[Federal Register Volume 83, Number 248 (Friday, December 28, 2018)]
[Notices]
[Page 67278]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2018-28255]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL19-24-000]


Exelon Generation Company, LLC; Notice of Institution of Section 
206 Proceeding and Refund Effective Date

    On December 20, 2018, the Commission issued an order in Docket No. 
EL19-24-000, pursuant to section 206 of the Federal Power Act (FPA), 16 
U.S.C. 824e (2012), instituting an investigation into the continued 
justness and reasonableness of Exelon Generation Company, LLC's rate 
for providing Reactive Supply and Voltage Control Service. Exelon 
Generation Company, LLC, 165 FERC 61,245 (2018).
    The refund effective date in Docket No. EL19-24-000, established 
pursuant to section 206(b) of the FPA, will be the date of publication 
of this notice in the Federal Register.
    Any interested person desiring to be heard in Docket No. EL19-24-
000 must file a notice of intervention or motion to intervene, as 
appropriate, with the Federal Energy Regulatory Commission, 888 First 
Street NE, Washington, DC 20426, in accordance with Rule 214 of the 
Commission's Rules of Practice and Procedure, 18 CFR 385.214, within 21 
days of the date of issuance of the order.

    Dated: December 20, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-28255 Filed 12-27-18; 8:45 am]
BILLING CODE 6717-01-P