[Federal Register Volume 84, Number 37 (Monday, February 25, 2019)]
[Notices]
[Pages 6002-6003]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2019-03146]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2622-013]


Turners Falls Hydro, LLC; Notice of Application Tendered for 
Filing With the Commission and Soliciting Additional Study Requests and 
Establishing Procedural Schedule for Relicensing and a Deadline for 
Submission of Final Amendments

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent Minor License.
    b. Project No.: 2622-013.
    c. Date filed: February 4, 2019.
    d. Applicant: Turners Falls Hydro, LLC (Turners Falls Hydro).
    e. Name of Project: Turners Falls Project.
    f. Location: On the Connecticut River, in the power canal of the 
Turners Falls Hydroelectric Project No. 1889, in Franklin County, 
Massachusetts. No federal lands are occupied by the project works or 
located within the project boundary.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)-825(r).
    h. Applicant Contact: Mr. Michael Scarzello, Director, Eagle Creek 
Renewable Energy, LLC, 65 Madison Avenue, Suite 500, Morristown, NJ 
07960; Phone at (973) 998-8400, or email at 
[email protected].
    i. FERC Contact: Amanda Gill, (202) 502-6773 or 
[email protected].
    j. Cooperating agencies: Federal, state, local, and tribal agencies 
with jurisdiction and/or special expertise with respect to 
environmental issues that wish to cooperate in the preparation of the 
environmental document should follow the instructions for filing such 
requests described in item l below. Cooperating agencies should note 
the Commission's policy that agencies that cooperate in the preparation 
of the environmental document cannot also intervene. See 94 FERC 61,076 
(2001).
    k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's 
regulations, if any resource agency, Indian Tribe, or person believes 
that an additional scientific study should be conducted in order to 
form an adequate factual basis for a complete analysis of the 
application on its merit, the resource agency, Indian Tribe, or person 
must file a request for a study with the Commission not later than 60 
days from the date of filing of the application, and

[[Page 6003]]

serve a copy of the request on the applicant.
    l. Deadline for filing additional study requests and requests for 
cooperating agency status: April 5, 2019.
    The Commission strongly encourages electronic filing. Please file 
additional study requests and requests for cooperating agency status 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support 
at [email protected], (866) 208-3676 (toll free), or (202) 
502-8659 (TTY). In lieu of electronic filing, please send a paper copy 
to: Secretary, Federal Energy Regulatory Commission, 888 First Street 
NE, Washington, DC 20426. The first page of any filing should include 
docket number P-2622-013.
    m. The application is not ready for environmental analysis at this 
time.
    n. Project Description: The Turners Falls Project consists of: (1) 
An existing 10-foot-long, 20-foot-wide, 12- to 22-foot-high forebay; 
(2) a 20-foot-wide, 22-foot-high trashrack with 1.5-inch clear-bar 
spacing; (3) two headgates; (4) an 8.5-foot-diameter, 50-foot-long 
steel penstock; (5) a 3,847-square foot powerhouse containing one 937-
kilowatt vertical Francis-type turbine-generator unit; (6) a 50-foot-
long, underground flume; (7) an 80-foot-long, 10-foot-wide tailrace; 
(8) a 1,000-foot-long, 13.8-kilovolt transmission line; (9) and 
appurtenant facilities.
    When generating, the project withdraws up to 289 cubic feet per 
second from FirstLight Hydro Generating Company's power canal for the 
Turners Falls Hydroelectric Project No. 1889, and discharges directly 
into the Connecticut River. Turners Falls Hydro operates the project in 
a run-of-river mode with an average annual generation of approximately 
1,512 megawatt-hours. Turners Falls Hydro proposes to continue 
operating the project in a run-of-river mode and does not propose any 
new construction or modifications to the project.
    o. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's website at http://www.ferc.gov using the eLibrary link. 
Enter the docket number excluding the last three digits in the docket 
number field to access the document. For assistance, contact FERC 
Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    p. Procedural schedule and final amendments: The application will 
be processed according to the following preliminary schedule. Revisions 
to the schedule will be made as appropriate.

Issue Deficiency Letter (if necessary)--April 2019
Request Additional Information--April 2019
Issue Acceptance Letter--July 2019
Issue Scoping Document 1 for Comments--August 2019
Request Additional Information (if necessary)--September 2019
Issue Scoping Document 2--October 2019
Issue Notice of Ready for Environmental Analysis--October 2019
Issue Notice of Availability of Environmental Assessment--May 2020

    Final amendments to the application must be filed with the 
Commission no later than 30 days from the issuance date of the notice 
of ready for environmental analysis.

    Dated: February 15, 2019.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2019-03146 Filed 2-22-19; 8:45 am]
 BILLING CODE 6717-01-P