[Federal Register Volume 84, Number 83 (Tuesday, April 30, 2019)]
[Notices]
[Pages 18323-18324]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-08720]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-025 and 52-026; NRC-2008-0252]


Southern Nuclear Operating Company, Inc.; Vogtle Electric 
Generating Plant, Units 3 and 4; Administrative Changes To Align 
Initial Test Program With Regulatory Guide 1.68

AGENCY: Nuclear Regulatory Commission.

ACTION: Exemption and combined license amendment; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is granting an 
exemption to allow a departure from the certification information of 
Tier 1 of the generic design control document (DCD) and is issuing 
License Amendment No. 154 for Unit 3 and No. 153 for Unit 4 to Combined 
Licenses (COLs), NPF-91 and NPF-92. The COLs were issued to Southern 
Nuclear Operating Company, Inc., and Georgia Power Company, Oglethorpe 
Power Corporation, MEAG Power SPVM, LLC, MEAG Power SPVJ, LLC, MEAG 
Power SPVP, LLC, and the City of Dalton, Georgia (collectively SNC); 
for construction and operation of the Vogtle Electric Generating Plant 
(VEGP) Units 3 and 4, located in Burke County, Georgia.
    The granting of the exemption allows the changes to Tier 1 
information asked for in the amendment. Because the acceptability of 
the exemption was determined in part by the acceptability of the 
amendment, the exemption and amendment are being issued concurrently.

DATES: The exemption and amendment were issued on February 22, 2019.

ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address 
questions about NRC dockets in Regulations.gov to Jennifer Borges; 
telephone: 301-287-9127; email: [email protected]. For technical 
questions, contact the individual listed in the FOR FURTHER INFORMATION 
CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it is available 
in ADAMS) is provided the first time that it is mentioned in this 
document. The request for the amendment and exemption was submitted by 
letter dated August 30, 2018, and available in ADAMS under Accession 
No. ML18242A039.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Billy Gleaves, Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; 
telephone: 301-415-5848; email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Introduction

    The NRC is granting an exemption from paragraph B of section III, 
``Scope and Contents,'' of appendix D, ``Design Certification Rule for 
the AP1000,'' to part 52 of title 10 of the Code of Federal Regulations 
(10 CFR), and issuing License Amendment Nos. 154 and 153 to COLs, NPF-
91 and NPF-92, to SNC. The exemption is required by paragraph A.4 of 
Section VIII, ``Processes for Changes and Departures,'' appendix D, to 
10 CFR part 52 to allow SNC to depart from Tier 1 information. With the 
requested amendment, SNC sought proposed changes in the form of 
departures from the generic AP1000 DCD Tier 1 and Tier 2 information in 
the VEGP COL plant-specific Tier 1 plant-specific DCD (PS-DCD) and the 
Tier 2 Updated Final Safety Analysis Report (UFSAR) to reflect revision 
of the description and scope of the Initial Test Program (ITP) to 
remove component testing as a separately identified program or phase of 
the ITP. Additionally, preoperational and startup test specifications 
were proposed to be removed from the ITP. The amendment also proposed 
corresponding changes to the COL license conditions that referenced 
UFSAR sections impacted by the changes. The changes align plant-
specific Tier 1, Section 3.4 descriptions for ITP with Regulatory Guide 
(RG) 1.68, ``Initial Test Programs for Water-Cooled Nuclear Power 
Plants,'' Revision 3. These changes involve a revision to Section 
2.D(10) and 2.D(12) of the COL conditions for VEGP Units 3 and 4 and, 
UFSAR Table 13.4-201 and Section 14.2.
    Part of the justification for granting the exemption was provided 
by the review of the amendment. Because the exemption is necessary in 
order to issue the requested license amendment, the NRC granted the 
exemption and issued the amendment concurrently, rather than in 
sequence. This included issuing a combined safety evaluation containing 
the NRC staff's review of both the exemption request and the license 
amendment. The exemption met all applicable regulatory criteria set 
forth in Sec. Sec.  50.12, 52.7, and section VIII.A.4 of appendix D to 
10 CFR part 52. The license amendment was found to be acceptable as 
well. The combined safety evaluation is available in ADAMS under 
Accession No. ML19035A763.
    Identical exemption documents (except for referenced unit numbers 
and license numbers) were issued to SNC for VEGP Units 3 and 4 (COLs 
NPF-91 and NPF-92). The exemption documents for VEGP Units 3 and 4 can 
be found in ADAMS under Accession Nos. ML19035A761 and ML19035A762, 
respectively. The exemption is reproduced (with the exception of 
abbreviated titles and additional citations) in Section II of this 
document. The amendment documents for COLs NPF-91 and NPF-92 are 
available in ADAMS under Accession Nos.

