ENVIRONMENTAL PROTECTION AGENCY
[Petitions IV-2014-13; FRL-9992-57-Region 4]
Clean Air Act Operating Permit Program; Petition for Objection to
State Operating Permit for Piedmont Natural Gas--Wadesboro Compressor
Station (Anson County, North Carolina)
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice of final order on petitions to object to state operating
permits.
-----------------------------------------------------------------------
SUMMARY: The EPA Administrator signed an Order, dated March 20, 2019,
denying the petition submitted by Pee Dee Water Air Land and Lives and
the Blue Ridge Environmental Defense League (Petitioners) objecting to
a proposed Clean Air Act (CAA) title V operating permit issued to
Piedmont Natural Gas (PNG) for its facility located in Wadesboro, Anson
County, North Carolina. The Order responds to an October 3, 2014,
petition requesting that EPA object to the proposed initial permit
number 10097T01. This permitting action was issued by the North
Carolina Department of Environment and Natural Resources (NCDENR). The
Order constitutes a final action on the petition addressed therein.
ADDRESSES: Copies of the Order, the petition, and all pertinent
information relating thereto are on file at the following location: EPA
Region 4; Air, Pesticides and Toxics Management Division; 61 Forsyth
Street SW, Atlanta, Georgia 30303-8960. The Order is also available
electronically at the following address: https://www.epa.gov/title-v-operating-permits/2019-order-denying-petition-object-title-v-operating-permit-png-wadesboro.
FOR FURTHER INFORMATION CONTACT: Art Hofmeister, Air Permitting
Section, EPA Region 4, at (404) 562-9115 or [email protected].
SUPPLEMENTARY INFORMATION: The CAA affords EPA a 45-day period to
review
[[Page 16852]]
and, as appropriate, the authority to object to operating permits
proposed by state permitting authorities under title V of the CAA, 42
U.S.C. 7661-7661f. Section 505(b)(2) of the CAA and 40 CFR 70.8(d)
authorize any person to petition the EPA Administrator to object to a
title V operating permit within 60 days after the expiration of EPA's
45-day review period if EPA has not objected on its own initiative.
Petitions must be based only on objections to the permit that were
raised with reasonable specificity during the public comment period
provided by the state, unless the petitioner demonstrates that it was
impracticable to raise these issues during the comment period or the
grounds for the issues arose after this period. Pursuant to sections
307(b) and 505(b)(2) of the CAA, a petition for judicial review of
those parts of the Order that deny issues in the petition may be filed
in the United States Court of Appeals for the appropriate circuit
within 60 days from the date this notice is published in the Federal
Register.
Petitioners submitted a petition requesting that EPA object to the
proposed CAA title V operating permit no. 10097T01 issued by NCDENR to
PNG. Petitioners claim that this permitting action: Failed to meet the
requirements for adequate public notice; grossly underestimates
emissions and, thus, fails to assure compliance with national ambient
air quality standards and state implementation standards; fails to
include adequate monitoring to assure compliance with applicable
opacity standards; and failed to include an environmental justice
analysis.
On March 20, 2019, the Administrator issued an Order denying the
petition. The Order explains EPA's basis for denying the petition.
Dated: April 11, 2019.
Mary S. Walker,
Acting Regional Administrator, Region 4.
[FR Doc. 2019-08160 Filed 4-22-19; 8:45 am]
BILLING CODE 6560-50-P