application, 
which is on file with the Commission and open to public inspection. The 
filing may also be viewed on the web at http://www.ferc.gov using the 
eLibrary link. Enter the docket number excluding the last three digits 
in the docket number field to access the document. For assistance, 
contact FERC at [email protected] or call toll-free, (866) 
208-3676 or TTY, (202) 502-8659.
    Any questions regarding this application should be directed to Todd 
Cash, Enstor Gas, LLC, 10375 Richmond Ave., Suite 1900, Houston, TX 
77042, (281) 374-3085, [email protected] or Lisa M. Tonery, 
Orrick, Herrington & Sutcliffe LLP, 51 West 52nd Street, New York, N.Y. 
10019, (212) 506-3710, [email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 3 copies of filings made with the Commission and must provide a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list and will be 
notified of any meetings associated with the Commission's environmental 
review process. Environmental commentors will not be required to serve 
copies of filed documents on all other parties. However, the non-party 
commentors will not receive copies of all documents filed by other 
parties or issued by the Commission and will not have the right to seek 
court review of the Commission's final order.
    As of the February 27, 2018 date of the Commission's order in 
Docket No. CP16-4-001, the Commission will apply its revised practice 
concerning out-of-time motions to intervene in any new Natural Gas Act 
section 3 or section 7 proceeding.\1\ Persons desiring to become a 
party to a certificate proceeding are to intervene in a timely manner. 
If seeking to intervene out-of-time, the movant is required to ``show 
good cause why the time limitation should be waived, and should provide 
justification by reference to factors set forth in Rule 214(d)(1) of 
the Commission's Rules and Regulations.\2\
---------------------------------------------------------------------------

    \1\ Tennessee Gas Pipeline Company, L.L.C., 162 FERC 61,167 at 
50 (2018).
    \2\ 18 CFR 385.214(d)(1).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically

[[Page 18842]]

should submit an original and 3 copies of the protest or intervention 
to the Federal Energy regulatory Commission, 888 First Street NE, 
Washington, DC 20426.
    Comment Date: May 17, 2019.

    Dated: April 26, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-08905 Filed 5-1-19; 8:45 am]