[[Page 18324]]

ML19035A757 and ML19035A759, respectively. A summary of the amendment 
documents is provided in Section III of this document.

II. Exemption

    Reproduced below is the exemption document issued to VEGP Units 3 
and Unit 4. It makes reference to the combined safety evaluation that 
provides the reasoning for the findings made by the NRC (and listed 
under Item 1) in order to grant the exemption:
    1. In an application dated August 30, 2018, SNC requested from the 
Commission an exemption to allow departures from Tier 1 information in 
the certified DCD incorporated by reference in 10 CFR part 52, appendix 
D, as part of license amendment request 18-024, ``Administrative 
Changes to Align Initial Test Program with Regulatory Guide 1.68.''
    For the reasons set forth in Section 3.1 of the NRC staff's Safety 
Evaluation, which can be found in ADAMS under Accession No. 
ML19035A763, the Commission finds that:
    A. The exemption is authorized by law;
    B. the exemption presents no undue risk to public health and 
safety;
    C. the exemption is consistent with the common defense and 
security;
    D. special circumstances are present in that the application of the 
rule in this circumstance is not necessary to serve the underlying 
purpose of the rule;
    E. the special circumstances outweigh any decrease in safety that 
may result from the reduction in standardization caused by the 
exemption; and
    F. the exemption will not result in a significant decrease in the 
level of safety otherwise provided by the design.
    2. Accordingly, the licensee is granted an exemption from the 
certified DCD Tier 1 information, with corresponding information in COL 
Appendix C of the Facility Combined License as described in the 
licensee's request dated August 30, 2018 This exemption is related to, 
and necessary for the granting of License Amendment No. 154 [for Unit 3 
and No. 153 for Unit 4] which is being issued concurrently with this 
exemption.
    3. As explained in Section 5.0 of the NRC staff's Safety Evaluation 
(ADAMS Accession No. ML19035A763), this exemption meets the eligibility 
criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9). 
Therefore, pursuant to 10 CFR 51.22(b), no environmental impact 
statement or environmental assessment needs to be prepared in 
connection with the issuance of the exemption.
    4. This exemption is effective as of the date of its issuance.

III. License Amendment Request

    By letter dated August 30, 2018, (ADAMS Accession Nos. 
ML18242A039), SNC requested that the NRC amend the COLs for VEGP, Units 
3 and 4, COLs NPF-91 and NPF-92. The proposed amendment is described in 
Section I of this Federal Register notice.
    The Commission has determined for these amendments that the 
application complies with the standards and requirements of the Atomic 
Energy Act of 1954, as amended (the Act), and the Commission's rules 
and regulations. The Commission has made appropriate findings as 
required by the Act and the Commission's rules and regulations in 10 
CFR Chapter I, which are set forth in the license amendment.
    A notice of consideration of issuance of amendment to facility 
operating license or COL, as applicable, proposed no significant 
hazards consideration determination, and opportunity for a hearing in 
connection with these actions, was published in the Federal Register on 
September 19, 2018 (83 FR 47372). No comments were received during the 
30-day comment period.
    The Commission has determined that these amendments satisfy the 
criteria for categorical exclusion in accordance with 10 CFR 51.22. 
Therefore, pursuant to 10 CFR 51.22(b), no environmental impact 
statement or environmental assessment need be prepared for these 
amendments.

IV. Conclusion

    Using the reasons set forth in the combined safety evaluation, the 
staff granted the exemption and issued the amendment that SNC requested 
on August 30, 2018.
    The exemption and amendment were issued to SNC on February 22, 
2019, as part of a combined package (ADAMS Accession No. ML19035A755).

    Dated at Rockville, Maryland, this 25th day of April 2019.

    For the Nuclear Regulatory Commission.
Jennifer L. Dixon-Herrity,
Chief, Licensing Branch 2, Division of Licensing, Siting, and 
Environmental Analysis, Office of New Reactors.
[FR Doc. 2019-08720 Filed 4-29-19; 8:45 am]